The ISIS 7-year business plan<br />

The following model of the Zoological Information Management System (ZIMS) development process<br />

was developed to serve as a projection for the project, not as a budget.<br />

Assumptions of the model:<br />

– Assuming continued membership growth, increases in ISIS membership fee revenue will be<br />

limited to inflation adjustments of not more than 5% per year.<br />

– We will fully develop the aquarium membership category.<br />

– We will be successful in our “friends and family” portion of our capital<br />

campaign (Goal: US $5 million).<br />

– We will seek new revenue opportunities.<br />

– We will gain increased revenue from government and foundation grants (although on a<br />

percentage basis these grants will account for less of the larger overall operating budget – from<br />

30% down to 20%).<br />

– The Animal Records Keeping System (ARKS), the Medical Animal Records Keeping<br />

System (MedARKS) and ISIS central database will be phased out in the next two years.<br />

– Most ISIS operating and ZIMS development expenses will not increase more than an average<br />

of five percent per year.<br />

– ISIS staff time on the ZIMS Project will be capitalized until ZIMS deployment.<br />

– All projections include US $2.2 million (over five years) in ISIS capital investment<br />

in the ZIMS Project. These numbers are shown in the financial model separately.<br />

Estimated costs<br />

The ZIMS vendor development cost will be US $3 million over a three-year period. We have agreed<br />

to pay the ZIMS vendor CGI over a 24-month period (May 2004-April 2006). Because ISIS member<br />

pledges have been promised over a seven-year period (2003-2009 – many members have made five<br />

year pledges starting in different years), we plan to use bridge loan financing of up to US $2 million.<br />

We will pay this loan as pledges are received.<br />

We have estimated the member-driven design and development process at US $2 million over a<br />

three-year period. This estimate includes costs of workshops and input gathering from members.<br />

This estimate does not include ISIS staff salaries (nor the valuable contributed time from the many<br />

hard-working volunteers).<br />

We have estimated hosting costs through the deployment phase at US $1.25 million; ISIS and<br />

community infrastructure improvement at US $1.25 million and global community training and<br />

deployment support at US $4.7 million. (These estimates also do not include ISIS staff time,<br />

which is capitalized in the model as part of the project cost.)<br />