Schedule<br />
� Track 1 pro<strong>to</strong>types in final<br />
integration<br />
� Completed pro<strong>to</strong>types available starting<br />
Dec 08<br />
� Total of 6-10 units planned<br />
� Track 2 production schedule:<br />
� Preliminary Design Review – Jan 2009<br />
� Critical Design Review – Apr 2009<br />
� First Pre-production Units available – 4thQ<br />
2010 (CY)<br />
� Completion of Qual & Certs – 3Q 2010<br />