a) Calculate the EOQ for the workbooks.<br />

b) What are the annual holding costs for the workbooks?<br />

c) What are the annual ordering costs?<br />

<strong>Chapter</strong> 12, <strong>problems</strong> 12.9<br />

Southeastern Bell stocks a certain switch connector at its central<br />

warehouse for supplying field service offices. The yearly demand<br />

for these connectors is 15,000 units. Southeastern estimates its<br />

annual holding cost for this item to be $25 per unit. The cost to<br />

place and process an order from the supplier is $75. The company<br />

operates 300 days per year, and the lead time to receive an order<br />

from the supplier is 2 working days.<br />

a) Find the economic order quantity.<br />

b) Find the annual holding costs.<br />

c) Find the annual ordering costs.<br />

d) What is the reorder point?<br />

<strong>Chapter</strong> 12, <strong>problems</strong> 12.15<br />

M. Cotteleer Electronics supplies microcomputer circuitry to a<br />

company that incorporates microprocessors into refrigerators and<br />

other home appliances. One of the components has an annual<br />

demand of 250 units, and this is constant throughout the year.<br />

Carrying cost is estimated to be $1 per unit per year, and the<br />

ordering cost is $20 per order.<br />

a) To minimize cost, how many units should be ordered each time<br />

an order is placed?<br />

b) How many orders per year are needed with the optimal policy?