29.02.2016 Views

Restored

dwr_mag_w16

dwr_mag_w16

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

Feature | San Clemente Dam Demolition<br />

Above: In the dewatered reservoir, excavators and<br />

trucks remove sediment in 2014 in preparation<br />

for the Diversion Dike constructed later that year<br />

to divert the Carmel River and retain reservoir<br />

sediment.<br />

Above: From July to August 2015, the 300-foot<br />

long, 106-foot tall San Clemente Dam in Monterey<br />

County was removed in four weeks using excavators<br />

equipped with hydraulic hammers.<br />

Left: DSOD's Engineer Kristen Martin inspects the<br />

project.<br />

“Our main objective was to confirm that<br />

an obvious threat to the downstream population<br />

would not exist after the dam was<br />

removed.” said DSOD Engineer Kristen<br />

Martin with the Design Engineering Branch.<br />

“We independently evaluated designs to<br />

ensure the safety of the project.”<br />

DSOD and California American Water<br />

(Cal Am), the dam owner, worked together<br />

to reduce the risk of dam failure after DSOD<br />

evaluated and determined that the thin concrete<br />

arch dam was seismically unstable. The<br />

final solution involved relocating and stabilizing<br />

the sediment that had accumulated<br />

behind the dam, re-routing the Carmel River,<br />

demolishing the dam and providing habitat<br />

restoration for the Carmel River channel.<br />

“There have been a number of Department<br />

engineers, environmental scientists and attorneys<br />

from DSOD, South Central Region<br />

Office and our legal office working on this<br />

project for decades,” said David Gutierrez,<br />

Chief of DSOD. “There were complex<br />

engineering, financial and environmental<br />

issues to resolve and sometimes competing<br />

interests to overcome. All this hard work<br />

8 DWR Magazine j<br />

Winter 2015 | 2016<br />

Our main objective was to confirm that<br />

an obvious threat to the downstream<br />

population would not exist after the<br />

dam was removed.<br />

—Kristen Martin, DSOD Engineer<br />

Design Engineering Branch.<br />

resulted in a unique project that met all goals<br />

including eliminating a long-standing threat<br />

to both people and the environment.”<br />

Today, where the concrete dam once<br />

impeded Carmel River flows, the water<br />

is flowing freely again, providing habitat<br />

for endangered South Central steelhead<br />

trout, California red-legged frogs and other<br />

native species.<br />

“However, the build-up of sediments<br />

behind the dam, which filled 95 percent<br />

of the reservoir’s capacity and the rerouting<br />

of the Carmel River flows through San<br />

Clemente Creek on the upstream side of<br />

the dam were not the only things that made<br />

this project unique and complex,” said<br />

Supervising Engineer Daniel Meyersohn of<br />

DSOD’s Design Engineering Branch. “The<br />

fact that this was a design-build project added<br />

to its intricacy. Phases of the project were<br />

constantly being designed, reviewed, concurred<br />

with, and then built, which forced us<br />

to adapt and expedite our process.”<br />

Assessing Stability<br />

“In order to divert the river into its new<br />

reroute channel, a diversion dike was constructed<br />

across the old course of the Carmel<br />

River at the upstream end of the sediment<br />

stockpile,” said DSOD Geologist Robert<br />

Burns. “Located approximately one mile up<br />

from where the dam sat, the dike also serves<br />

as a sediment retention structure and is<br />

www.water.ca.gov

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!