new heights
2eWZ7Uj
2eWZ7Uj
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
WORLDWIDE HEAVY TRANSPORTATION AND LIFTING<br />
Case studies – Americas<br />
Case studies –<br />
Africa, Caspian and Middle East<br />
RECEIVING AND STORAGE OF 12 PIPE RACK<br />
MODULES, VENEZUELA<br />
OVERVIEW: ALE has successfully performed the receiving and storage of 12 pipe rack<br />
modules, weighing a total of 1,312.2t, for the Deep Conversion Project.<br />
SERVICES REQUIRED: The 12 modules ranged in weight and size, with some as heavy<br />
as 161.8t and measuring up to 32.1m long, 11.5m wide and 11m high.<br />
The modules were received from the vessel at the Port of Guanta, where they were<br />
prepared for onward transportation to the refinery.<br />
Two transport configurations were utilised, consisting of 32 axle lines of SPMT in a 4 file<br />
16 configuration and 40 axle lines of SPMT in a 4 file 20 configuration with two spacer beds.<br />
Overall, ALE has to date received 44 pipe rack modules out of the 96 for the Deep<br />
Conversion Project.<br />
GANTRY CRANE ROTATION, BRAZIL<br />
OVERVIEW: ALE has successfully loaded, rotated and unloaded<br />
a 2,810t gantry crane from its temporary position, onto its final<br />
track location at a shipyard in Espírito Santo, Brazil.<br />
SERVICES REQUIRED: ALE was hired to uplift a gantry crane,<br />
weighing 2,810t, from a temporary position, rotate and unload<br />
it onto its final track location.<br />
The gantry crane measured 150m wide and 95m high and was<br />
shipped fully assembled from Asia. The ship transporting it could<br />
only be moored 90 degrees to the quay. Therefore, once the<br />
gantry was unloaded, ALE needed to rotate it, so the gantry<br />
crane could move on its rails, alongside the quay.<br />
To execute this very delicate operation, ALE utilised 132 axle<br />
lines of SPMT with eight PPUs to perform the manoeuvres.<br />
During the moves, ALE faced a number of challenges. One of<br />
these was the fact that one of the gantry legs had a hinge on the<br />
top. This meant that any misalignment during the rotation (in any of<br />
CLICK HERE TO SEE MORE CASE<br />
STUDIES FROM THIS REGION<br />
the two directions) could have caused an opening of the leg<br />
and potential damage to the structure or even the collapse<br />
of it. The limits were set at 500mm for the leg opening and<br />
only 300mm for the longitudinal misalignment between the legs.<br />
To reach this delicate tolerance, SPMTs were synchronised and<br />
laser systems were installed to monitor the distance in between<br />
the legs. A topography was also used for this same purpose.<br />
Due to the very heavy loads imposed on the gantry crane<br />
structure, all of the support points between the gantry and<br />
ALE´s equipment needed to be aligned with the crane<br />
manufacturer’s guidelines. For this, ALE made two visits with<br />
the client to the manufacturer in China, so the safest transport<br />
configuration was chosen.<br />
The whole operation, including the jacking-up, rotation and jacking<br />
down, took four hours to complete. The crane will be used on the<br />
yard to handle ship blocks.<br />
TRANSPORTATION AND INSTALLATION OF HEAVY CARGO TO TWO COMBINED-CYCLE<br />
POWER PLANTS, EGYPT<br />
OVERVIEW: ALE has been awarded the transportation and<br />
installation scope for the largest combined cycle project in<br />
the world.<br />
ALE has successfully completed the first stage, involving the<br />
transportation and installation of heavy mechanical equipment to<br />
the <strong>new</strong>ly constructed gas combined-cycle power plants in Beni<br />
Suef and New Capital, Egypt.<br />
SERVICES REQUIRED: In the short period of 10 weeks, ALE has<br />
transported six gas turbines, six generators and two transformers<br />
to the power plant in Beni Suef, installing all of the turbines and<br />
generators. Simultaneously, ALE has transported one transformer,<br />
two generators and two turbines to New Capital, also installing all of<br />
the turbines and generators.<br />
Because of the challenging slopes and roads ALE faced during the<br />
route, it needed up to three prime movers to carry the<br />
heaviest gas turbines.<br />
WEIGHING, TRANSPORTATION AND LOAD-OUT OF TWO JACKETS, QATAR<br />
OVERVIEW: ALE has successfully completed the weighing, transportation and load-out of two jackets in Ras Laffan, Qatar.<br />
SERVICES REQUIRED:<br />
Both jackets were weighed using<br />
eight 600t weightors. The jackets<br />
weighed 2,628t and 2,581t and<br />
measured 57.04m long x 35m<br />
wide x 36.80m high, making these<br />
jackets the largest and heaviest<br />
jacket to ever be fabricated in Qatar.<br />
ALE transported the jackets<br />
from the fabrication yard to the<br />
quayside. ALE used 144 axle lines<br />
of Gen 3 SPMTs in a 6 x 2 file 24<br />
configuration.<br />
In consideration of the site<br />
restrictions and the limitations set<br />
by the semi-submersible barge, a<br />
side load-out was performed on<br />
the barge to enable the jacket to<br />
float-off once offshore.<br />
The load-out operation was fully<br />
controlled by a self-ballasting<br />
system of the semi-submersible<br />
barge. Each load-out operation<br />
took approximately three hours<br />
to complete.<br />
ALE’s award-winning Trojan truck and an MAN truck are being used<br />
on the project, reducing the amount of prime movers,<br />
from three to two.<br />
The gas turbines and generators were installed using skidding<br />
gantries and were moved inside the plant using<br />
24 axle lines of SPMT in a 4 file 12 configuration.<br />
This is part of a bigger contract, where each power plant will have<br />
the power of 4,800 MW, separated in eight gas blocks<br />
and four steam blocks. The total heavy cargo ALE has been<br />
contracted to deliver comprises of: 16 gas turbines weighing<br />
486t and the corresponding generators, eight steam generators,<br />
transformers and more than 380 boiler modules.<br />
The cargo was first delivered to Beni Suef power plant and then to<br />
New Capital power plant two months later. So far,<br />
ALE has not only fulfilled the intended plan but has also managed<br />
to shorten the transportation time of this project.<br />
18. CLICK HERE TO SEE MORE CASE STUDIES FROM THIS REGION<br />
19.