22. Stage 4 – The Definition of the Scope and Content of the<br />
Bidder’s Proposal<br />
• The principal purpose of the bidders’ proposal is to describe how<br />
they will meet the OBS and define the inputs that will deliver the<br />
outputs.<br />
• However, based on the evaluation criteria defined in Stage 3,<br />
and given that the bidder’s proposal is intended to be<br />
incorporated into the Contract it is sometimes useful to require<br />
that bidders submit their proposals in two parts:<br />
− the first to define the solution and provide a functional<br />
specification of the inputs to satisfy the OBS that will <strong>for</strong>m<br />
part of the Contract (hereafter referred to as the “Input<br />
Specification”); and<br />
− secondly, the evidence of the bidder’s competence, skill and<br />
experience to deliver and implement the proposed solution<br />
and inputs that will be used <strong>for</strong> the purposes of evaluation<br />
only (hereafter referred to as the “Supporting Evidence”).<br />
• The Input Specification should as a minimum require that bidders<br />
propose:<br />
− An OBS Compliance Matrix that confirms whether or not their<br />
proposal meets the per<strong>for</strong>mance standards and service levels<br />
<strong>for</strong> each output defined in the OBS, and identifies any<br />
shortfalls or limitations in their achievement.<br />
− A top-level description of the inputs that are proposed and<br />
how they contribute to the delivery of the outputs. This<br />
should include a clear picture of what inputs contribute to the<br />
delivery of which outputs;<br />
− A technical specification of each input that:<br />
� describes the physical (qualitative and quantitative)<br />
per<strong>for</strong>mance characteristics of the input;<br />
� describes how the physical and per<strong>for</strong>mance characteristics<br />
of the input enables the input to contribute to the delivery<br />
of the output.<br />
− A description as to how any constraints specified in the OBS<br />
will be complied with.<br />
− A specification of any Government Furnished Assets (GFA)<br />
that is required to be provided by the Authority (either<br />
Page 13 of 17