Study units and arrangement materials gave by us to C_ACTIVATE05 Test are approved by the experts and industry specialists. You can without much of a stretch breeze through your accreditation test with our cerebrum dumps and PDF test questions. You can use discount coupon for 20% off “20off2018” For more information please visit here: https://www.certschief.com/exam/C_ACTIVATE05/
Study units and arrangement materials gave by us to C_ACTIVATE05 Test are approved by the experts and industry specialists. You can without much of a stretch breeze through your accreditation test with our cerebrum dumps and PDF test questions. You can use discount coupon for 20% off “20off2018” For more information please visit here: https://www.certschief.com/exam/C_ACTIVATE05/
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
Question: 10<br />
Which estimation technique can be used in Agile project delivery to size the user stories during sprint<br />
planning?<br />
Please choose the correct answer.<br />
Response:<br />
A. Detailed bottom-up effort estimate the breaks each user story up into hours or shorter tasks<br />
B. Product Owner’s relative estimate of the effort that will be needed to implement the user story<br />
C. Detailed bottom-up effort estimate by the SCRUM Master in story points based on the user story<br />
complexity<br />
D. Relative estimate in ideal person days that reflects the best estimate provided by the project team<br />
Question: 11<br />
Answer: D<br />
Which activities are part of the Design and Configuration application of the SAP Activate methodology?<br />
There are 2 correct answers to this question.<br />
Response:<br />
A. Perform Fit/Gap Analysis<br />
B. Schedule kick-off workshop<br />
C. Conduct Scope Validation<br />
D. Confirm Integration prerequisites<br />
Question: 12<br />
Answer: A,C<br />
How are the build and test tasks planned and executed in the Realize phase?<br />
Please choose the correct answer.<br />
Response:<br />
A. By using the sprint backlog list as input for each iteration.<br />
B. With Q-Gates for sign off after each iteration<br />
C. By executing regression tests after each iteration<br />
D. By using incremental build in fixed-scope iteration<br />
Answer: D<br />