SRM181 - PROJECT MANAGEMENT 1<br />
INITIATION STAGE<br />
Selection site and function<br />
Firstly, the Adani Company selected site of Carmichael Coal Mine located at north west of Clermont 160 km and the<br />
coal rail network established at Abbot Point Port is 25 km north of Bowen (adani 2018). The coal rail designed up<br />
to previous draft. It is a narrow gauge rail, the function of the coal rail is that every year the Carmichael Mine could<br />
carry out 4000 million tonnes to make ensure the Carmichael Coal Mine yearly production rate 27.5 million tonnes<br />
per year (adani 2018). The length of the narrow gauge rail is 200 km, it using current railway facilities for running<br />
between Carmichael Coal Mine to Abbot Point port (adani 2018). Comparing with built a new railway between the<br />
Galilee Basin and Abbot Point Port, this plan of using existing rail infrastructure is better value for money. The<br />
benefit of narrow gauge rail line is can make ensure the project delivery, cost savings, moreover can satisfied with<br />
growing energy demand in Asia countries. On the other hand, when the Carmichael Coal Mine permit construction<br />
operation, at the first stage of produce coal is about 27.5 million tonnes per year. The Carmichael Coal Mine is lager<br />
comparing with the coal mine in the Hunter Valley and the Bowen Basin.<br />
The Carmichael Coal Mine will become the 125th with huge producing of coals of Australia (adani 2018). By paying<br />
taxes and royalties of the Carmichael Coal Mine that is about billions of dollars each year which could help Australia<br />
governments to establish the public facilities, such as new schools, hospitals even for new roads of Queensland. The<br />
Adani company wanted to upgrade Goonyella line to support Abbot Point line so that rising production capacity of<br />
the Carmichael Mine, this line will be carrying up to 50 million tonnes and export from the Carmichael Coal Mine 27<br />
million tonnes per year (adani 2018).<br />
The initiation stage of investment to the Carmichael Coal Mine<br />
The Adani wanted to investment to the Carmichael Mine 16 billion dollars, every year could export coals up to 60<br />
million tonnes (adani 2018). Furthermore, at the first stage, the Adani company planning to export coals from<br />
the Carmichael Mine for 10 million to 15 million tonnes, the top of coal production achieved 27 million tonnes.<br />
The total coal produced from 2009-2008 was 190 million tonnes, total value of coal mining production 41.5 billion<br />
dollars, contribution to Queensland government was 26 billion, the employees of coal mine were 21575(Australia<br />
Government Department of the Environment 2015). According to analyst’s report, the Adani company wanted to<br />
start a plan which is called “ultra-capital light” to services the Carmichael Mine. This plan could reduce the early<br />
stage of the capital.<br />
Comparing with previous railway designing and new railway designing<br />
The detail of previous railway designing with rail line for 388 km length, standard gauge for 1435 mm. The first<br />
stage of railway capability for 40 million tonnes per year. The maximum speed for loaded of rail lines is between<br />
80 km/hr to 100 km/hr. The service life period of railway is rail track for 50 years, drainage structures for 50 years,<br />
bridge structures for 100 years. The train consist of 3 locos 220 wagons (Australia Government Department of the<br />
Environment 2015).<br />
CARMICHAEL COAL MINE AND RAIL PROJECT 8