9.2.4 EVM -- Practice Exercises, Cont’d<br />
EVM Question 3<br />
The construction project is running behind<br />
schedule and over budget.<br />
To bring the project in on budget, which<br />
of the following is true of the TCPI?<br />
A. The TCPI is less than 1.0<br />
B. The TCPI is negative<br />
C. The TCPI is greater than 1.0<br />
D. The TCPI is an index of how far off<br />
schedule the project is running<br />
If the project is running over budget up<br />
until now, the CPI going forward would<br />
have to be ‘GOOD’ (greater that 1.0) in<br />
order to bring the project in on budget.<br />
Hence answer C is correct. “CPI going<br />
forward” is how you should think of TCPI.<br />
TCPI is Scenario 3, as presented on pg.<br />
19<br />
Solution at right<br />