1. Formal appointment of Design/Consultant Team – December 2019.

2. Planning collation and formal submission between beginning of January 2020 – end of February 2020.

3. Expected Planning Approval – Beginning of May 2020.

4. Building Warrant collation and formal submission between beginning of May 2020 – beginning of June 2020.

5. Expected Demolition Warrant Approval – Mid July 2020.

6. Expected Building Warrant Approval – Mid August 2020.

7. Tendering/negotiating/contract agreement process – End of May 2020 to mid August 2020.

8. Warehouse 16 & 17 demolition works between July – August 2020.

9. New office and Visitor Experience construction between September 2020 to December 2021.

10. Demolition of existing offi ces between January to February 2022.

MILESTONES

35