Installation of all fifty (50) turbines complete
Energisation of substation complete
Ongoing commissioning of turbines
Ongoing energisation of turbines
Installation of bottom tower sections (S1 & S2) completed at all 54 turbine locations
Three (3) turbines fully installed
All access tracks, hardstands and substation complete
Energisation of substation complete
All turbine components have been delivered to site
Three (3) Main cranes now onsite to support turbine installation
Nightworks may take place as installation works progress
Road maintenance and repairs will continue as we monitor on weekly basis
Ongoing Electrical completion of turbines
Ongoing commissioning of turbines
Ongoing energisation of turbines
Did you know the main installation cranes at
Moorabool South wind farm are fitted with an
aviation warning light? These are operational at all
times.
Image -Installation of the first turbine at Moorabool South wind farm