12.11.2020 Views

Waimea Water_AR_20_Flip

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

WAIMEA WATER LIMITED | ANNUAL REPORT 2020

OVERVIEW

Construction

The Contractor, FHTJV, has

achieved for WWL a number of

major construction milestones.

Objective

WWL works collaboratively with

our Construction Contractor, and

to be responsive and open to

opportunities that enhance the dam

as the build progresses. WWL is

striving to build a world-class dam

that complies with regulations and

best practice guidelines.

Progress

Construction commenced in March

2019, with early work on the access

roads to site. As outlined earlier, the

site was shut down for five weeks in

2020 due to COVID-19. When work

recommenced on 28 April under

Level 3 restrictions, additional office

and amenity blocks and physical

distancing measures were required,

which impacted productivity.

Fortunately, favourable weather

conditions, along with the Contractor

mobilising more resources, have

helped recover some of the

construction programme, which is

currently six months behind. On any

given day, between 140 and 180

personnel can be onsite.

To date the Contractor has:

• Completed site establishment

works, including Lee Valley Access

Road upgrades and two bridges.

• Cleared approximately 80% of

the vegetation within the

reservoir footprint.

• Cleared, mapped and approved

much of the right-hand side

(RHS) abutment rock foundation.

• Completed approximately 90%

of the approximately 165m long

diversion culvert. Fifteen of 17

sections are constructed, with

temporary diversion works well

underway.

• Stabilised approximate 1,900m2

of the slope above the RHS plinth.

• Commenced construction of the

left-hand side (LHS) and RHS

plinth.

• Largely completed bulk

earthworks to remove overburden

and Class-3 rock.

• Commenced excavation and

cleaning of the spillway foundation.

• Completed early grouting work in

advance of river diversion.

• Imported 11,000m3 of Zone

3P drainage material of a total

forecasted 80,000m3.

• Extracted and processed

18,000m3 of river gravels into

drainage material.

An overview of progress to date and

the next phase of construction is

illustrated on page 27.

CONSTRUCTION PROGRESS BY NUMBERS

Diversion culvert 90%

Vegetation clearance 72%

Excavation 47%

Onsite material processing 22%

Concrete works 21%

Rock import 14%

Anchors 13%

Reo steel 7%

0% 25% 50% 75% 100%

22

23

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!