Various NOCs are required while the Plan are submitted to the Designated

Authority for sanction / completion :-

1. Fire

2. Structural Stability/ Safety

3. Lift Installation / Safety

4. Height Clearance / Airport Authority

5. Electrical Safety

6. Labour Cess

These NOCs are mandatory to be submitted to the designated Authority along

with the Construction plans, only after the sanctioned of such plans by

Designated Authority the same are submitted to RERA for onward registration

of the project in RERA, only thereafter the registration granted by RERA and

Construction / sale of project can start .