Various NOCs are required while the Plan are submitted to the Designated
Authority for sanction / completion :-
1. Fire
2. Structural Stability/ Safety
3. Lift Installation / Safety
4. Height Clearance / Airport Authority
5. Electrical Safety
6. Labour Cess
These NOCs are mandatory to be submitted to the designated Authority along
with the Construction plans, only after the sanctioned of such plans by
Designated Authority the same are submitted to RERA for onward registration
of the project in RERA, only thereafter the registration granted by RERA and
Construction / sale of project can start .