Objective of Work<br />
1) To Reduce the Velocity of Runoff water for Conservation of Soil.<br />
1) Stop the Soil erosion; improve the Moisture in Land & Increase the Production.<br />
1) Earth work in rough excavation, filling excavated earth into depression on banking as<br />
304 directed, top be leveled and neatly dressed.<br />
Standard measurement: 1) 1× 2m +0.90 m ×1.0 = 1.45 cum<br />
2<br />
Total Field Bund:<br />
19268 R.m.× 1.45cum = 27938.60 cum<br />
Total net Qty<br />
Total Amount =Rs, 349000.00<br />
(Says Amount is Rs, 349000.00)<br />
= 27938.6cum<br />
16% Deduct = 4470.0 cum<br />
Total Net Voluble Qty = 23468.0 cum<br />
23468 cum×@ 49.10 =Rs, 1152278.00<br />
22 % Extra = Rs 253501.0<br />
Contingencies charges 2% =Rs, 28115.00<br />
Page | 119