ROLLING MILLS | Russula Newsletter No. 19 | November 2019

Nucor Steel – Utah upgrades finishing

end of bar mill #1

Nucor Corporation contracted Russula to upgrade

the drives and automation of the finishing end of its

bar mill #1 in Plymouth, Utah. Russula successfully

completed a similar upgrade for bar mill #2 in September

2016.

The main objective of the upgrade was to replace

the obsolete automation and AC/DC drive equipment

with a new modern first line control and HMI

system. The new, modern drives, control and HMI

helped Nucor Utah improve operational performance,

failure troubleshooting, spare parts availability

as well as facilitate training.

The scope of this upgrade included all the equipment

from the aligning rollers at the cooling bed to

the removal rolls, including layer forming, straightening

and cold shear cutting, layer forming, bundle

forming, tying stations and bundle exit. The existing

AC and DC drives were part of the Reliance Electric

drive series, which had become antiquated and had

limited replacement parts and support. All of the

AC and DC drives were replaced with ABB ACS880

and ABB DCS880 drives respectively. The drives

were supplied pre-installed in a new lineup up of

cabinets to match the existing power distribution

and to reuse the existing power cables whenever

possible. The existing Automax automation system

and Reliance RIO hardware were replaced with new

hardware based on Allen Bradley ControlLogix and

Point IO series and Factory Talk HMI.

Russula was also responsible for the installation

advisement, commissioning and training. The electrical

and automation equipment was assembled in

the Russula workshop at the end of last year and

underwent a factory acceptance test in January

2019. Technical specialists from Nucor Steel – Utah

and Russula were present during the test to ensure

that the new automation and drives functioned

correctly and according to specification. Commissioning

occurred in March, 2019. The switchover

was implemented in a fast and sequenced manner

in order to least disturb production.

The cooperation between Russula and the Nucor

Steel – Utah mill began in 2014 with the upgrade

of mill #2 stacker. This is the fourth consecutive revamp

project that has occurred over that time.

Nucor Corporation is the largest steel producer in

the United States, and is North America’s largest recycler.

Nucor Steel – Utah is one of Nucor’s 13 bar

mills strategically located across the United States,

which produce a wide usage of bar product for

the agricultural, automotive, construction, energy,

furniture, machinery, metal building, railroad, recreational

equipment, shipbuilding, heavy truck and

trailer market segments. The capacity of Nucor’s

bar mills is approximately 8,830,000 tons per year.