WATER SOLUTIONS | Russula Newsletter No. 19 | November 2019

Big River Steel awards Russula water

treatment complex for Flex Mill

expansion

In January 2019, Big River Steel awarded Russula a

contract to supply the water treatment solution for

Big River Steel’s Flex Mill expansion that will double

the hot-rolled steel production capacity to 3.3

million tons annually. Russula designed and supplied

the 154,000 gpm water treatment complex

for the first phase of Big River Steel, delivered in 14

months from the contract award date.

This expansion was contemplated in the original

layout of the water treatment complex which is divided

into four areas to treat water from the meltshop,

continuous caster, hot strip mill, and cold

mill. Part of the existing installations will be expanded

and other areas entirely built from scratch. In

order to double capacity, BRS will be adding a new

meltshop and continuous caster, which will require

three new water treatment areas, for the meltshop,

continuous caster and waste water. The existing

make up water and HSM areas will be expanded.

In total, the new expansion will treat an additional

92,000 gpm of water critical to the steel process.

Energy efficiency, water preservation, and environmental

stewardship are the considerations at the

forefront of the expansion design basis.

The basic engineering for the water treatment expansion

began in January of this year. The startup is

estimated for the fourth quarter, 2020.

About Big River Steel

Big River Steel invested $1.3 billion to build and

start up the world’s first Flex Mill. The mill produces

a wide product spectrum of advanced automotive

steels and motor lamination and semi-processed

non-grain oriented electrical steels. Since

operations began in early 2017, Big River Steel has

provided steel products to nearly 200 customers in

the automotive, energy, construction and agricultural

industries. The expansion will permit BRS to

produce higher grades of electrical steels that can

be used to improve energy efficiency in hybrid and

electric vehicles.

Russula will be supplying the

water treatment solution for

the Big River Steel Flex Mill

expansion that will double the

hot-rolled strip production to

3.3 MTpy. The new expansion

will treat an additional 92,000

gpm of water critical to the

steel process.