RAJASTHAN STATE ROAD DEVELOPMENT &<br />

CONSTRUCTION CORPORATION LTD.<br />

Improvement of Jodhpur - Osian - Phalodi Road km 2/000 to 121/500 (SH-<br />

61) under BOT Annuity Scheme (Jodhpur - Osian - Phalodi)<br />

BOT BOT (Annuity) Project<br />

Length - 117.17 Km<br />

Project Cost - Rs. 202.97 Crore<br />

District - Jodhpur, Phalodi<br />

State - Rajasthan<br />

RESIDENT RESIDENT ENGINEER<br />

ENGINEER<br />

RSRDCC RSRDCC RSRDCC Ltd. Ltd. , , Unit Unit - - JODHPUR JODHPUR - - I<br />

I


1 Name of Project :<br />

2 Object of Project :<br />

5 Necessity of Project :<br />

6 Road History :<br />

TECHNICAL REPORT<br />

Improvement of Jodhpur - Osian - Phalodi Road km 2/000 to<br />

121/500 (SH-61) under BOT Annuity Scheme (Jodhpur -<br />

Osian - Phalodi)<br />

Road project is proposed for widening strengthening and<br />

improvement of Phalodi (NH-15) - Osian - Jodhpur (NH-65)<br />

Road (SH-61) from Km. 2/000 to 121/500. It is an<br />

improvement link connecting Jodhpur - Phalodi. This is the<br />

shortest route connecting NH-15 to NH-65. Phalodi is<br />

Strategic important point for Army Movement. Osian is<br />

famous for Osian mata temple a hindu worship place. Thus<br />

the route is important from defence, religious and economic<br />

point of view. It is therefore necessary to strengthen, widen<br />

and improve the reach under considration.<br />

3 Location of the Project : This project is on the part of State Highway No. 61 of Km.<br />

2/000 to 121/50 (Starting from Phalodi<br />

Lohawat, Osian & Mathania.<br />

to Jodhpur via<br />

4 Climatic condition : a) The average annual rainfall of Phalodi district is 300<br />

mm<br />

b) Maximum Temp. during summer 45°C and<br />

c)<br />

Minimum 5°C during winter<br />

Water table 30 to 120 M below ground level.<br />

Rajasthan is the second largest state of the country and is one<br />

of the few states that show a great contrast from one area to<br />

another. This disparity is noticeable in respect of climate, soil,<br />

vegetation, mineral resources, etc.This is very important state<br />

highway (SH-61) connecting almost all the container &<br />

<strong>com</strong>mercial traffic leading towards Bikaner, Jaiselmer,<br />

Ganganagar. Looking to the traffic growth & improvement of<br />

this area there is very necessity to further improvement of this<br />

road by strengthening.<br />

Previously, the Road was constructed in various stages.<br />

Originally the road was 3.0 m wide subsequently widened to<br />

5.5m and finally to 7m.in various stages / reaches.


7 Design Proposals :<br />

The Project design scope of work in this project are :<br />

a) Geometric Design and General Features :<br />

The Geometric design of the Project Highway shall<br />

confirm to the standards of IRC.Existing Horizontal<br />

Curves, which are found deficient in radius, lay out ,<br />

transition lengths or super elevation shall corrected<br />

to the specified standards.<br />

Any deficiencies in vertical profile in respect of<br />

grades, layout of vertical curves and sight distance<br />

shall be corrected to meet the minimum specified<br />

requirements.<br />

The design speed shall be adopted for various<br />

terrain classified as per IRC standard for plain area<br />

rulling speed 80 km./hr. and minimum 65km./hr.<br />

b) Intersections and Junctions :<br />

Intersections and Junctions shall be improved as per<br />

IRC:SP:41.<br />

c) Pavement Design :<br />

The design of flexible pavement is covered in two<br />

part namely, new pavements, and widening and<br />

strengthening of existing pavements. As per IRC:37<br />

and IRC81<br />

d) Roadside Drainage :<br />

The design and construction of surface and sub<br />

surface drains for highway drainage shall be carried<br />

out in accordance with the requirements an as per<br />

IRC Specification.<br />

e) Widening of Cross - Drainage Works :


The design of drainage system such as surface and<br />

sub-surface drainage for pavement, median,<br />

shoulder, high embankment shall be carried out in<br />

accordance with IRC: SP: 42 and IRC: SP: 50. Surface<br />

runoff from the main highway, embankment slopes<br />

and the service roads shall be discharged through<br />

longitudinal drains, which shall be designed for<br />

adequate cross section, bed slopes, invert levels and<br />

the outfalls. If necessary, the walls of the drains shall<br />

be designed to retain the adjoining earth. Where<br />

drains are required to be the covered, the cover of<br />

the drain shall be designed for carrying the<br />

maximum expected wheel load. The covered drains<br />

shall be provided with iron gratings / , strong<br />

enough to withstand expected loading.<br />

f) Traffic Control Devices and Road Safety Works &<br />

Roadside Furniture :<br />

(i)Traffic Control Devices shall <strong>com</strong>prise of traffic<br />

signs, road markings, safety barriers, pedestrian<br />

railing, etc. as per guidelines in IRC:35, IRC:67 and<br />

Section 800 of the MoRTH Specifications shall be<br />

followed in adopting appropriate road markings<br />

and traffic signs for Road Safety Works.<br />

(ii) Pavement marking shall also be carefully<br />

planned depending upon the requirement for each<br />

location and shall conform to IRC-35. The Project<br />

Highway shall incorporate all such safety features<br />

such as elaborate system of signs and markings, cat’s<br />

eyes, delineators, hazard markers, safety barriers at<br />

hazardous locations, pedestrian guardrails so that<br />

the Project Highway operates as a “Forgiving<br />

Highway”.<br />

g) Toll Plazas :<br />

4 Nos. of Toll Plaza for collection of toll shall be<br />

constructed for the fee collection system speedily,<br />

efficient and user friendly. The design of toll plazas<br />

shall be such that they are aesthetically pleasing and<br />

efficient and the fee collection staff should be quick,<br />

courteous and adequately trained before<br />

deployment as per concession agreement:<br />

h) Roadside Furniture :


(i) The Project Highway shall be provided with<br />

elaborate system of traffic signs and markings. The<br />

traffic signs for various situations/location would be<br />

in accordance with IRC 67 in terms of location,<br />

configuration and colour scheme.<br />

i) Landscaping and Plantation :<br />

The concessionaire shall plant tees and hurbs of<br />

required number and type at the appropriate<br />

locations with in the Right of Way and in the land<br />

earmarked by the Government for the forestation.<br />

And also maintain the trees and shrubs in good<br />

condition during the operation period.<br />

Provision of Rs. 1.88 Crore has been taken.<br />

8 Scope of Work : The Project scope of work in this project are :<br />

I a) The construction of new paved shoulder in km<br />

2/000 to 121/500 is proposed. The Crust of this<br />

paved shoulder is taken same as new construction of<br />

road. Detail is as under.<br />

1. Sub Grade soil of 9% CBR<br />

2. GSB 30% CBR - 200mm Thick<br />

3. WMM - 250mm Thick<br />

4. DBM - 75mm Thick<br />

5. BC - 40mm Thick<br />

b) The construction of New BT Road on the bye pass is<br />

proposed at Mathania, Osian & Ummaidnagar.<br />

Manaklav to Mathania - 12.13 Km<br />

Osian Sharp Bend - 0.5 km<br />

Ummaid Nagar Bye Pass - 1.22 Km<br />

Sharp Bend after Manaklao - 0.5 km<br />

For this stretch new construction the crust is<br />

proposed is as under :-<br />

1. Sub Grade soil of 9% CBR<br />

2. GSB 30% CBR - 200mm Thick<br />

3. WMM - 250mm Thick<br />

4. DBM - 50mm Thick<br />

5. BC - 40mm Thick<br />

c) The New CC road of 3300m length is taken. The<br />

length is proposed in several stretches.<br />

Osian Village - 1850 m (4 Lane Road)<br />

Mathania Village - 1500 m


Proposed CC Road Crust is proposed as under :-<br />

1. GSB - 150mm Thick<br />

2. CC M-10 - 150mm Thick<br />

3. CC M-30 - 300mm Thick<br />

(d) Strengthening of existing surface i.e. from km 2/000 -<br />

121/500 is proposed by providing 50mm thick DBM<br />

for improving super elevation, camber correction<br />

and undulations and 40mm thick BC.<br />

(e) 60/70 grade bitumen shall be used for DBM<br />

(f) Widening of existing carriageway to two lane (7.0m)<br />

carriageway with 2x1.50m Paved Shoulder and<br />

2x1.0m Hard Shoulder.<br />

(g) Proposal to improve the existing formation in 12.0m<br />

width with side slopes with Hard shoulders on both<br />

side of the carriageway<br />

(h) Adequate provision for suitable road furnitures have<br />

been taken.<br />

(i) Improvement of junctions of link roads have been<br />

taken.<br />

(j) Improvement of curves will be done by providing<br />

extra widening and providing adequate<br />

superelevetion.<br />

(k) Land acquisition required for Bye Pass, Utilities &<br />

other requirement.<br />

(l) Provision for 4 No. of Toll Plaza in km 6/500, 39/900<br />

km, 90/000 km, 109/000 has been taken.<br />

(m) Provision for widening CD work which are less than<br />

12.0m width has also proposed to widen. And few<br />

new has been introduced.<br />

(n) Provision of pick up bus stop is at 8 places.<br />

8 Project Facilities : Following project facility has been taken:<br />

1 Bus Shelters<br />

2 Public Facilities<br />

9 Availability of Labour and<br />

Material<br />

: (a) Labour : Unskilled and skilled laborers are<br />

sufficiently available in the adjoining areas.<br />

(b) Material Crusher grit, ballast and crusher dust etc.<br />

are localy available and Kankar is available at Local<br />

quarry. Water, Mooram are locally available and<br />

bricks are also available.


10 Availability of Land :<br />

11 Specifications<br />

a<br />

b<br />

c<br />

Land for road improvement is available with State PWD<br />

because work is to be executed on existing road. So there is<br />

full availability of land in required width. For aquiring land in<br />

this area is not a problem.<br />

In Km. 2/000 - 121/500 : Proposed specification are as under :-<br />

The road crust for widening work has been designed as per<br />

(i) Widening<br />

It is proposed to maintain the 7.00m Carriageway with Paved<br />

& hard shoulders.<br />

(ii)Sub Base, Base & BT work<br />

Thickness of new pavement is provided as per IRC 37-2001.<br />

Combination of thickness is GSB- 200 mm, WMM-250 mm,<br />

DBM-50 mm & BC - 40 mm.<br />

(iii) Shoulders :<br />

150 mm Granular material in 1.00 m width on both side.<br />

(iv) CC pavement :<br />

150 mm CC 1:3:6 as base & 300mm CC M-30 will be provided<br />

according to IRC:15-2002 & IRC:58-2002 with suitable<br />

expansion & contraction joints.<br />

(v) Precast CC Interlocking Block :<br />

Precast CC interlocking Block of thickness 100mm has been<br />

taken in lay byes.<br />

(vi) Road furniture :<br />

It is proposed to provide necessary boards, missing km/ 5th<br />

km stones, centre line and edge line to improve road<br />

aesthetics.<br />

(vii) Road Safety Works :<br />

For Height of Embankment is 1.5m - 3.0m Stone Pitching at<br />

slopes with Delineators at interval of 2.5m taken.<br />

For Height of Embankment is more than 2.0m Stone Pitching<br />

at slopes with Delineators at interval of 2.5m with Retaining /<br />

Protection wall is taken.<br />

For Sharp Curves Cat eyes with Shevron & Speed limit Sign<br />

boards has been taken<br />

d For intersection and junction notification board with RPM has<br />

been provided to control the speed.<br />

12 Tollable Traffic category : This is as per Govt. Notification dated April 2007 copy of the<br />

Rates<br />

same is enclosed.<br />

13 Traffic data weight age : The traffic census datas at km 6/500, 39/900, 90/000, 109/000<br />

conducted<br />

annexure<br />

from 21-05-10 to 28-05-2010 are enclosed at


14 Growth rate of traffic :<br />

15 Anticipated gross traffic<br />

volume (base year 2010-11)<br />

16 Toll able nett traffic volume<br />

17 Anticipated Toll collection<br />

18 Deduction of operational<br />

charges<br />

19 Construction Period<br />

20 Base year<br />

21 Tollable period :<br />

22 Project concession period 20 Years 0 Months 0 days<br />

23 Project cost Rs. 20,297.29 Lacs<br />

The traffic data collected as per special survey conducted for<br />

seven day with 5% growth.<br />

Average traffic with weight age in Base year 2010-11 has been<br />

worked out.<br />

The calculation for toll able nett Traffic volume is as per<br />

Annexure table-4<br />

On the basis of toll able traffic and corresponding applicable<br />

rates, anticipated toll collection has been worked out quarter<br />

wise and is tabulated in table 6 and quarterly out lay of<br />

investment and interest has been worked out in table 5<br />

Total deduction for operational charges for toll collection , and<br />

servicing to be allowed 7.5% net toll collection of quarterly<br />

basis along with 0.5-1.5% provision of project construction<br />

cost.<br />

The construction period is assumed as 1 year 6 Months.<br />

2010-11<br />

Repayment calculations has been framed as table No.6<br />

Repayment period is 18 Years 6 Months 0 Days


RAJASTHAN STATE ROAD DEVELOPMENT &<br />

CONSTRUCTION CORPORATION LTD.<br />

Route Map<br />

RESIDENT RESIDENT RESIDENT ENGINEER<br />

ENGINEER<br />

RSRDCC RSRDCC RSRDCC Ltd. Ltd. , , , Unit Unit - - JODHPUR JODHPUR - - I<br />

I


RAJASTHAN STATE ROAD DEVELOPMENT &<br />

CONSTRUCTION CORPORATION LTD.<br />

Unit - Jodhpur - I<br />

It is certified that :-<br />

(A) there is no toll tax plaza existing within 50 km of Phalodi (NH-15) - Osian - Jodhpur<br />

(NH-65) under BOT with Annuity, which is in the scope of the Proposed BOT project.<br />

(B) Traffic census was conducted in km 6/500, 39/900, 90/000, 109/500 of SH-61 for 7 days<br />

i.e. 21-05-2010 to 28-05-2010 and was checked by undersigned.<br />

RESIDENT RESIDENT ENGINEER<br />

ENGINEER<br />

RSRDCC RSRDCC Ltd. Ltd. , , , Unit Unit Unit - - Jodhpur Jodhpur - - I<br />

I


Base Year : 2010-11<br />

S. No. Particulars Cost (in Rs.)<br />

1 PART : A Improvement of Existing Road 795,732,491.00<br />

2 PART : B CD Works (Culverts / Bridges) with Drains 117,609,533.95<br />

3 PART : C Cement Concrete Pavement 68,965,155.00<br />

4 PART : D Road Furniture 43,560,359.28<br />

5 PART : E Road Work for Toll Plaza, Lay Bye 45,276,703.00<br />

6 PART : F Bye Passes 179,800,343.13<br />

7 PART : G Improvement of Verical & Horizontal Curves 136,125,464.00<br />

Project Facilities<br />

ABSTRACT OF PROJECT<br />

Name of Work :- Improvement of Jodhpur - Osian - Phalodi Road km 2/000 to 121/500 (SH-61)<br />

under BOT Annuity Scheme (Jodhpur - Osian - Phalodi)<br />

Construction Period: 18 Months<br />

01.01.2011 to 30.06.2012<br />

8 PART: H Toll Plaza (4 nos.) 19,594,400.00<br />

9 PART: I Public Utility Services 30,982,462.74<br />

10 PART: J Landscaping & Tree Plantation 18,770,500.00<br />

Total Cost 1,456,417,412.10<br />

Say Rs. in Lacs 14564.17<br />

11 PART: K Add: Escalation for 1 year 0.00<br />

12 PART: L Tender Premium @ 0% 0.00<br />

13 PART: M Cost of contigencies 5% Rs.<br />

728.21<br />

14 PART: N Quality Control (1%) Rs.<br />

145.64<br />

15 PART: O Guarantee Commission to State Govt. (1%) Rs.<br />

145.64<br />

16 PART: P Cost of Land Acquisition Rs.<br />

549.84<br />

17 PART: Q Cost of Utility Shifting (1%) Rs.<br />

145.64<br />

Sub Total 16279.14<br />

18 PART: R A & F Charges (10%) Rs.<br />

1,627.91<br />

19 PART: S Application Fee and Front end fee (0.5%) Rs.<br />

81.40<br />

Sub Total Rs.<br />

17,988.45<br />

20 PART : T Interest during construction Rs.<br />

2,308.84<br />

Grand Total Rs.<br />

20,297.29<br />

RESIDENT ENGINEER<br />

RSRDCC Ltd. , Unit - Jodhpur - I


Base Year : 2010-11<br />

ABSTRACT OF PROJECT<br />

Name of Work :- Improvement of Jodhpur - Osian - Phalodi Road km 2/000 to 121/500 (SH-61)<br />

under BOT Annuity Scheme (Jodhpur - Osian - Phalodi)<br />

Abstract of Strengthening Coat<br />

Construction Period: 18 Months<br />

01.07.2019 to 30.06.2020<br />

S. No. Particulars Cost (in Rs.)<br />

1 PART : A Improvement of Existing Road 747,779,604.00<br />

Total Cost 747,779,604.00<br />

Say Rs. in Lacs 7477.80<br />

11 PART: B Add: Escalation for year 2019 - 2020 4122.72<br />

12 PART: C Tender Premium @ 0% 0.00<br />

Grand Total Rs.<br />

11,600.52<br />

13 PART: D Cost of contigencies 5% Rs.<br />

580.03<br />

14 PART: E Quality Control (1%) Rs.<br />

116.01<br />

Sub Total Rs.<br />

12,296.55<br />

RESIDENT ENGINEER<br />

RSRDCC Ltd. , Unit - Jodhpur - I


Base Year : 2010-11<br />

ABSTRACT OF PROJECT<br />

Name of Work :- Improvement of Jodhpur - Osian - Phalodi Road km 2/000 to 121/500 (SH-61)<br />

under BOT Annuity Scheme (Jodhpur - Osian - Phalodi)<br />

Abstract of Renewal Coat<br />

Construction Period: 18 Months<br />

01.07.2026 to 30.06.2027<br />

S. No. Particulars Cost (in Rs.)<br />

1 PART : A Improvement of Existing Road 288,101,930.00<br />

Total Cost 288,101,930.00<br />

Say Rs. in Lacs 2881.02<br />

11 PART: B Add: Escalation for year 2026 - 2027 3407.89<br />

12 PART: C Tender Premium @ 0% 0.00<br />

Grand Total Rs.<br />

6,288.91<br />

13 PART: D Cost of contigencies 5% Rs.<br />

314.45<br />

14 PART: E Quality Control (1%) Rs.<br />

62.89<br />

Sub Total Rs.<br />

6,666.24<br />

RESIDENT ENGINEER<br />

RSRDCC Ltd. , Unit - Jodhpur - I


S.<br />

No.<br />

Improvement of Jodhpur - Osian - Phalodi Road km 2/000 to 121/500 (SH-61) under BOT Annuity Scheme (Jodhpur - Osian - Phalodi)<br />

Item<br />

No.<br />

Abstract of Quantites<br />

PART 'A' - I SITE CLEARANCE & EARTHWORK IMPROVEMENT & WIDENING OF EXISTING ROAD<br />

Description No. L B H Factor Q Unit Rate Amount<br />

1 R-2 Clearing Grass and Removal of Rubbish<br />

2.1 Cutting of trees, including cutting of trunks, branches and<br />

removal of stumps, roots stacking of serviceable material with<br />

all lifts and upto a lead of 1000 m and earth filling in the<br />

depression/ pit as per MORTH specification clause 201.<br />

2.1.1 (i) Girth from 300 mm to 600 mm 25 25 Each 138.00 3450.00<br />

2.1.2 (ii) Girth from 600 mm to 900 mm 25 25 Each 246.00 6150.00<br />

2.1.3 (ii) Girth from 900 mm to 1800 mm 25 25 Each 479.00 11975.00<br />

2 R-2 Clearing Grass and Removal of Rubbish<br />

2 Clearing grass and removal of rubbish maximum 150mm in<br />

thickness upto a distance of 100 Mtr outside the periphery of the<br />

area by manual means . Note ; where only grass is met with , the<br />

area clear shall be measured & paid for under this item<br />

MORTH clause 201 )<br />

(<br />

2 10000.00 6 120000.00<br />

Total= 12.00 hectare 9559.00 114708.00<br />

3 Clearing and Grubbing Road Land<br />

R-2/3 Clearing and grubbing road land including uprooting rank<br />

(ii)<br />

vegetation, grass, bushes, shrubs, saplings and trees girth upto<br />

300 mm, removal of stumps of trees cut earlier and disposal of<br />

unserviceable materials and stacking of serviceable material<br />

upto a lead of 1000m including removal and disposal of top<br />

organic soil not exceeding in 150 mm thickness as per MORTH<br />

specification clause 201<br />

By Manual Means<br />

(A) In Area of light jungle 2 3500 3 21000.00<br />

Total= 2.10 hectare 28919.00 60730.00<br />

4 Dismantling of Structures


R-2/4 Dismantling upto 1.5m in foundation and/or 1.5m above<br />

ground level including T&P and scaffolding wherever necessary,<br />

sorting the dismantled material, disposal of unserviceable<br />

material, and stacking serviceable material with in a lead of<br />

1000m. [MoRTH Specification clause 202]<br />

(ii) By Mechanical Means<br />

4.1.1.2 Cement Concrete M-15 & M-20 LS 100.00<br />

Total= 100.00 cum 243.00 24300.00<br />

4.1.1.3 Prestressed / Reinforced Cement Concrete grade M-20 & Above LS 100.00<br />

Total= 100.00 cum 644.00 64400.00<br />

4.3.2 RR Masonry in cement mortar LS 100.00<br />

Total= 100.00 cum 167.00 16700.00<br />

5 R-<br />

Dismantling of Flexible Pavements<br />

Dismantling of flexible pavements and disposal of dismantled<br />

2/2.4.1 materials upto a lead of 1000 metres, stacking serviceable and<br />

0 unserviceable materials separately as per MORTH specification<br />

clause 202.<br />

For CC Pavement Section + New Bituminous Road<br />

6 R-3/<br />

3.1<br />

By Mechanical Means<br />

(A) Bituminous Courses (From Verticle Curve Improvement) 1 3689.05 3689.05<br />

Total= 3689.05 cum 151.00 557047.00<br />

(B) Granular courses (From Verticle Curve Improvement) 1 13821.97 13821.97<br />

Total= 13821.97 cum 271.00 3745755.00<br />

Earth work in excavation, including stacking/disposal of<br />

surplus material with all lifts and lead upto 495 metres,<br />

exclusive of <strong>com</strong>pensation of earth [MoRTH specification :<br />

Clause 301 to 305]<br />

3.1.1.3 Mechanically by power shovel, including mechanical loading<br />

and carriage by tipper/dumper (6T capacity)<br />

for Widening of Road (5.5-10.00) 1 51468.93 7.5 0.5 193008.49<br />

for Widening of Road (3.5-10.00) 1 5410.17 9.5 0.5 25698.31<br />

7.0 m existing Road 1 24666.28 6 0.5 73998.84<br />

Removal of Heaps of soil along the road 1 12000 6 1.5 108000.00<br />

400705.64 Cum 61.00 24443044.00<br />

7 3.7 Extra for laying earth as per specification for <strong>com</strong>paction in 200<br />

mm thick loose layers and dressing [MoRTH Specification<br />

Clause 305.3.5].


BY MECHANICAL MEANS, using Motor Grader, from earth in<br />

stock piles with all lead and lift but excluding rolling and<br />

watering.<br />

for Widening of Road (3.5-10.00) 1 51468.93 7.5 0.5 193008.49<br />

for Widening of Road (3.5-10.00) 1 5410.17 9.5 0.5 25698.31<br />

7.0 m existing Road 1 24666.28 6 0.5 73998.84<br />

Total= 292705.64 cum 15.00 4390585.00


8 3.7.4 Extra for watering the earth to bring the earth upto required<br />

O.M.C excluding rolling<br />

for Widening of Road (3.5-10.00) 1 51468.93 7.5 0.5 193008.49<br />

for Widening of Road (3.5-10.00) 1 5410.17 9.5 0.5 25698.31<br />

7.0 m existing Road 1 24666.28 6 0.5 73998.84<br />

292705.64 cum 11.00 3219762.00<br />

9 3.7.5 Extra for rolling to specification with the use of Vibratory roller<br />

when earth is at suitable moisture content with desired field<br />

density not less than 95% of maximum dry density (Modify<br />

Heavy Proctor test), excluding watering.<br />

292705.64 cum 24.00 7024936.00<br />

10 R-3/6 Compaction of original ground with maximum of six passes of 8-<br />

10 tonnes power roller including filling depression occurring<br />

during rolling [MoRTH Specification : Clause 305.3.4]<br />

for Widening of Road (3.5-10.00) 1 51468.93 7.5 386016.98<br />

for Widening of Road (3.5-10.00) 1 5410.17 9.5 51396.62<br />

7.0 m existing Road 1 24666.28 6 147997.68<br />

Total= 5854.11 sqm 199.00 1164969.00<br />

11 R-3/3 Dressing of earth work including cutting and filling upto 15cm<br />

[MoRTH Specification Clause 301 to 305]<br />

1 76135.21 4 304540.84 sqm<br />

3045.41 100 sqm 15.00 45682.00<br />

12 R-3/4 Box cutting/Trenching the Sub Grade to proper slope, camber<br />

and removing inequalities including removing deleterious stuff<br />

and depositing on the road side slopes (cutting of earth shall be<br />

paid separately in the respective item on the basis of<br />

classification of the excavation done by the Engineer (MoRTH<br />

specification clause 301 to 305)<br />

for Widening of Road (3.5-10.00) 1 51468.93 7.5 386016.98<br />

for Widening of Road (3.5-10.00) 1 5410.17 9.5 51396.62<br />

7.0 m existing Road 1 24666.28 6 147997.68<br />

5854.11 100 sqm 41.00 240019.00


13 3.1 Earth work in excavation in foundation trenches etc.in drains<br />

and channels etc. not exceeding 2m.depth, including dress-sing<br />

of bottom and sides of trenches, stacking the excavated soil 3m.<br />

Clear from the edge of excavation including disposal surplus<br />

soil as directed within a lead of 1000 metres [Most Specification :<br />

Clause 301,304]<br />

For Drains along the road 1 81545.38 1 0.5 40772.69 Cum 74.00 3017180.00<br />

TOTAL PART 'A' - I 48151392.00


PART 'A' - II BASE & SUB BASE WORK IMPROVEMENT & WIDENING OF EXISTING ROAD<br />

S.<br />

No.<br />

Item<br />

No.<br />

Description No. L B H Factor Q Unit Rate Amount<br />

Base & Sub Base<br />

R-4 Granular Sub - base with Well Graded Material (Table 400.1)<br />

Plant Mix Method<br />

1 4.3 Providing laying spreading and <strong>com</strong>pacting specified graded<br />

sand, gravel as per Table 400-1,400-2 or any other course<br />

material as per design mix, as per CBR in sub base course<br />

including premixing the material at OMC in wet mix plant,<br />

carriage of mixed material spreading in uniform layers with<br />

motor grader F.E loader on a prepared base and <strong>com</strong>pacting<br />

with vibratory roller to achieve desired density (as per I.S.2720)<br />

including all material, labor, machinery, lighting guarding,<br />

barricading and maintenance of diversion <strong>com</strong>plete.[MoRTH<br />

specification : Clause 401]. By mechanical means with lead up to<br />

1 km<br />

By mechanical means with lead upto 1 km<br />

(i) For Grading I Material<br />

for Widening of Road (5.5-7.00) 1 51468.93 7.50 0.2 1.02 78747.46<br />

for Widening of Road (3.5-7.00) 1 5410.17 10.50 0.2 1.02 11588.58<br />

7.0 m existing Road 1 24666.28 6.00 0.2 1.02 30191.53<br />

Total= 120527.57 cum 490.00 59058512.00<br />

2 3.1 Extra rate for carriage of mixed material additional lead from :-<br />

3.1.1 2nd km to 30th km 1 120527.57 120527.57 Cum/Km 92.35 11130722.00<br />

R-5 Wet Mix Macadam


3 5.3 Providing, laying, spreading and <strong>com</strong>pacting stone aggregate<br />

for Wet Mix Macadam (as per table 400-10 and 400-11)<br />

specification including premixing the material with water to<br />

OMC in wet mix plant as per approved design mix, carriage of<br />

mixed material by Tipper to site, laying in uniform layers with<br />

motor grader/Front end Loader/paver finisher, in sub base/<br />

base course on a well prepared under base and <strong>com</strong>pacting with<br />

vibratory roller to achieve the desired density including lighting,<br />

guarding, barricading and maintenance of diversion etc.<br />

(MoRTH specification : Clause 406) by mechanical means with<br />

lead up to 1 Km.<br />

By Mechanical Means with 1 km lead<br />

for Widening of Road (5.5-7.00) 1 51468.93 4.8 0.25 1.02 78747.4629<br />

for Widening of Road (3.5-7.00) 1 5410.17 6.8 0.25 1.02 11588.5841<br />

7.0 m existing Road 1 24666.28 3.3 0.25 1.02 30191.5267<br />

Total= 120527.57 cum 765.00 92203594.00<br />

4 2.1 Extra rate for carriage of mixed material additional lead from :-<br />

2.1.1 2nd km to 30th km 1 120527.57 120527.57 Cum /Km 92.35 11130722.00<br />

B Hard shoulders<br />

5 R-4/2 Providing and laying granular sub-base material having P.I.not<br />

more than 6, including spreading in layers not exceeding 150<br />

mm <strong>com</strong>pacted thickness and consolidation by 8-10 tonne<br />

power roller to required camber and grade including cost of<br />

water and hire charges of machinery, including T&P with all<br />

lead (Compacted thickness to be measured).as per MORTH<br />

specification table 400-1, 400-2 :<br />

2.1 For grading-I with CBR value not less than 30.<br />

to attain 100% proctor density. 2 81545.38 1 0.15 1.02 24952.89<br />

Total= 24952.89 Cum 286.00 7136526.00<br />

TOTAL PART 'A' - II 180660076.00


PART 'A' - <strong>III</strong> BITUMINOUS WORK IMPROVEMENT & WIDENING OF EXISTING ROAD<br />

S.<br />

No.<br />

Item<br />

No.<br />

Description No. L B H Factor Q Unit Rate Amount<br />

Bituminous Work<br />

R-6 Prime Coat<br />

1 6.1 Providing and applying primer coat over prepared surface or<br />

for Widening of Road (5.5-10.00) 1 51468.93 4.5 1.02 236242.39<br />

for Widening of Road (3.5-10.00) 1 5410.17 6.5 1.02 35869.43<br />

7.0 m existing Road 1 24666.28 3.0 1.02 75478.82<br />

Total= 347590.63 sqm 21.00 7299404.00<br />

6.1.1 Add extra for 1.5 Kg / 10 Sqm emulsion 1.5 347590.63 521385.95 sqm 2.10 1094911.00<br />

2 6.2<br />

Tack Coat<br />

Providing and applying tack coat on the prepared surface, with<br />

for Widening of Road (5.5-10.00) 2 51468.93 5.5 1.02 577481.39<br />

1 51468.93 4.5 1.02 236242.39<br />

for Widening of Road (3.5-10.00) 2 5410.17 3.5 1.02 38628.61<br />

1 5410.17 6.5 1.02 35869.43<br />

7.0 m existing Road 2 24666.28 7 1.02 352234.48<br />

1 24666.28 3 1.02 75478.82<br />

Improvement of Mathania & Osian Internal Road (Osian -0.65 +<br />

Mathania 0.75 )<br />

2 1400.00 7 1.02 19992.00<br />

= Ummed Nagar - 2.4 2 2400.00 5.5 1.02 26928.00<br />

1362855.12 sqm 8.00 10902841.00<br />

6.2.1 Add extra for .75Kg / 10 Sqm emulsion 0.75 1362855.1 1022141.34 sqm 2.90 2964210.00<br />

Total=


3 R-6 Dense Bituminous Macadam<br />

6 Providing and laying Dense Bituminous Macadam on prepared<br />

surface with specified graded crushed aggregates as per table<br />

510 and design mix for base/binder course including loading of<br />

material with Front end loader, heating of binder (including cost<br />

of anti-stripping <strong>com</strong>pound wherever required) aggregate and<br />

filler in hot mix plant 40-60 TPH, transporting the mixed<br />

material by tippers and laying with sensor paver finisher as per<br />

clause 507.3.5 to the required level and grade rolling by self<br />

propelled power rollers and vibratory rollers or pneumatic tyred<br />

roller 150-250KN. TP=0.7MPa to achieve the desired density<br />

(approved by the department) but excluding cost of primer/tack<br />

coat. [MoRTH Specification : Clause 507 & 112]<br />

6.2 Grading II (19 mm nominal size) - Bitumen @ 4.5 % of mix<br />

for Widening of Road (5.5-10.00) 1 51468.93 4.5 0.05 1.02 11812.12<br />

for Widening of Road (3.5-10.00) 1 5410.17 6.5 0.05 1.02 1793.47<br />

7.0 m existing Road 1 24666.28 3 0.05 1.02 3773.94<br />

Camber Correction & Grade Improvement 1 51468.93 5.5 0.05 1.02 14437.03<br />

1 5410.17 3.5 0.05 1.02 965.72<br />

1 24666.28 7 0.05 1.02 8805.86<br />

Vertical Improvement of Curve 1 9985.77 1 9985.77<br />

Total=<br />

51573.92 cum 4799.00 247503232.0<br />

4 28 Cost of bitumen to be added when it varies from job mix<br />

formula adopted in any of the above items. Taken 0.5 %<br />

28.2 60/70 Penetration grade 1 51573.92 0.5 2.35 605.994 ton 34494.0 20903141.0<br />

5 9.2 30 km. -Same as Above 51573.918 cum 92.35 4762852.00


6 6.3 Providing and laying bituminous macadam on prepared surface<br />

with specified graded crushed aggregate as per table 500 - 4,<br />

grading -1for base / binder course including loading of<br />

aggregates with F.E loader and heating and mixing of stone<br />

aggregate and bitumen ( including cost of antstripping<br />

<strong>com</strong>pound wherever required) in hot mix plant transporting the<br />

mixed material in tipper to paver and laying mixed material<br />

with sansor paver finisher to the required level and grade<br />

rolling by power roller & vibratory <strong>com</strong>pactor to achieve the<br />

desired density (approved by the department )excluding cost of<br />

primer /tack coat [MoRTH Specification : Clause 504,112] 50-100<br />

mm <strong>com</strong>pacted thickness with 3.30% bitumen 60/70 grade with<br />

lead of mix 1 Km.<br />

Improvement of Mathania & Osian Internal Road (Osian -0.65 +<br />

Mathania 0.75 )<br />

2 1400.00 7 0.05 1.02 999.60<br />

= Ummed Nagar - 2.4 2 2400.00 5.5 0.05 1.02 1346.40<br />

2346.000 Cum 3649.00 8560554.00<br />

7 Extra rate for carriage of mixed material additional lead from :-<br />

30 km. -Same as Above 2346.00 cum 92.35 216654.00<br />

8 6.8 Providing , laying and consolidation Semi Dense Bituminous<br />

Concrete, as per Design Mix, on prepared surface with specified<br />

graded crushed aggregates(as per table 500-15) for wearing<br />

coarse including loading aggregates with F.E loader, heating<br />

aggregate and binder in Hot Mix Plant 100-120 TPH (including<br />

cost of antistripping <strong>com</strong>pound wherever required ) and<br />

transporting the mixed material with tipper and laying with<br />

paver finisher with Sensor to the required level rolling with<br />

Vibratory Compactor or 150 to 250 KN pneumatic tyred roller<br />

with TP=0.7 Mpa and power roller to achieve the desired<br />

density (as per approved job mix), but excluding primer/tack<br />

coat [MORTH Specification Clause 508,112]<br />

Bitumen @ 5 % of mix With lead of mix material 1 KM<br />

60/70 grade<br />

Improvement of Mathania & Osian Internal Road (Osian -0.65 +<br />

Mathania 0.75 )<br />

2 1400.00 7 0.025 1.02 499.80<br />

= Ummed Nagar - 2.4 2 2400.00 5.5 0.025 1.02 673.20<br />

1173.000 Cum 5203.00 6103119.00


9 Extra rate for carriage of mixed material additional lead from :-<br />

30 km. -Same as Above 1173.00 cum 92.35 108327.00<br />

10 R-6/9 Providing and laying bituminous concrete as per design mix on<br />

prepared surface with specified graded stone as per table 500-18<br />

for wearing course including loading of aggregate with Front<br />

end loader and hot mixing of binder (including cost of antistripping<br />

<strong>com</strong>pound, wherever required) and 3% cement filler<br />

with aggregates in hot mix plant 40-60 TPH Transporting the<br />

mix material with tipper and laying with sensor paver finisher<br />

(as per clouse 507.3.5) to the required level , grades and rolling<br />

with vibratory <strong>com</strong>pactor and pneumatic tyred roller 150-250<br />

KN,TP=0.7 Mpa, to achieve the desired density (approved by<br />

the department) excluding cost of primer/tack coat (MoRTH<br />

Specification : Clause -509 & 112)<br />

12.1 Grading I (19 mm nominal size) - Bitumen @ 5.5 % of mix &<br />

thickness 50 - 65 mm with lead of mix material 1km<br />

With 60/70 penetration grade straight run bitumen / PMB<br />

for Widening of Road (5.5-7.00) 1 51468.93 10 0.04 1.02 20999.32<br />

for Widening of Road (3.5-10.00) 1 5410.17 10 0.04 1.02 2207.35<br />

7.0 m existing Road 1 24666.28 10 0.04 1.02 10063.84<br />

Curve Improvement 1 19489.62 10 0.04 1 7795.85<br />

Total= 41066.36 cum 5757.00 236419053.00<br />

11 28 Cost of bitumen to be added when it varies from job mix<br />

formula adopted in any of the above items. Taken 0.5 %<br />

28.2 60/70 Penetration grade 1 41066.36 0.5 2.3 472.26 tonne 34494 16290246.00<br />

12 12.2 Extra rate for carriage of mixed material additional lead from :-<br />

30 km. -Same as Above 41066.36 cum 92.35 3792479.00<br />

TOTAL PART 'C' 566921023.00


S.<br />

No.<br />

Improvement of Jodhpur - Osian - Phalodi Road km 2/000 to 121/500 (SH-61) under BOT Annuity Scheme (Jodhpur - Osian - Phalodi)<br />

Item<br />

No.<br />

Description No. L B H Factor Q Unit Rate Amount<br />

1 R-6 Dense Bituminous Macadam<br />

9 Providing and laying Dense Bituminous Macadam on prepared<br />

surface with specified graded crushed aggregates as per table<br />

510 and design mix for base/binder course including loading of<br />

material with Front end loader, heating of binder (including cost<br />

of anti-stripping <strong>com</strong>pound wherever required) aggregate and<br />

filler in hot mix plant 40-60 TPH, transporting the mixed<br />

material by tippers and laying with sensor paver finisher as per<br />

clause 507.3.5 to the required level and grade rolling by self<br />

propelled power rollers and vibratory rollers or pneumatic tyred<br />

roller 150-250KN. TP=0.7MPa to achieve the desired density<br />

(approved by the department) but excluding cost of primer/tack<br />

coat. [MoRTH Specification : Clause 507 & 112]<br />

9.1 Grading I (40 mm nominal size) - Bitumen @ 4.5 % of mix (60/70<br />

for widening of road 1 115314.00 10 0.06 1.02 70572.17<br />

Total=<br />

70572.17 cum 4799.00 338675835.0<br />

2 28 Cost of bitumen to be added when it varies from job mix<br />

formula adopted in any of the above items. Taken 0.5 %<br />

28.2 60/70 Penetration grade 1 70572.17 0.5 2.35 829.223 ton 344944.0 286035490.0<br />

3 9.2 Extra rate for carriage of mixed material additional lead average<br />

30km. -Same as Above<br />

Abstract of Quantites<br />

PART 'A' IMPROVEMENT & WIDENING OF EXISTING ROAD<br />

Strengthening coat at 7th Year (Taking inflation 5% per year)<br />

70572.168 cum 92.35 6517340.00


4 R-6/12 Providing and laying bituminous concrete as per design mix on<br />

prepared surface with specified graded stone as per table 500-18<br />

for wearing course including loading of aggregate with Front<br />

end loader and hot mixing of binder (including cost of antistripping<br />

<strong>com</strong>pound, wherever required) and 3% cement filler<br />

with aggregates in hot mix plant 40-60 TPH Transporting the<br />

mix material with tipper and laying with sensor paver finisher<br />

(as per clouse 507.3.5) to the required level , grades and rolling<br />

with vibratory <strong>com</strong>pactor and pneumatic tyred roller 150-250<br />

KN,TP=0.7 Mpa, to achieve the desired density (approved by<br />

the department) excluding cost of primer/tack coat (MoRTH<br />

Specification : Clause -509 & 112)<br />

12.1 Grading I (19 mm nominal size) - Bitumen @ 5 % of mix &<br />

thickness 50 - 65 mm with lead of mix material 1km<br />

With 60/70 penetration grade straight run bitumen<br />

for road 1 46650.00 10 0.04 18660.00<br />

Total= 18660.00 cum 5757.00 107425620<br />

2 28 Cost of bitumen to be added when it varies from job mix<br />

formula adopted in any of the above items. Taken 0.5 %<br />

28.2 60/70 Penetration grade 1 18660.0 0.5 2.3 214.59 tonne 34494 7402068.00<br />

3 12.2 Extra rate for carriage of mixed material additional lead average<br />

30 km. -Same as Above<br />

18660.00 cum 92.35 1723251.00<br />

Total Cost of I st Strengthening Coat 747779604.0


S.<br />

No.<br />

Improvement of Jodhpur - Osian - Phalodi Road km 2/000 to 121/500 (SH-61) under BOT Annuity Scheme (Jodhpur - Osian - Phalodi)<br />

Item<br />

No.<br />

Renewal coat at 14th Year (Taking inflation 5% per year)<br />

Description No. L B H Factor Q Unit Rate Amount<br />

1 R-6/12 Providing and laying bituminous concrete as per design mix on<br />

prepared surface with specified graded stone as per table 500-18<br />

for wearing course including loading of aggregate with Front<br />

end loader and hot mixing of binder (including cost of antistripping<br />

<strong>com</strong>pound, wherever required) and 3% cement filler<br />

with aggregates in hot mix plant 40-60 TPH Transporting the<br />

mix material with tipper and laying with sensor paver finisher<br />

(as per clouse 507.3.5) to the required level , grades and rolling<br />

with vibratory <strong>com</strong>pactor and pneumatic tyred roller 150-250<br />

KN,TP=0.7 Mpa, to achieve the desired density (approved by<br />

the department) excluding cost of primer/tack coat (MoRTH<br />

Specification : Clause -509 & 112)<br />

Abstract of Quantites<br />

PART 'A' IMPROVEMENT & WIDENING OF EXISTING ROAD<br />

12.1 Grading I (19 mm nominal size) - Bitumen @ 5 % of mix &<br />

thickness 50 - 65 mm with lead of mix material 1km<br />

With 60/70 penetration grade straight run bitumen<br />

for Reconstruction of road 1 115314.00 10 0.04 46125.60<br />

Total= 46125.60 cum 5757.00 265545080.00<br />

2 28 Cost of bitumen to be added when it varies from job mix<br />

formula adopted in any of the above items. Taken 0.5 %<br />

28.2 60/70 Penetration grade 1 46125.6 0.5 2.3 530.44 tonne 34494 18297150.00<br />

3 12.2 Extra rate for carriage of mixed material additional lead average<br />

30 km. -Same as Above<br />

46125.60 cum 92.35 4259700.00<br />

Total Cost of Ist Renewal Cost 288101930.0


Improvement of Jodhpur - Osian - Phalodi Road km 2/000 to 121/500 (SH-61)<br />

under BOT Annuity Scheme (Jodhpur - Osian - Phalodi)<br />

S.No.<br />

1 Start End<br />

2 2000 3550 5.5 1550.00<br />

3 3550 3800 7 250.00<br />

4 3800 6100 5.5 2300.00<br />

5 6100 14950 7 8850.00<br />

6 14950 28100 5.5 13150.00<br />

7 28100 31000 7 2900.00<br />

8 31000 38500 5.5 7500.00<br />

9 38500 44050 3.5 5550.00<br />

10 44050 62500 7 18450.00<br />

11 62500 72500 5.5 10000.00<br />

12 72500 75500 7.0 1150.00<br />

13 75500 76150 Bye Pass 650.00 533<br />

14 76150 80000 7.0 3850.00<br />

15 80000 96000 5.5 16000.00<br />

16 96000 98400 Bye Pass 2400.00 1288<br />

17 98400 101760 5.5 3360.00<br />

18 101760 114775 Bye Pass 13015.00 12133<br />

19 114775 118000 5.5 3225.00<br />

20 118000 119610 7.0 1610.00<br />

21 119610 120160 Bye Pass<br />

(Curve)<br />

550.00 325<br />

22 120160 121500 7.0 1340.00<br />

Total Length<br />

Total length of Toll Road<br />

Detail of BT Road<br />

Chainage Road Width Length (m)<br />

117650.00 14279<br />

117164.00<br />

Bye Pass<br />

Length (m)


1 Total Road Length of 3.5m width<br />

5550.00<br />

2 Total Road Length of 5.5m width<br />

57085.00<br />

3 Total Road Length of 7.0m width<br />

38400.00<br />

4 CC Road in Osian<br />

1850.00<br />

5 Total By Pass<br />

14279.00<br />

Total Length of Tollable Road<br />

Carriageway Detail<br />

117164.00


Improvement of Jodhpur - Osian - Phalodi Road km 2/000 to 121/500 (SH-61) under BOT Annuity Scheme (Jodhpur - Osian -<br />

Phalodi)<br />

Km. 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18<br />

BM/SDBC 60 59 58 57 56 55 54 53 52 51 50 49 48 47 46 45 44<br />

Km. 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35<br />

BM/SDBC 43 42 41 40 39 38 37 36 35 34 33 32 31 30 29 28 27<br />

Km. 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52<br />

BM/SDBC 26 25 24 23 22 21 20 19 18 17 16 15 14 13 12 11 10<br />

Km. 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69<br />

BM/SDBC 9 8 7 6 5 4 3 2 1 0 1 2 3 4 5 6 7<br />

Km. 70 71 72 73 74 75 76 77 78 79 80 81 82 83 84 85 86<br />

BM/SDBC 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24<br />

Km. 87 88 89 90 91 92 93 94 95 96 97 98 99 100 101 102 103<br />

BM/SDBC 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41<br />

Km. 104 105 106 107 108 109 110 111 112 113 114 115 116 117 118 119 120<br />

BM/SDBC 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58<br />

Km. 121 122<br />

BM/SDBC 59 60<br />

LEAD CHART (193/0 - 213/0)<br />

Average Lead 30 Km<br />

Executive Engineer<br />

RSRDCC Unit Jodhpur<br />

Jodhpur


S.<br />

No.<br />

Improvement of Jodhpur - Osian - Phalodi Road km 2/000 to 121/500 (SH-61) under BOT Annuity Scheme (Jodhpur - Osian -<br />

Phalodi)<br />

Item<br />

No.<br />

1 R-2 Clearing Grass and Removal of Rubbish<br />

Description No. L B H Factor Q Unit Rate Amount<br />

2 Clearing grass and removal of rubbish maximum 150mm in<br />

thickness upto a distance of 100 Mtr outside the periphery of the<br />

area by manual means . Note ; where only grass is met with , the<br />

area clear shall be measured & paid for under this item (<br />

MORTH clause 201 )<br />

By Manual Means 1 1000 18 18000.00<br />

Total= 1.80 hectare 9559.00 17207.00<br />

2 Clearing and Grubbing Road Land<br />

R-2/3 Clearing and grubbing road land including uprooting rank<br />

vegetation, grass, bushes, shrubs, saplings and trees girth upto<br />

300 mm, removal of stumps of trees cut earlier and disposal of<br />

unserviceable materials and stacking of serviceable material<br />

upto a lead of 1000m including removal and disposal of top<br />

organic soil not exceeding in 150 mm thickness as per MORTH<br />

specification clause 201<br />

(ii) By Manual Means<br />

(A) In Area of light jungle 1 1000 2 2000.00<br />

Total= 0.20 hectare 28919.00 5784.00<br />

3 R-3/ 3.1 Earth work in excavation, including stacking/disposal of<br />

surplus material with all lifts and lead upto 495 metres,<br />

exclusive of <strong>com</strong>pensation of earth [MoRTH specification :<br />

Clause 301 to 305]<br />

3.1.1.3 Mechanically by power shovel, including mechanical loading<br />

and carriage by tipper/dumper (6T capacity)<br />

Abstract of Quantites<br />

PART 'F CONSTRUCTION OF BY PASSES BY PASSES<br />

1 1000 13 0.5 1.02 6630.00 Cum 61.00 404430.00


4 3.7.4 Extra for watering the earth to bring the earth upto required<br />

O.M.C excluding rolling<br />

5 3.7.5 Extra for rolling to specification with the use of Vibratory roller<br />

when earth is at suitable moisture content with desired field<br />

density not less than 95% of maximum dry density (Modify<br />

Heavy Proctor test), excluding watering.<br />

1 1000 13 0.5 1.02 6500.00 cum 11.00 71500.00<br />

1 1000 13 0.5 1.02 6500.00 cum 24.00 156000.00<br />

4 R-3/6 Compaction of original ground with maximum of six passes of 8-<br />

10 tonnes power roller including filling depression occurring<br />

during rolling [MoRTH Specification : Clause 305.3.4]<br />

New Road 1 1000 13 1.02 13000.00 sqm<br />

Total= 130.00 sqm 199.00 25870.00<br />

5 R-3/3 Dressing of earth work including cutting and filling upto 15cm<br />

[MoRTH Specification Clause 301 to 305]<br />

1 1000 2 1.02 2000.00<br />

20.00 cum 15.00 300.00<br />

6 R-3/4 Box cutting/Trenching the Sub Grade to proper slope, camber<br />

and removing inequalities including removing deleterious stuff<br />

and depositing on the road side slopes (cutting of earth shall be<br />

paid separately in the respective item on the basis of<br />

classification of the excavation done by the Engineer (MoRTH<br />

specification clause 301 to 305)<br />

New Road 1 1000 12 1.02 12000.00<br />

120.00 sqm 41.00 4920.00


R-4 Granular Sub -base with Well Graded Material (Table 400.1)<br />

Plant Mix Method<br />

1 4.3 Providing laying spreading and <strong>com</strong>pacting specified graded<br />

sand, gravel as per Table 400-1,400-2 or any other course<br />

material as per design mix, as per CBR in sub base course<br />

including premixing the material at OMC in wet mix plant,<br />

carriage of mixed material spreading in uniform layers with<br />

motor grader F.E loader on a prepared base and <strong>com</strong>pacting<br />

with vibratory roller to achieve desired density (as per I.S.2720)<br />

including all material, labor, machinery, lighting guarding,<br />

barricading and maintenance of diversion <strong>com</strong>plete.[MoRTH<br />

specification : Clause 401]. By mechanical means with lead up to<br />

1 km<br />

By mechanical means with lead upto 1 km<br />

(i) For Grading I Material<br />

For reconstruction of new road 1 1000 13.00 0.2 1.02 2652.00<br />

Total= 2652.00 cum 490.00 1299480.00<br />

2 3.1 Extra rate for carriage of mixed material additional lead from :-<br />

3.1.1 2nd km to 30th km 1 2652 1 2652.00 Cum/K<br />

m<br />

R-5 Wet Mix Macadam<br />

92.35 244913.00


3 2 Providing, laying, spreading and <strong>com</strong>pacting stone aggregate<br />

for Wet Mix Macadam (as per table 400-10 and 400-11)<br />

specification including premixing the material with water to<br />

OMC in wet mix plant as per approved design mix, carriage of<br />

mixed material by Tipper to site, laying in uniform layers with<br />

motor grader/Front end Loader/paver finisher, in sub base/<br />

base course on a well prepared under base and <strong>com</strong>pacting with<br />

vibratory roller to achieve the desired density including<br />

lighting, guarding, barricading and maintenance of diversion<br />

etc. (MoRTH specification : Clause 406) by mechanical means<br />

with lead up to 1 Km.<br />

By Mechanical Means with 1 km lead 1 1000 10.3 0.25 1.02 2626.50<br />

Total= 2626.50 cum 765.00 2009273.00<br />

4 2.1 Extra rate for carriage of mixed material additional lead from :-<br />

2.1.1 2nd km to 13th km 1 2626.50 1 2626.50 Cum<br />

/Km<br />

B Hard shoulders<br />

5 R-4/2 Providing and laying granular sub-base material having P.I.not<br />

more than 6, including spreading in layers not exceeding 150<br />

mm <strong>com</strong>pacted thickness and consolidation by 8-10 tonne<br />

power roller to required camber and grade including cost of<br />

water and hire charges of machinery, including T&P with all<br />

lead (Compacted thickness to be measured).as per MORTH<br />

specification table 400-1, 400-2 :<br />

2.1 For grading-I with CBR value not less than 30.<br />

to attain 100% proctor density. 2 1000 1 0.15 1.02 306.00<br />

92.35 242558.00<br />

Total= 306.00 Cum 286.00 87516.00


PART 'C' BITUMINOUS COURSES<br />

R-6 Prime Coat<br />

1 6.1 Providing and applying primer coat over prepared surface or<br />

granular base with bitumen emulsion as per IS: 8887 &<br />

manufacturer’s specifications @ 6 kg /10 sqm with a self<br />

propelled or towed bitumen pressure sprayer equipped for<br />

spraying the material uniformly at specified rates and<br />

temperatures as per MoRTH specification CI 502 & 112 (<br />

Including cleaning of road surface )<br />

for new road 1 1000 10 1.02 10200.00<br />

Total= 10200.00 sqm 21.00 214200.00<br />

6.1.1 Add extra to item No. 1 for 1.5 Kg / 10 Sqm emulsion 1 10200 1.5 1.02 15606.00 sqm 2.10 32773.00<br />

Tack Coat<br />

2 6.2 Providing and applying tack coat on the prepared surface, with<br />

bitumen emulsion as per IS : 8887 & manufacturer’s<br />

specifications @ 2 kg /10sqm. With a self propelled or towed<br />

bitumen pressure sprayer equipped for spraying the material<br />

uniformly at specified rates and temperatures as per MoRTH<br />

specification Clause 503 & 112 ( Including cleaning of<br />

bituminous road surface )<br />

for widening of road 1 1000 10 1.02 10200.00<br />

Total=<br />

10200.00 sqm 8.00 81600.00<br />

6.2.1 Add extra for .75Kg / 10 Sqm emulsion 1 10200 7650.00 sqm 2.90 22185.00


3 R-6 Dense Bituminous Macadam<br />

9 Providing and laying Dense Bituminous Macadam on prepared<br />

surface with specified graded crushed aggregates as per table<br />

510 and design mix for base/binder course including loading of<br />

material with Front end loader, heating of binder (including cost<br />

of anti-stripping <strong>com</strong>pound wherever required) aggregate and<br />

filler in hot mix plant 40-60 TPH, transporting the mixed<br />

material by tippers and laying with sensor paver finisher as per<br />

clause 507.3.5 to the required level and grade rolling by self<br />

propelled power rollers and vibratory rollers or pneumatic<br />

tyred roller 150-250KN. TP=0.7MPa to achieve the desired<br />

density (approved by the department) but excluding cost of<br />

primer/tack coat. [MoRTH Specification : Clause 507 & 112]<br />

9.1 Grading II (19 mm nominal size) - Bitumen @ minimum 4.5 % of<br />

mix (60/70 grade) & thickness 50 - 75 mm<br />

for new road 1 1000 10 0.075 1.02 765.00<br />

Total=<br />

765.00 cum 4799.00 3671235.0<br />

3a 28 Cost of bitumen to be added when it varies from job mix<br />

formula adopted in any of the above items. Taken 0.5 %<br />

28.2 60/70 Penetration grade 1 765.00 0.5 2.35 8.99 ton 34494.0 310058.0<br />

4 9.2 Extra rate for carriage of mixed material additional lead average<br />

30 km. -Same as Above<br />

765.000 cum 92.35 70648.00


5 R-6/12 Providing and laying bituminous concrete as per design mix on<br />

prepared surface with specified graded stone as per table 500-<br />

18 for wearing course including loading of aggregate with Front<br />

end loader and hot mixing of binder (including cost of antistripping<br />

<strong>com</strong>pound, wherever required) and 3% cement filler<br />

with aggregates in hot mix plant 40-60 TPH Transporting the<br />

mix material with tipper and laying with sensor paver finisher<br />

(as per clouse 507.3.5) to the required level , grades and rolling<br />

with vibratory <strong>com</strong>pactor and pneumatic tyred roller 150-250<br />

KN,TP=0.7 Mpa, to achieve the desired density (approved by<br />

the department) excluding cost of primer/tack coat (MoRTH<br />

Specification : Clause -509 & 112)<br />

12.1 Grading I (19 mm nominal size) - Bitumen @ 5 % of mix &<br />

thickness 50 - 65 mm with lead of mix material 1km<br />

With 60/70 penetration grade straight run bitumen<br />

for Reconstruction of road 1 1000 10 0.04 400.00<br />

Total= 400.00 cum 5757.00 2302800.00<br />

5a 28 Cost of bitumen to be added when it varies from job mix<br />

formula adopted in any of the above items. Taken 0.5 %<br />

28.2 60/70 Penetration grade 1 400.00 0.5 2.3 4.60 tonne 34494 158673.00<br />

6 12.2 Extra rate for carriage of mixed material additional lead average<br />

30 km. -Same as Above<br />

400.00 cum 92.35 36940.00<br />

TOTAL<br />

11470863.00<br />

Total length of By Pass Road (Mathania, Ummed Nagar, Osian ) km 14.28<br />

Slope protection 16007890.4<br />

Total cost of By Pass Road 179800343.1


Extra Work Required for Slope Protection<br />

1 R-3/ 3.1 Earth work in excavation, including stacking/disposal of<br />

surplus material with all lifts and lead upto 495 metres,<br />

exclusive of <strong>com</strong>pensation of earth [MoRTH specification :<br />

Clause 301 to 305]<br />

3.1.1.3 Mechanically by power shovel, including mechanical loading 1 1200 13 2.5 1.02 39000.00<br />

1 1200 6 2.5 1.02 18000.00<br />

Total= 57000.00 cum 61.00 3477000.00<br />

2 3.7.4 Extra for watering the earth to bring the earth upto required<br />

O.M.C excluding rolling<br />

3 3.7.5 Extra for rolling to specification with the use of Vibratory roller<br />

when earth is at suitable moisture content with desired field<br />

density not less than 95% of maximum dry density (Modify<br />

Heavy Proctor test), excluding watering.<br />

1 57000.0 57000.00 cum 11.00 627000.00<br />

1 57000.0 57000.00 cum 24.00 1368000.00<br />

4 R-3/6 Compaction of original ground with maximum of six passes of 8-<br />

10 tonnes power roller including filling depression occurring<br />

during rolling [MoRTH Specification : Clause 305.3.4]<br />

New Road 1 1200 25 1.02 30000.00 sqm<br />

Total= 300.00 sqm 199.00 59700.00<br />

5 R-3/3 Dressing of earth work including cutting and filling upto 15cm<br />

[MoRTH Specification Clause 301 to 305]<br />

Stone Pitching on Slope<br />

6 R-11 /<br />

1.1.1<br />

1 1200 2 1.02 2400.00<br />

Earth work in excavation for foundation of structure <strong>com</strong>plete<br />

with all lift, dewatering shoring and shuttering etc .including<br />

refilling of trenches in 25.mm layers, ramming, watering and<br />

disposal of surplus soil within a lead of 1000 meters, as per<br />

drawing and technical specification.[MoRTH Specification :<br />

Clause : 304]<br />

For Embankment above 2.5m high 1 1200.00 1.20 0.90 1296.00<br />

24.00 cum 15.00 360.00


Sloped length 6.70m taken for 3.0m average height<br />

embankment. c/c of shutes taken 5.0m. =1200/5 = 240<br />

7 R-14/5 Providing and laying graded stone aggregate Filter Material<br />

underneath pitching on slopes <strong>com</strong>plete as per drawing and<br />

technical Specification [MoRTH Specification : Clause 2504]<br />

8 R-14/<br />

4.1<br />

9 R-10/<br />

10.3<br />

10 R-10/<br />

10.10.1<br />

Providing and laying Pitching on slopes <strong>com</strong>plete as per<br />

drawing and technical -specification. [MOST Specification :<br />

Clause : 2504] With<br />

R.R.Stone , weighing not less than 40 Kg, thickness not less than<br />

150 mm (Specific gravity not less than 2.65).<br />

240 6.70 0.85 0.45 615.06<br />

Total =<br />

1911.06 Cum 95.00 181550.70<br />

1 996.00 6.70 0.15 1000.98 cum 617.00 617604.66<br />

1 996.00 6.70 0.30 2001.96 cum 754.00 1509477.84<br />

Providing and laying Plain cement concrete M15 mix with stone<br />

aggregate 20mm nominal size mechanically mixed and vibrated,<br />

in foundation up to a depth of 1.50 below Ground level and or<br />

1.50 meters above ground/bed level.<br />

M15 Grade Mix 1 1200.00 0.45 0.15 81.00<br />

1 1200.00 1.20 0.15 216.00<br />

240 6.70 0.85 0.15 205.02<br />

240 6.70 0.60 0.08 72.36<br />

2 1200.00 0.45 0.08 86.40<br />

Total =<br />

Providing and laying Random Rubble stone masonry in cement<br />

sand mortar 1:3, in foundation up to a depth of 1.50 meters and<br />

also 1.50 meters above Ground /Bed level [MoRTH<br />

Specification : Clause 1000/1400]<br />

Toe wall 1 1200.00 0.90 0.30 324.00<br />

1 1200.00 0.75 0.30 270.00<br />

660.78 cum 2783.00 1838950.74


11 R-<br />

10/10.1<br />

2+10.13<br />

1 1200.00 0.60 0.30 216.00<br />

1020 * 6.7 = 1608 2 1608.00 0.30 0.45 434.16<br />

Random Rubble masonry in cement sand mortar 1:3 in<br />

superstructures upto a height of 4 metres or part thereof above<br />

1.50m level from Ground/Bed level.[MoRTH Specfication :<br />

Clause 1000/1400]<br />

Toe Wall 1 1200.00 0.45 0.45 243.00<br />

At Shoulders 1 1164.00 0.45 0.75 392.85<br />

12 R-10/14 Providing Cement plaster 12mm thick in cement mortar (1:3) at<br />

all levels [MoRTH Specification: Clause:1000/1300]<br />

Stone Pitching on Shoulder<br />

13 R-14/5 Providing and laying graded stone aggregate Filter Material<br />

underneath pitching on slopes <strong>com</strong>plete as per drawing and<br />

technical Specification [MoRTH Specification : Clause 2504]<br />

14 R-14/<br />

4.1<br />

Providing and laying Pitching on slopes <strong>com</strong>plete as per<br />

drawing and technical -specification. [MOST Specification :<br />

Clause : 2504] With<br />

R.R.Stone , weighing not less than 40 Kg, thickness not less than<br />

150 mm (Specific gravity not less than 2.65).<br />

Total Cost<br />

Total =<br />

Total =<br />

2 240.00 6.70 1.05 3376.80<br />

1 1164.00 1.05 1222.20<br />

1 1200.00 1.05 1260.00<br />

Total =<br />

1244.16 cum 2586.00 3217397.76<br />

635.85 cum 2784.00 1770206.40<br />

5859.00 sqm 99.00 580041.00<br />

1 1164.00 2.05 0.15 357.93 sqm 617.00 220842.81<br />

1 1164.00 2.05 0.30 715.86 cum 754.00 539758.44<br />

16007890.4


Improvement of Jodhpur - Osian - Phalodi Road km 2/000 to 121/500 (SH-61) under BOT Annuity Scheme<br />

PART 'D' TRAFFIC SIGNS, MARKINGSAND OTHER ROAD APPURTENANCES<br />

S. No. BSR No. Description No. L B H Qty. Unit Rate Amount<br />

1 R-7/13 Supply & fixing of precast reinforced cement concrete M-<br />

15 grade kilometre stone of standard design as per IRC: 8-<br />

1980, fixing in position in cement concrete 1:4:8 including<br />

painting and printing etc.<br />

a 13.1 5 th Km. Stone (size 50 x1 52x25 cm) 0.2 1.00 0.20 Each 1743.00 348.60<br />

b 13.2 Ordinary Km. Stone 1 1.00 1.00 Each 1012.00 1012.00<br />

c 13.3 200m stone 4 1.00 4.00 Each 303.00 1212.00<br />

2 R-7/25 Supplying and fixing delineator with 30cm. outer dia<br />

RCC hume pipe NP-2 (as per IS 458-1971) pipe 1.0m.<br />

Long, 40cm. embedded in cement concrete 1:4:8. block of<br />

size 50cm.x50cm.x40cm. including excavation upto 40 cm.<br />

depth. The inside of pipe shall be filled with cement<br />

concrete 1:4:8 (1 cement : 4 coarse sand : 8 coarse<br />

aggregate with nominal size aggregate 20mm size) top<br />

with semi circular humping. The pipes shall be painted<br />

white/black with enamel paint with white round<br />

reflector 7.5 cm. dia at top on side facing the traffic and<br />

opposite side ( as per IRC-79 ).<br />

(Jodhpur - Osian - Phalodi)<br />

Abstract of Cost<br />

1 15.00 Each 350.00 5250.00


3 R-7/12 Providing and laying of hot applied thermoplastic<br />

<strong>com</strong>pound inclusive type I reflectrosing glass beads as<br />

per table 800-3, 800-4 applied in uniform thickness of at<br />

least 2.5 mm and spread uniformly with reflectorising<br />

glass beads type II in addition @ 250 gms per Sqm with a<br />

road marking machine as per IRC: 35 <strong>com</strong>plete with<br />

traffic diversion arrangement as per MORTH<br />

specification clause 803.4.<br />

Centre Line (Straight Portion) 1 850.00 0.33 0.15 42.08<br />

Centre Line (Curve Portion) 1 150.00 0.50 0.15 11.25<br />

Edge Line 2 1000.00 0.10 200.00<br />

Vertical Strips & Others 25.00<br />

Total 278.33 Sqm 543.00 151130.48<br />

4 R-7/18 Supply of centerline raised pavement marker (RPM) size<br />

125 x 75 x 20 mm made out of aluminium alloy duly<br />

white power costing paint with two side reflective having<br />

fixing provision with nail <strong>com</strong>plete in all respect.<br />

For Toll Plaza 4 8.00 20.00 48.00 13.33<br />

13.33 Each 350.00 4666.67<br />

5 R-7/16 Supplying of Cat's eye made of aluminium alloy size 75 x<br />

100 x 22 mm having 21 biconvex lenses embedded in<br />

circular disk of AS plastic on each side.<br />

On curved reach i.e. 15% on 7.5 m c/c on both the edge<br />

lines<br />

2 150.00 7.50 40.00<br />

40.00 Each 154.00 6160.00


6 7.17 Providing overhead signs with a corrosion resistant 2 mm<br />

thick aluminium alloy sheet with high intensity grade<br />

retro- reflective sheeting of encapsulated lens exclusive<br />

lettering, border & signs type with vertical and lateral<br />

clearance installed over a designed support system of<br />

aluminium alloy or galvanised steel trestles and trusses of<br />

sections and type as per structural design requirements<br />

and approved plans as per MORTH specifications clause<br />

802.2, 802.3 & 802.7.<br />

Boards required - toll road begins and toll road ends at<br />

Toll road begins and toll road ends at - 2.00<br />

Toll Plaza ahead -1 km - 8.00<br />

Toll Plaza ahead -500m - 8.00<br />

Total Board Required 18.00<br />

a 7.48 Supply of High Intensity retro reflecting Type IV sign<br />

plate made out of 2.0 mm thick aluminium sheet face to<br />

be fully covered with blue / green high intensity grade<br />

retro reflective sheet and logo/ matters, boarder made of<br />

with similar type of white sheeting after etching<br />

treatment of aluminium sheet , the back side is to be<br />

painted with epoxy grey paint. The plate is to be fixed on<br />

40x40x5 mm angle iron frame with help of aluminium<br />

rivets.<br />

Aluminium Alloy plate for over head sign 0.15 1.70 3.40 0.88<br />

0.88 Sqm 5142.00 4547.16<br />

b 7.17.1 Truss & Vertical Support<br />

1 0.15 1.50 0.23<br />

0.23 MT 64560.00 14816.15


8 R-7/34 Providing and erecting a "W" metal beam crash barrier<br />

<strong>com</strong>prising of 3 mm thick corrugated sheet metal beam<br />

rail , 70 cm above road/ ground level, fixed on ISMC<br />

series channel vertical post, 150 x 75 x 5 mm spaced 2 mm<br />

centre-to-centre, 1.8 m high, 1.1 m below ground / road<br />

level, all steel parts and fitments to be galvanised by hot<br />

dip process, all fittings to conform to IS: 1367 and IS: 1364<br />

, metal beam rail to be fixed on the vertical post with a<br />

spacer of channel section 150 x 75 x 5 mm, 330 mm long<br />

<strong>com</strong>plete as per MORTH specification Clause 810.<br />

Length of crash barrier = 2 1200.00 1.25 117.65 25.50<br />

9 7.15 Providing and fixing of retro- reflectorised inclusive<br />

cautionary, mandatory and informatory sign as per IRC-<br />

67 made of high intensity grade sheeting lettering, border<br />

& signs fixed over aluminium sheeting, 1.5 mm thick,<br />

fixed on mild steel angle iron frame 50mmx50mmx6mm<br />

supported on a mild steel angle iron post<br />

75mmx75mmx6mm upto the top of sign board, length of<br />

post from bottom of sign board is 2.85m. upto foundation<br />

level post duly painted in black & white synthetic<br />

enamel. fixed to the ground by means of properly<br />

designed foundation with M-15 grade cement concrete 45<br />

Cm x 45 Cm x 60Cm, 60 cm below ground level as per<br />

approved drawing & as per MORTH specification Cl.<br />

801.<br />

a 7.15.6 60cm x 60cm square<br />

For curves - 1 15.00 15.00<br />

For Culverts & Bridges - 1 37.00 37.00<br />

For Schools 1 13.00 13.00<br />

For Leftl Right roads -& Cross Roads 1 22.00 22.00<br />

Total No. of boards - 87.00<br />

25.50 Rmt 2829.00 72137.70<br />

0.74 Each 3820.00 2824.82


7.15.3 60cm Circular Prohibitory<br />

For Speed limit - 1 7.00 7.00<br />

For No overtaking - 1 20.00 20.00<br />

Total No. of boards - 27.00<br />

10 7.16 Providing and erecting direction and place identification<br />

retro - reflectorised sign as per IRC:67 made of high<br />

intensity grade sheeting exclusive of lettering, border &<br />

signs fixed over aluminium sheeting, 2 mm thick fixed on<br />

a mild steel angle iron frame 50mmx50mmx6mm<br />

supported on mild steel angle iron post 75 x 75 x 6 mm<br />

upto the top of sign board, length of post from bottom of<br />

sign board is 2.85 m. upto foundation level post duly<br />

painted in black and white synthetic enamel alternate<br />

ship 30cm. wide fixed to the ground by means properly<br />

designed foundation with M-15 grade cement concrete<br />

45cm x 45cm x 60 Cm , 60 Cm below ground level as per<br />

approved drawing & as per MORTH specifications clause<br />

801.<br />

7.16.2 Double angle post<br />

a 7.16.2.2 90 cm. X 60 cm.<br />

For Public telephones - 2 0.25 0.50<br />

For Filling stations - 1 14.00 14.00<br />

For hospitals - 1 2.00 2.00<br />

For police stations - 1 4.00 4.00<br />

Temples 1 20.00 20.00<br />

Total No. of boards - 40.50<br />

0.23 Each 3308.00 759.17<br />

0.34 Each 4600.00 1583.51<br />

b 7.16.2.4 120 cm. X 75 cm.<br />

No. of boards - 2 0.25 0.50<br />

0.50 Each 7666.00 3833.00


c 7.16.2.6 150 cm. X 120 cm.<br />

No. of locations where one road is crossing is. _<br />

No. of boards required - 1 22.00 22.00<br />

0.19 Each 15332.00 2867.01<br />

d 7.16.2.7 180 cm. X 120 cm.<br />

No. of locations where two roads are crossing are -<br />

Total No. of boards required - 5 x 2 = 10 1 5.00 5.00<br />

0.04 Each 18399.00 781.94<br />

11 7.20 Supply & fixing of Shevron sign of size 600x450mm<br />

made out of alluminium sheet 2mm thick with fixing<br />

provision on M.S. angle iron post 50x50x6mm, 3M. long<br />

screwed with stainless steel nut bolts of 8 M. dia, plate is<br />

covered by high intensity grade retro-reflective sheeting<br />

& black reflective arrows, <strong>com</strong>plete in all respect.<br />

Total Curve Length<br />

(Boards @ distance of 10m c/c)<br />

150.00<br />

Total No. of boards required - 30.00 Each 3200.00 96000.00<br />

12 7.5 Painting & printing letters on kilometer stone with first<br />

quality synthetic enamel paint as per MoRTH<br />

specification clause 800.<br />

a 7.5.1 5th Kilometer stone. 0.20 Each 323.00 64.60<br />

b 7.5.2 Ordinary Kilometer stone. 1.00 Each 171.00 171.00<br />

c 7.5.3 200 meter Stone. 4.00 Each 22.00 88.00<br />

Total<br />

370253.80<br />

Total length of Road km 117.65<br />

Total cost of Road Furniture 43560359.3


Improvement of Jodhpur - Osian - Phalodi Road km 2/000 to 121/500 (SH-61) under BOT Annuity<br />

Scheme (Jodhpur - Osian - Phalodi)<br />

PART 'B' - Part 2 DRAINS<br />

S. No. BSR No. Description No. L B H Qty. Unit Rate<br />

1000 mt.<br />

Amount<br />

1 R-3/10.1 Earth work in excavation in foundation trenches etc.in<br />

drains and channels etc. not exceeding 2m.depth,<br />

including dress-sing of bottom and sides of trenches,<br />

stacking the excavated soil 3m. Clear from the edge of<br />

excavation including disposal surplus soil as directed<br />

within a lead of 1000 metres [Most Specification : Clause<br />

301,304]<br />

3.10.1 Ordinary soil<br />

2 R-10/1 Providing and laying mechnically mixed and vibrated<br />

Cement Concrete in foundation upto a depth of 1.5<br />

metres below ground level and 1.50 metres above<br />

Ground/Bed level.[MoRTH Specification : Clause<br />

1000/1700]<br />

10.1.2a Cement concrete 1:3:6 mix crushed stone aggregates<br />

20mm nominal size.<br />

3 R-<br />

10/10.2<br />

Abstract of Cost<br />

1 1000.00 1.50 0.85 1275.00<br />

1275.00 Cum 74.00 94350.00<br />

1 1000.00 1.50 0.10 150.00<br />

150.00 Cum 2526.00 378900.00<br />

Providing and laying Plain cement concrete M15 mix<br />

with stone aggregate 20mm nominal size mechnically<br />

mixed and vibrated, in foundation upto a depth of 1.50<br />

below Ground level and or 1.50 meters above<br />

ground/bed level.<br />

Bed of Drain 1 1000.00 0.30 0.08 22.50<br />

22.50 Cum 2419.00 54427.50


4 R-10/12 Providing and laying Random Rubble masonry in<br />

foundation upto a depth of 1.50 metres and 1.50 metres<br />

above Ground /Bed level.[MoRTH Specfication: Clause<br />

1000/1400]<br />

In cement sand mortar 1:3<br />

4 R-10/16 Providing Cement plaster 12mm thick in cement mortar<br />

1:3 at all levels [MoRTH Specfication: Clause:1000/1300]<br />

5 R-10/23 Reinforced cement concrete M30 mix with stone<br />

aggregate 20mm nominal size mechnically mixed and<br />

vibrated for reinforced concrete work in slab in<br />

superstructure at any level excluding steel reinforcement<br />

but including center-ing and shuttering laid in position<br />

[MoRTH Specification : Clause 1000/1700]<br />

2 1000.00 0.40 0.75 600.00<br />

600.00 Cum 2586.00 1551600.00<br />

2 1000.00 0.75 1500.00<br />

1500.00 Sqm 99.00 148500.00<br />

Drain Top 1 1000.00 0.3 0.075 22.50<br />

Drain Slab (50% taken for the City/Built up area) 50% 1000.00 1.1 0.15 82.50<br />

105.00 Cum 4045.00 424725.00<br />

6 R-10/61 Providing and laying Steel reinforcement at any level in<br />

foundation <strong>com</strong>plete as per drawing and technical<br />

Specification.[MoRTH Specification : Section: 1600(N)]<br />

6.2 Cold Twisted bars (Taking 65 kg/Cum)<br />

1 105.00 65 6.83 Ton 51636.00 352415.70<br />

Total<br />

3004918.20<br />

Total length of Drain (1 side) (existing 180m at Mathania) km 6.52<br />

Total cost of Drain 19592066.7


Improvement of Jodhpur - Osian - Phalodi Road km 2/000 to 121/500 (SH-61) under BOT Annuity Scheme (Jodhpur - Osian<br />

- Phalodi)<br />

PART 'C' CEMENT CONCRETE PAVEMENT<br />

1000 mt.<br />

Description No. L B H Q Unit Rate Amount<br />

S.<br />

No.<br />

Item<br />

No.<br />

1 Granular Sub-base<br />

Plant Mix Method<br />

R-4/2 Providing laying spreading and <strong>com</strong>pacting specified graded<br />

sand, gravel as per Table 400-1,400-2 or any other course<br />

material as per design mix, as per CBR in sub base course<br />

including premixing the material at OMC in wet mix plant,<br />

carriage of mixed material spreading in uniform layers with<br />

motoe grader F.E loader on a prepared base and <strong>com</strong>pacting<br />

with vibratory roller to achieve desired density (as per I.S.2720)<br />

including all material, labour, machinery, lighting guarding,<br />

barricading and maintenance of diversion <strong>com</strong>plete.[MoRTH<br />

specification : Clause 401].<br />

2.1 For Grading I Material<br />

Abstract of Quantites<br />

CC pavement 1 1000 13.5 0.15 2025.00<br />

Total = 2025.00 cum 490.00 992250.00<br />

2 R-16/1 Construction of dry lean cement concrete sub-base over a<br />

prepared sub-grade with coarse and fine aggregate conforming<br />

to IS: 383, the size of coarse aggregate not exceeding 25 mm ,<br />

aggregate cement ratio not to exceed 15:1 , aggregate gradation<br />

after blening to be as per Table 600-1, cement content not to be<br />

less than 150 Kg/Cum, optimum moisture content to be<br />

determined during trial length construction, concrete strength<br />

not to be less than 10 Mpa at 7 days, mixed in a batching plant<br />

as per mix design, transported to site, laid with a hydrostatic<br />

paver with electronic sensor, <strong>com</strong>pacting with 8-10 tonne<br />

vibratory roller, finishing and curing <strong>com</strong>plete as per MoRTH<br />

specification clause 601.<br />

1.3 CC pavement 1 1000 12 0.15 1800.00 Cum 1554.00 2797200.00


3 Cement Concrete Pavement<br />

R-16/<br />

16.5<br />

5 R-<br />

7/47.3<br />

Providing and Laying un-reinforced, dowel jointed, plain<br />

cement concrete pavement over a prepared sub-base with 43<br />

grade cement @ 400 kg per cum, coarse and fine aggregate<br />

conforming to IS:383, maximum size of coarse aggregate not<br />

exceeding 25mm, mixed in a batching and mixing plant as per<br />

approved mix design, transported to site, laid with a fixed form<br />

or slip form paver, spread, <strong>com</strong>pacted and finished in a<br />

continuous operation including provision of contraction,<br />

expansion, construction and longitudinal joints, joint filler,<br />

separation membrane, sealant primer, joint sealant, debonding<br />

strip, dowel bar, tie rod, admixtures and vacuum processing<br />

pump as approved, curing <strong>com</strong>pound, finishing to lines and<br />

grades as per drawing as per MoRTH Specification : Clause No.<br />

602, 112.<br />

2.4 CC pavement 1 1000 7 0.3 2100.00 Cum 4165.00 8746500.00<br />

Providing and fixing of Precast concrete interlocking blocks of<br />

100mm thick manufactured from fully <strong>com</strong>puterized automatic<br />

stationery hydraulic vibro pressed machine & full <strong>com</strong>puterized<br />

automatic batching plant of class A-I as per BS: 6717-2001. The<br />

C.C. interlocking paving blocks be laid on average 50mm thick<br />

bed of coarse sand and the joint is to be filled with fine sand.<br />

Laying procedure on <strong>com</strong>pacted sub base as defined. The work<br />

includes earth work in cutting of B/T road, cutting of WBM<br />

road and disposal of unserviceable material with all leads & lifts<br />

and stacking of serviceable material <strong>com</strong>plete job is to be<br />

executed as per the instructions of Engineer-in-charge. The rates<br />

to be inclusive of all lead, lifts & taxes General specification of<br />

Blocks:<br />

1. Shape : As specified by Engineer-in-charge<br />

2. Tensile splitting strength and breaking load as per BS: 6717-<br />

2001<br />

3. Colour : Grey cement natural colour<br />

4. Variation in Dimension : Less than 1.6mm<br />

5. Variation in thickness : Less than 3.2mm


3 R-3/<br />

3.1<br />

New Carriageway 2 1000 1.5 3000.00<br />

Earth work in excavation, including stacking/disposal of<br />

surplus material with all lifts and lead upto 495 metres,<br />

exclusive of <strong>com</strong>pensation of earth [MoRTH specification :<br />

Clause 301 to 305]<br />

3000.00 Cum 587.00 1761000.00<br />

3.1.1.3 Mechanically by power shovel, including mechanical loading<br />

and carriage by tipper/dumper (6T capacity)<br />

New Carriageway 1 1000.0 7.5 0.5 3750.00<br />

3750.00 Cum 49.00 183750.00<br />

4 3.7.4 Extra for watering the earth to bring the earth upto required<br />

O.M.C excluding rolling<br />

7.0 m existing Road 1 1000.0 6 0.5 3000.00<br />

3000.00 cum 9.00 27000.00<br />

5 3.7.5 Extra for rolling to specification with the use of Vibratory roller<br />

when earth is at suitable moisture content with desired field<br />

density not less than 95% of maximum dry density (Modify<br />

Heavy Proctor test), excluding watering.<br />

3000.00 cum 22.00 0.00<br />

6 R-3/6 Compaction of original ground with maximum of six passes of 8-<br />

10 tonnes power roller including filling depression occurring<br />

during rolling [MoRTH Specification : Clause 305.3.4]<br />

7.0 m existing Road 1 1000.0 6 6000.00<br />

Total= 60.00 sqm 188.00 11280.00<br />

G. total =<br />

14518980.0<br />

Total length of CC Road km 4.75<br />

Total cost of Rigid Pavement 68965155.0


Improvement of Jodhpur - Osian - Phalodi Road km 2/000 to 121/500 (SH-61) under<br />

BOT Annuity Scheme (Jodhpur - Osian - Phalodi)<br />

1 Osian 73250 75100 1850.00 4 Lane<br />

74100 74550 -450.00 2 Lane<br />

Existing<br />

2 Mathania 102000 103500 1500.00 2 Lane<br />

Equivalent 2 Lane CC road Length<br />

LOCATION OF CC ROAD<br />

S.No. LOCATION<br />

CHAINAGE<br />

LENGTH<br />

(M)<br />

Start End<br />

4750.00<br />

Remarks


S.<br />

No.<br />

Improvement of Jodhpur - Osian - Phalodi Road km 2/000 to 121/500 (SH-61) under BOT Annuity Scheme (Jodhpur - Osian -<br />

Phalodi)<br />

PART 'G' Improvement of curves<br />

Item<br />

No.<br />

Description No. L B H Q Unit Rate Amount<br />

3 R-3/ 3.1 Earth work in excavation, including stacking/disposal of<br />

surplus material with all lifts and lead upto 495 metres,<br />

exclusive of <strong>com</strong>pensation of earth [MoRTH specification :<br />

Clause 301 to 305]<br />

3.1.1.3 Mechanically by power shovel, including mechanical loading<br />

and carriage by tipper/dumper (6T capacity)<br />

Verical Curve 1 65848.13 65848.13<br />

Horizontal Curve 1 8750.15 8750.15<br />

74598.28 Cum 61.00 4550496.00<br />

3 3.7 Extra for laying earth as per specification for <strong>com</strong>paction in 200<br />

mm thick loose layers and dressing [MoRTH Specification<br />

Clause 305.3.5].<br />

BY MECHANICAL MEANS, using Motor Grader, from earth in<br />

stock piles with all lead and lift but excluding rolling and<br />

watering.<br />

Verical Curve 1 11357.29 11357.29<br />

Horizontal Curve 1 7934.26233 7934.26<br />

Total= 19291.56 cum 15.00 289374.00<br />

4 3.7.4 Extra for watering the earth to bring the earth upto required<br />

O.M.C excluding rolling<br />

5 3.7.5 Extra for rolling to specification with the use of Vibratory roller<br />

when earth is at suitable moisture content with desired field<br />

density not less than 95% of maximum dry density (Modify<br />

Heavy Proctor test), excluding watering.<br />

Abstract of Quantites<br />

1 19291.56 19291.56 cum 11.00 212208.00<br />

1 19291.56 19291.56 cum 24.00 0.00


4 R-3/6 Compaction of original ground with maximum of six passes of 8-<br />

10 tonnes power roller including filling depression occurring<br />

during rolling [MoRTH Specification : Clause 305.3.4]<br />

Verical Curve 1 16418.04 13 213434.52<br />

Horizontal Curve 1 3071.58 10 30715.80<br />

Total= 2441.50 sqm 199.00 485860.00<br />

5 R-3/3 Dressing of earth work including cutting and filling upto 15cm<br />

[MoRTH Specification Clause 301 to 305]<br />

Verical Curve 1 16418.04 2 32836.08<br />

Horizontal Curve 2 3071.58 3 18429.48<br />

512.66 cum 15.00 7690.00<br />

6 R-3/4 Box cutting/Trenching the Sub Grade to proper slope, camber<br />

and removing inequalities including removing deleterious stuff<br />

and depositing on the road side slopes (cutting of earth shall be<br />

paid separately in the respective item on the basis of<br />

classification of the excavation done by the Engineer (MoRTH<br />

specification clause 301 to 305)<br />

Verical Curve 1 16418.04 12 197016.48<br />

Horizontal Curve 2 3071.58 12 73717.92<br />

270734.40 sqm 41.00 11100111.00


R-4 Granular Sub -base with Well Graded Material (Table 400.1)<br />

Plant Mix Method<br />

1 4.3 Providing laying spreading and <strong>com</strong>pacting specified graded<br />

sand, gravel as per Table 400-1,400-2 or any other course<br />

material as per design mix, as per CBR in sub base course<br />

including premixing the material at OMC in wet mix plant,<br />

carriage of mixed material spreading in uniform layers with<br />

motor grader F.E loader on a prepared base and <strong>com</strong>pacting<br />

with vibratory roller to achieve desired density (as per I.S.2720)<br />

including all material, labor, machinery, lighting guarding,<br />

barricading and maintenance of diversion <strong>com</strong>plete.[MoRTH<br />

specification : Clause 401]. By mechanical means with lead up to<br />

1 km<br />

By mechanical means with lead upto 1 km<br />

(i) For Grading I Material<br />

Verical Curve 1 14967.75 14967.75<br />

Horizontal Curve 1 5925.45 5925.45<br />

Total= 20893.20 cum 490.00 10237668.00<br />

2 3.1 Extra rate for carriage of mixed material additional lead from :-<br />

3.1.1 2nd km to 30th km 1 20893.1987 1 20893.20 Cum<br />

/Km<br />

92.35 1929487.00


R-5 Wet Mix Macadam<br />

3 2 Providing, laying, spreading and <strong>com</strong>pacting stone aggregate<br />

for Wet Mix Macadam (as per table 400-10 and 400-11)<br />

specification including premixing the material with water to<br />

OMC in wet mix plant as per approved design mix, carriage of<br />

mixed material by Tipper to site, laying in uniform layers with<br />

motor grader/Front end Loader/paver finisher, in sub base/<br />

base course on a well prepared under base and <strong>com</strong>pacting with<br />

vibratory roller to achieve the desired density including lighting,<br />

guarding, barricading and maintenance of diversion etc.<br />

(MoRTH specification : Clause 406) by mechanical means with<br />

lead up to 1 Km.<br />

By Mechanical Means with 1 km lead<br />

Verical Curve 1 16967.52 16967.52<br />

Horizontal Curve 2 4858.14 9716.27<br />

Total= 26683.80 cum 765.00 20413105.00<br />

4 2.1 Extra rate for carriage of mixed material additional lead from :-<br />

2.1.1 2nd km to 13th km 1 26683.80 1 26683.80 Cum<br />

/Km<br />

B Hard shoulders<br />

5 R-4/2 Providing and laying granular sub-base material having P.I.not<br />

more than 6, including spreading in layers not exceeding 150<br />

mm <strong>com</strong>pacted thickness and consolidation by 8-10 tonne<br />

power roller to required camber and grade including cost of<br />

water and hire charges of machinery, including T&P with all<br />

lead (Compacted thickness to be measured).as per MORTH<br />

specification table 400-1, 400-2 :<br />

2.1 For grading-I with CBR value not less than 30.<br />

to attain 100% proctor density.<br />

Verical Curve 2 16418.04 1.5 0.15 7388.12<br />

Horizontal Curve 1 3071.58 1.5 0.15 691.11<br />

92.35 2464249.00


Total= 8079.22 Cum 286.00 2310658.00


PART 'C' BITUMINOUS COURSES<br />

R-6 Prime Coat<br />

1 6.1 Providing and applying primer coat over prepared surface or<br />

granular base with bitumen emulsion as per IS: 8887 &<br />

manufacturer’s specifications @ 6 kg /10 sqm with a self<br />

propelled or towed bitumen pressure sprayer equipped for<br />

spraying the material uniformly at specified rates and<br />

temperatures as per MoRTH specification CI 502 & 112 (<br />

Including cleaning of road surface )<br />

Verical Curve 1 16418.04 7 114926.28<br />

Horizontal Curve 1 3071.58 7 21501.06<br />

Total= 136427.34 sqm 21.00 2864975.00<br />

6.1.1 Add extra to item No. 1 for 1.5 Kg / 10 Sqm emulsion 1 136427 1.5 204641.01 sqm 2.10 429747.00<br />

Tack Coat<br />

2 6.2 Providing and applying tack coat on the prepared surface, with<br />

bitumen emulsion as per IS : 8887 & manufacturer’s<br />

specifications @ 2 kg /10sqm. With a self propelled or towed<br />

bitumen pressure sprayer equipped for spraying the material<br />

uniformly at specified rates and temperatures as per MoRTH<br />

specification Clause 503 & 112 ( Including cleaning of<br />

bituminous road surface )<br />

Verical Curve 1 16418.04 7 114926.28<br />

Horizontal Curve 1 3071.58 7 21501.06<br />

Total= 136427.34 sqm 8.00 1091419.00<br />

6.2.1 Add extra for .75Kg / 10 Sqm emulsion 1 136427.34 102320.51 sqm 2.90 296730.00


3 R-6 Dense Bituminous Macadam<br />

9 Providing and laying Dense Bituminous Macadam on prepared<br />

surface with specified graded crushed aggregates as per table<br />

510 and design mix for base/binder course including loading of<br />

material with Front end loader, heating of binder (including cost<br />

of anti-stripping <strong>com</strong>pound wherever required) aggregate and<br />

filler in hot mix plant 40-60 TPH, transporting the mixed<br />

material by tippers and laying with sensor paver finisher as per<br />

clause 507.3.5 to the required level and grade rolling by self<br />

propelled power rollers and vibratory rollers or pneumatic tyred<br />

roller 150-250KN. TP=0.7MPa to achieve the desired density<br />

(approved by the department) but excluding cost of primer/tack<br />

coat. [MoRTH Specification : Clause 507 & 112]<br />

9.1 Grading II (19 mm nominal size) - Bitumen @ minimum 4.5 % of<br />

mix (60/70 grade) & thickness 50 - 75 mm<br />

Verical Curve 1 16418 7 0.060 6895.58<br />

Horizontal Curve 1 3072 7 0.060 1290.06<br />

Total= 8185.64 cum 4799.00 39282889.0<br />

3a 28 Cost of bitumen to be added when it varies from job mix<br />

formula adopted in any of the above items. Taken 0.5 %<br />

28.2 60/70 Penetration grade 1 8185.64 0.5 2.35 96.18 ton 34494.0 3317677.0<br />

4 9.2 Extra rate for carriage of mixed material additional lead average<br />

30 km. -Same as Above<br />

8185.640 cum 92.35 755944.00


5 R-6/12 Providing and laying bituminous concrete as per design mix on<br />

prepared surface with specified graded stone as per table 500-18<br />

for wearing course including loading of aggregate with Front<br />

end loader and hot mixing of binder (including cost of antistripping<br />

<strong>com</strong>pound, wherever required) and 3% cement filler<br />

with aggregates in hot mix plant 40-60 TPH Transporting the<br />

mix material with tipper and laying with sensor paver finisher<br />

(as per clouse 507.3.5) to the required level , grades and rolling<br />

with vibratory <strong>com</strong>pactor and pneumatic tyred roller 150-250<br />

KN,TP=0.7 Mpa, to achieve the desired density (approved by the<br />

department) excluding cost of primer/tack coat (MoRTH<br />

Specification : Clause -509 & 112)<br />

12.1 Grading I (19 mm nominal size) - Bitumen @ 5 % of mix &<br />

thickness 50 - 65 mm with lead of mix material 1km<br />

With 60/70 penetration grade straight run bitumen<br />

Verical Curve 1 16418.04 7 0.04 4597.05<br />

Horizontal Curve 1 3071.58 7 0.04 860.04<br />

Total= 5457.09 cum 5757.00 31416488.00<br />

5a 28 Cost of bitumen to be added when it varies from job mix<br />

formula adopted in any of the above items. Taken 0.5 %<br />

28.2 60/70 Penetration grade 1 5457.09 0.5 2.3 62.76 tonne 34494 2164726.00<br />

6 12.2 Extra rate for carriage of mixed material additional lead average<br />

30 km. -Same as Above<br />

5457.09 cum 92.35 503963.00<br />

TOTAL<br />

136125464.00<br />

Improvement of Curves 136125464.0


Improvement of Jodhpur - Osian - Phalodi Road km 2/000 to 121/500 (SH-61) under BOT Annuity Scheme (Jodhpur - Osian - Phalodi)<br />

S.<br />

No.<br />

Width<br />

of C/W<br />

Chainage Length X-<br />

(M)<br />

Section<br />

Start End<br />

Area of<br />

Cutting<br />

X-Section<br />

Area of<br />

Filling<br />

Vertical Alignment to be change<br />

Max. Ht.<br />

of<br />

Cutting /<br />

Filling<br />

<strong>Vol</strong>ume<br />

of<br />

Cutting<br />

<strong>Vol</strong>ume of<br />

Cutting<br />

Bitumino<br />

us Course<br />

<strong>Vol</strong>ume<br />

of<br />

Cutting<br />

WBM<br />

Embank<br />

ment<br />

1 5 5950 2925 34.33 1.586 0.1 6.01 0.00 25.06 20.60 Filling<br />

5 49.98 7.41 0.25 216.98 8.75 56.23 64.97 62.48 29.99 Cutting<br />

5 50.5 12.24 0.4 8.84 30.30 46.08 30.30 Filling<br />

5 37.26 6.12 0.33 164.74 6.52 41.92 48.44 46.58 22.36 Cutting<br />

5 149.84 30.63 0.24 26.22 0.00 82.04 89.90 Filling<br />

5 271.64 77.49 0.45 1365.35 47.54 305.60 353.13 339.55 162.98 Cutting<br />

5 404.66 213.6 0.8 70.82 323.73 494.80 242.80 Filling<br />

5 93.74 28.17 0.5 478.31 16.40 105.46 121.86 117.18 56.24 Cutting<br />

5 140.92 35.66 0.39 24.66 78.92 77.15 84.55 Filling<br />

5 568.11 527.5 2.04 4682.70 99.42 639.12 738.54 710.14 340.87 Cutting<br />

5 298.08 472.12 2.58 3433.69 52.16 335.34 387.50 372.60 178.85 Cutting<br />

5 103.01 157.15 0.95 1156.59 18.03 115.89 133.91 128.76 61.81 Cutting<br />

5 162.5 59.19 0.52 28.44 73.94 130.00 148.28 97.50 Filling<br />

2 7 10060 13620 325 58.09 0.48 1284.13 79.63 511.88 422.50 406.25 195.00 Cutting<br />

3 7 13388 13620 129.1 87.21 1.3 959.04 31.63 203.33 167.83 161.38 77.46 Cutting<br />

7 63.4 12.59 0.29 15.53 9.51 57.85 38.04 Filling<br />

GSB<br />

WMM<br />

BT Remarks


7 39.97 3.31 0.14 131.09 9.79 62.95 51.96 49.96 23.98 Cutting<br />

4 7 14809 15700 387.62 204.12 0.945 2475.41 94.97 610.50 503.91 484.53 232.57 Cutting<br />

7 153.44 96.07 0.91 1086.78 37.59 241.67 199.47 191.80 92.06 Cutting<br />

5 5.5 17962 18445 334.89 458 3.08 3649.25 64.47 414.43 435.36 418.61 200.93 Cutting<br />

5.5 150.29 46.55 0.56 28.93 107.46 112.72 137.14 90.17 Filling<br />

6 5.5 24563 25088 49.89 1.65 0.1 9.60 0.00 18.21 29.93 Filling<br />

5.5 475.11 288.61 1.47 3190.85 91.46 587.95 617.64 593.89 285.07 Cutting<br />

7 7 28625 28775 150 36 0.46 657.00 36.75 236.25 195.00 187.50 90.00 Cutting<br />

8 7 30975 31975 150 14.26 0.19 36.75 0.00 109.50 90.00 Filling<br />

7 224.18 251.68 1.89 2367.05 54.92 353.08 291.43 280.23 134.51 Cutting<br />

7 224.51 115.71 0.79 55.00 496.17 134.71 204.87 134.71 Filling<br />

7 240.18 175 1.37 58.84 1436.28 144.11 219.16 144.11 Filling<br />

7 125 15.79 0.2 448.03 30.63 196.88 162.50 156.25 75.00 Cutting<br />

9 5.5 32750 33500 325 66.67 0.48 62.56 243.75 296.56 195.00 Filling<br />

5.5 125 37.49 0.62 628.07 24.06 154.69 162.50 156.25 75.00 Cutting<br />

5.5 159.33 137.13 1.51 1291.95 30.67 197.17 207.13 199.16 95.60 Cutting<br />

5.5 55.14 4.78 0.12 212.39 10.61 68.24 71.68 68.93 33.08 Cutting<br />

5.5 41.27 5.89 0.28 7.94 15.48 37.66 24.76 Filling<br />

10 3.5 40700 40840 139.83 25.12 0.28 685.69 17.13 110.12 181.78 174.79 83.90 Cutting<br />

11 7 52672 53037 75 8.3 0.22 260.60 18.38 118.13 97.50 93.75 45.00 Cutting


7 101.9 17.28 0.28 24.97 30.57 92.98 61.14 Filling<br />

7 137.5 27.6 0.4 564.45 33.69 216.56 178.75 171.88 82.50 Cutting<br />

12 7 59600 59950 50 18.34 0.76 263.38 12.25 78.75 65.00 62.50 30.00 Cutting<br />

7 63.28 16.25 0.44 284.61 15.50 99.67 82.26 79.10 37.97 Cutting<br />

7 40 7.4 0.38 159.80 9.80 63.00 52.00 50.00 24.00 Cutting<br />

7 60 25.89 0.9 343.23 14.70 94.50 78.00 75.00 36.00 Cutting<br />

13 7 61712 62750 426.38 439.5 1.8 4227.73 104.46 671.55 554.29 532.98 255.83 Cutting<br />

7 197.52 132.03 1.05 1457.51 48.39 311.09 256.78 246.90 118.51 Cutting<br />

7 66.03 11.16 0.3 16.18 25.75 60.25 39.62 Filling<br />

7 94.71 15.28 0.28 362.68 23.20 149.17 123.12 118.39 56.83 Cutting<br />

14 7 73425 73200 225.00 183.43 1.62 1891.51 55.13 354.38 292.50 281.25 135.00 Cutting<br />

15 7 74425 73535 890.00 7.98 0.35 218.05 347.10 812.13 534.00 Filling<br />

7 890.00 44.92 0.54 2717.44 218.05 1401.75 1157.00 1112.50 534.00 Cutting<br />

7 890.00 51.05 0.89 2760.35 218.05 1401.75 1157.00 1112.50 534.00 Cutting<br />

7 890.00 1.28 0.04 218.05 0.00 0.00 712.00 Filling<br />

15 7 74750 74380 370.00 0.15 0.01 1000.05 90.65 582.75 481.00 462.50 222.00 Cutting<br />

7 370.00 0.15 0.025 1000.05 90.65 582.75 481.00 462.50 222.00 Cutting<br />

7 370.00 2.11 0.1 90.65 0.00 270.10 222.00 Filling<br />

7 370.00 1.15 0.09 1007.05 90.65 582.75 481.00 462.50 222.00 Cutting<br />

7 370.00 30.86 0.41 1215.02 90.65 582.75 481.00 462.50 222.00 Cutting<br />

7 370.00 10.4 0.22 90.65 0.00 297.11 222.00 Filling


16 7 75425 75115 34.25 53.17 0.47 8.39 41.10 31.25 20.55 Filling<br />

7 42.25 12.4 0.53 200.88 10.35 66.54 54.93 52.81 25.35 Cutting<br />

7 56.25 2.18 0.1 167.14 13.78 88.59 73.13 70.31 33.75 Cutting<br />

7 175.75 1.79 0.1 43.06 0.00 128.30 210.90 Filling<br />

17 7 80200 77850 425.00 325.4 1.37 3425.30 104.13 669.38 552.50 531.25 255.00 Cutting<br />

7 229.00 139 0.89 56.11 654.94 137.40 208.96 137.40 Filling<br />

7 600.00 579.33 1.65 147.00 4680.00 360.00 547.50 360.00 Filling<br />

7 371.00 257.72 1.81 90.90 3279.64 222.60 338.54 222.60 Filling<br />

7 387.00 220.63 0.7 94.82 628.88 232.20 353.14 232.20 Filling<br />

18 7 113600 113500 100.00 49.57 0.98 616.99 24.50 157.50 130.00 125.00 60.00 Cutting<br />

19 7 119175 119312 135.00 70.96 1.03 861.22 33.08 212.63 175.50 168.75 81.00 Cutting<br />

20 7 120200 120312 112.50 35.18 0.66 27.56 153.56 67.50 102.66 67.50 Filling<br />

TOTAL LENGTH<br />

Total Road length of 3.5m<br />

Total Road length of 5.5m<br />

16418.04 54490.8 3689.05 13822.0 11357.29 14967.7 16967.5 9985.77<br />

Total Road length of 7.0m = 12197.72<br />

=<br />

=<br />

139.83<br />

4080.49


Improvement of Jodhpur - Osian - Phalodi Road km 2/000 to 121/500 (SH-61) under BOT Annuity Scheme (Jodhpur - Osian - Phalodi)<br />

Mazor Change in Horizontal Curve Alignment (Shift of centre more than 3.0m)<br />

S. Width Chaina Length<br />

Present Proposed Shift of LA New <strong>Vol</strong>ume of GSB WMM Bituminous<br />

No. of C/W ge<br />

Design Design Centre Required Road Cutting<br />

DBM<br />

speed speed<br />

Embank<br />

ment<br />

1 5.5 3912 163 45 65 4.92 0 163.00 476.78 244.5 213.94 97.8<br />

2 5.5 15200 136 45 80 8.34 793.968 471.47 397.80 204 178.50 81.6<br />

3 5.5 33100 324 40 100 9.49 2152.332 1123.20 947.70 486 425.25 194.4<br />

4 5.5 38350 147.62 45 80 3.64 268.67 511.75 431.79 221.43 193.75 88.572<br />

5 7 59700 141 40 65 7.13 703.73 488.80 412.43 211.5 185.06 84.6<br />

6 5.5 62525 93.52 40 65 8.14 532.88 324.20 273.55 140.28 122.75 56.112<br />

7 5.5 65025 117.44 50 80 3.9 320.61 407.13 343.51 176.16 154.14 70.464<br />

8 5.5 70715 92 50 80 15.66 1152.58 318.93 269.10 138.00 120.75 55.2<br />

9 5.5 72485 126 45 65 4.98 376.49 436.80 368.55 189.00 165.38 75.6<br />

10 5.5 73155 96 50 80 3.18 152.64 332.80 280.80 144.00 126.00 57.6<br />

11 7 120970 150 45 65 2250 150.00 506.25 300 262.5 90 BW - 110m Police Line<br />

12 7 119870 487 45 80 14610 3202.025 0 1314.90 888.78 292.2 New By pass<br />

proposed reduces<br />

80mm length of route<br />

13 5.5 81950 240 40 80 1800 1.65 972.00 518.40 438.00 144<br />

14 7 75300 371 45 65 257.72 1.81 1502.55 801.36 677.08 222.6<br />

15 7 75150 387 40 80 220.63 0.7 1567.35 835.92 706.28 232.2<br />

TOTA 3071.58 25592.242 7934.262 8750.1465 5925.45 4858.13625 1842.948<br />

Remarks


Improvement of Jodhpur - Osian - Phalodi Road km 2/000 to 121/500 (SH-61) under BOT Annuity Scheme (Jodhpur - Osian -<br />

S.<br />

No.<br />

PART 'E' Toll Plaza & truck Lay Bye, Junctions etc. (Road Work)<br />

Item<br />

No.<br />

1 R-2 Clearing Grass and Removal of Rubbish<br />

3 R-3/<br />

3.1<br />

Abstract of Quantites<br />

Description No. L B H factor Q Unit Rate Amount<br />

2 Clearing grass and removal of rubbish maximum 150mm in<br />

thickness upto a distance of 100 Mtr outside the periphery of<br />

the area by manual means . Note ; where only grass is met<br />

with , the area clear shall be measured & paid for under this<br />

item ( MORTH clause 201 )<br />

By Manual Means<br />

Toll Plaza 4 175 30 1 21000.00<br />

Bus Lay Bye 10 60 15 1 9000.00<br />

10 60 15 1 9000.00<br />

Total= 3.90 hectar 28919.00 112785.00<br />

Earth work in excavation, including stacking/disposal of<br />

surplus material with all lifts and lead upto 495 metres,<br />

exclusive of <strong>com</strong>pensation of earth [MoRTH specification :<br />

Clause 301 to 305]<br />

3.1.1.3 Mechanically by power shovel, including mechanical<br />

loading and carriage by tipper/dumper (6T capacity)<br />

Toll Plaza 4 175 10 0.5 1 3500.00<br />

Bus Lay Bye 10 60 15 0.5 1 9000.00<br />

10 60 15 0.5 1 9000.00<br />

Total=<br />

21500.00 cum 173.00 3719500.00<br />

4 3.7.4 Extra for watering the earth to bring the earth upto required<br />

O.M.C excluding rolling<br />

Toll Plaza 4 175 10 0.5 1 3500.00<br />

Bus Lay Bye 5 60 15 0.5 1 4500.00


5 3.7.5 Extra for rolling to specification with the use of Vibratory<br />

roller when earth is at suitable moisture content with<br />

desired field density not less than 95% of maximum dry<br />

density (Modify Heavy Proctor test), excluding watering.<br />

5 60 15 0.5 1 4500.00<br />

Total=<br />

12500.00 cum 173.00 2162500.00<br />

3 R-3/6 Compaction of original ground with maximum of six passes<br />

of 8-10 tonnes power roller including filling depression<br />

occurring during rolling [MoRTH Specification : Clause<br />

305.3.4]<br />

Toll Plaza 4 175 10 1 7000.00<br />

Bus Lay Bye 10 60 15 1 9000.00<br />

10 60 15 1 9000.00<br />

Total= 250.00 100<br />

sqm<br />

R-4 Granular Sub -base with Well Graded Material (Table<br />

400.1)<br />

Plant Mix Method<br />

4 3.1 Providing laying spreading and <strong>com</strong>pacting specified<br />

graded sand, gravel as per Table 400-1,400-2 or any other<br />

course material as per design mix, as per CBR in sub base<br />

course including premixing the material at OMC in wet mix<br />

plant, carriage of mixed material spreading in uniform<br />

layers with motor grader F.E loader on a prepared base and<br />

<strong>com</strong>pacting with vibratory roller to achieve desired density<br />

(as per I.S.2720) including all material, labor, machinery,<br />

lighting guarding, barricading and maintenance of diversion<br />

<strong>com</strong>plete.[MoRTH specification : Clause 401]. By mechanical<br />

means with lead up to 1 km<br />

By mechanical means with lead upto 1 km<br />

(i) For Grading I Material<br />

Toll Plaza 4 175 13 0.23 1 2093.00<br />

12500.00 cum 24.00 0.00<br />

199.00 49750.00


Truck Lay Bye 2 120 10 0.23 1 552.00<br />

2 120 10 0.23 1 552.00<br />

Bus Lay Bye 10 60 15 0.23 1 9000.00<br />

10 60 15 0.23 1 9000.00<br />

Total= 21197.00 cum 490.00 10386530.00<br />

5 3.4 Extra rate for carriage of mixed material additional lead<br />

from :a<br />

3.4.1 2nd km to 10th km 1 21197 9 190773.00 Cum<br />

/Km<br />

b 3.4.2 11th km to 13th km 1 21197 3 63591.00 Cum<br />

/Km<br />

R-5 Wet Mix Macadam<br />

6 2 Providing, laying, spreading and <strong>com</strong>pacting stone<br />

aggregate for Wet Mix Macadam (as per table 400-10 and<br />

400-11) specification including premixing the material with<br />

water to OMC in wet mix plant as per approved design mix,<br />

carriage of mixed material by Tipper to site, laying in<br />

uniform layers with motor grader/Front end Loader/paver<br />

finisher, in sub base/ base course on a well prepared under<br />

base and <strong>com</strong>pacting with vibratory roller to achieve the<br />

desired density including lighting, guarding, barricading<br />

and maintenance of diversion etc. (MoRTH specification :<br />

Clause 406) by mechanical means with lead up to 1 Km.<br />

3.65 696322.00<br />

3.2 203492.00<br />

By Mechanical Means with 1 km lead<br />

Toll Plaza 4 175 13 0.25 1 2275.00<br />

Bus Lay Bye 10 60 15 0.23 1 9000.00<br />

10 60 15 0.23 1 9000.00<br />

Total= 20275.00 cum 765.00 15510375.00<br />

7 2.1 Extra rate for carriage of mixed material additional lead<br />

from :a<br />

2.1.1 2nd km to 10th km 1 20275.0 9 182475.00 Cum<br />

/Km<br />

3.65 666034.00


2.1.2 11th km to 13th km 1 20275.0 3 60825.00 Cum<br />

/Km<br />

3.2 194640.00


B Hard shoulders<br />

8 R-4/2 Providing and laying granular sub-base material having P.I.<br />

not more than 6 including spreading in layers not exceeding<br />

150 mm <strong>com</strong>pacted thickness and consolidation by 8-10<br />

tonne power roller to required camber and grade including<br />

cost of water and hire charges of machinery including T&P<br />

with all lead (Compacted thickness to be measured).as per<br />

MoRTH specification table 400-1, 400-2,<br />

2.1 For grading-I with CBR value not less than 30.<br />

to attain 100% proctor density. Toll Plaza 4 300 1.5 0.15 1 270.00<br />

Bus Lay Bye 10 60 1.5 0.15 1 135.00<br />

10 60 1.5 0.15 1 135.00<br />

Total= 540.00 Cum 286.00 154440.00<br />

Prime Coat<br />

9 R-6/4 Providing and applying primer coat over prepared surface<br />

or granular base with bitumen emulsion as per IS: 8887 &<br />

manufacturer’s specifications @ 6 kg /10 sqm with a self<br />

propelled or towed bitumen pressure sprayer equipped for<br />

spraying the material uniformly at specified rates and<br />

temperatures as per MoRTH specification CI 502 & 112 (<br />

Including cleaning of road surface )<br />

Toll Plaza 4 175 13 1 9100.00<br />

Bus Lay Bye 10 60 7 1 4200.00<br />

10 60 7 1 4200.00<br />

Total= 17500.00 sqm 21.00 367500.00<br />

10 4.1 Add extra to item No. 1 for 1 Kg / 10 Sqm emulsion 1 17500.0 17500.00<br />

Total= 17500.00 sqm 2.10 36750.00


Tack Coat<br />

11 R-6/5 Providing and applying tack coat on the prepared surface,<br />

with bitumen emulsion as per IS : 8887 & manufacturer’s<br />

specifications @ 2 kg /10sqm. With a self propelled or towed<br />

bitumen pressure sprayer equipped for spraying the<br />

material uniformly at specified rates and temperatures as<br />

per MoRTH specification Clause 503 & 112 ( Including<br />

cleaning of bituminous road surface )<br />

Toll Plaza 4 175 13 1 9100.00<br />

Bus Lay Bye 10 60 7 1 4200.00<br />

10 60 7 1 4200.00<br />

Total=<br />

17500.00 sqm 8.00 140000.00<br />

12 5.1 Add extra for 0.1Kg / 10 Sqm emulsion 0.75 17500 13125.00 sqm 2.90 38063.00<br />

Dense Bituminous Macadam<br />

13 R-6/9 Providing and laying Dense Bituminous Macadam on<br />

prepared surface with specified graded crushed aggregates<br />

as per table 510 and design mix for base/binder course<br />

including loading of material with Front end loader, heating<br />

of binder (including cost of anti-stripping <strong>com</strong>pound<br />

wherever required) aggregate and filler in hot mix plant 40-<br />

60 TPH, transporting the mixed material by tippers and<br />

laying with sensor paver finisher as per clause 507.3.5 to the<br />

required level and grade rolling by self propelled power<br />

rollers and vibratory rollers or pneumatic tyred roller 150-<br />

250KN. TP=0.7MPa to achieve the desired density<br />

(approved by the department) but excluding cost of<br />

primer/tack coat. [MoRTH Specification : Clause 507 & 112]<br />

9.1 Grading I (40 mm nominal size) - Bitumen @ 4.5 % of mix<br />

(60/70 grade) & thickness 50 - 75 mm with lead of mix<br />

material 1km<br />

for Toll Plaza 4 175 13 0.09 1 819.000


Bus Lay Bye 10 60 7 0.05 1 210.00<br />

10 60 7 0.05 1 210.00<br />

Total=<br />

1239.00 cum 4799.00 5945961.0<br />

13a 28 Cost of bitumen to be added when it varies from job mix<br />

formula adopted in any of the above items. Taken 0.5 %<br />

28.2 60/70 Penetration grade 1 1239.00 0.5 2.35 14.558 tonne 34494.0 502173.0<br />

14 9.2.1 Extra rate for carriage of mixed material additional lead<br />

average 13 km. -Same as Above<br />

15 R-<br />

6/12<br />

Providing and laying bituminous concrete as per design mix<br />

on prepared surface with specified graded stone as per<br />

table 500-18 for wearing course including loading of<br />

aggregate with Front end loader and hot mixing of binder<br />

(including cost of anti-stripping <strong>com</strong>pound, wherever<br />

required) and 3% cement filler with aggregates in hot mix<br />

plant 40-60 TPH Transporting the mix material with tipper<br />

and laying with sensor paver finisher (as per clouse 507.3.5)<br />

to the required level , grades and rolling with vibratory<br />

<strong>com</strong>pactor and pneumatic tyred roller 150-250 KN,TP=0.7<br />

Mpa, to achieve the desired density (approved by the<br />

department) excluding cost of primer/tack coat (MoRTH<br />

Specification : Clause -509 & 112)<br />

1239.000 cum 42.45 52596.00<br />

12.1 Grading I (19 mm nominal size) - Bitumen @ 5 % of mix &<br />

thickness 50 - 65 mm with lead of mix material 1km<br />

With 60/70 penetration grade straight run bitumen<br />

Toll Plaza 4 175 13 0.04 364.00<br />

Bus Lay Bye 10 60 7 0.04 1 168.00<br />

10 60 7 0.04 1 168.00<br />

Total= 700.00 cum 5757.00 4029900.00<br />

15a 28 Cost of bitumen to be added when it varies from job mix<br />

formula adopted in any of the above items. Taken 0.5 %


28.2 60/70 Penetration grade 1 700.00 0.5 2.3 8.05 tonne 34494 277677.00<br />

16 12.3 Extra rate for carriage of mixed material additional lead<br />

average 13 km. -Same as Above<br />

700.00 cum 42.45 29715.00<br />

Total = 45276703.00


Improvement of Jodhpur - Osian - Phalodi Road km 2/000 to 121/500 (SH-61) under BOT Annuity<br />

Scheme (Jodhpur - Osian - Phalodi)<br />

Abstract of Quantites<br />

PART 'H' TOLL PLAZA<br />

S. No. Item No. No. L B Quantity Unit Rate Amount<br />

1 Toll collection canopy 1 18.00 9.00 162.00 Sqm 5500.00 891000.00<br />

2 Administrative Building<br />

Builtup Area<br />

3 Outer Development of Plot<br />

Main Building 2 12.00 6.00 144.00<br />

DG Area 1 5.00 3.00 15.00<br />

159.00 Sqm 10000.00 1590000.00<br />

1 15.00 30.00 450.00 Sqm 928.00 417600.00<br />

4 Toll Booths & Electrifications (L.S.) 2000000.00<br />

Total = 4898600.00


Improvement of Jodhpur - Osian - Phalodi Road km 2/000 to 121/500 (SH-61) under BOT Annuity<br />

Scheme (Jodhpur - Osian - Phalodi)<br />

PART - H: TOLL PLAZA<br />

Abstract of Cost<br />

S.No. Description QTY. Unit Rate Amount<br />

1 At Km 6/500 1 EACH 4898600.00 4898600.00<br />

2 At Km 39/900 1 EACH 4898600.00 4898600.00<br />

3 At Km 90/000 1 EACH 4898600.00 4898600.00<br />

4 At Km 109/500 1 EACH 4898600.00 4898600.00<br />

19594400.00


Improvement of Jodhpur - Osian - Phalodi Road km 2/000 to 121/500 (SH-61) under BOT Annuity Scheme (Jodhpur -<br />

Osian - Phalodi)<br />

Abstract of Cost<br />

PART - I: LAND ACQUISITION<br />

S.No. Description No. L B QTY. Unit Rate Amount<br />

1 Land required for widening for lay byes. 1 250 30 7500.00 Sqm. 80.00 600000.00<br />

2 For Toll Plaza Administrative Building 4 45 30 5400.00 Sqm. 80.00 432000.00<br />

3 Other land required for By Passes 1 14279 45 642555.00 Sqm. 80.00 51404400.00<br />

4 Land Required for Horizontal Curve Improvement 25592.24 Sqm. 80.00 2047379.32<br />

5 Compensation of House / Building 500000.00<br />

681047.24 TOTAL 54983779.32


Improvement of Jodhpur - Osian - Phalodi Road km 2/000 to 121/500 (SH-61) under BOT Annuity Scheme<br />

(Jodhpur - Osian - Phalodi)<br />

PART 'J' PUBLIC UTILITY SERVICES<br />

S.<br />

No.<br />

BSR<br />

No.<br />

Item No. No. L B H Quantity Unit Rate Amount<br />

1 L.S. Bus Shelter Canopy 18 6.45 3.23 375.00 Sqm 6500.00 2437519.50<br />

3 R-<br />

2/2<br />

3 R-3/<br />

3.1<br />

3.1.1.<br />

3<br />

Plateform & Island for the Bus Shelter<br />

Clearing grass and removal of rubbish maximum<br />

150mm in thickness upto a distance of 100 Mtr<br />

outside the periphery of the area by manual means<br />

. Note ; where only grass is met with , the area clear<br />

shall be measured & paid for under this item (<br />

MORTH cla<br />

By Manual Means 18 9.00 4.00 648.00 Cum<br />

Total= 0.06 hectare 9559.00 620.00<br />

Earth work in excavation, including<br />

stacking/disposal of surplus material with all lifts<br />

and lead upto 495 metres, exclusive of<br />

<strong>com</strong>pensation of<br />

Clause 301 to 305]<br />

earth [MoRTH specification :<br />

Mechanically by power shovel, including<br />

mechanical loading and carriage by<br />

tipper/dumper (6T capacity)<br />

Abstract of Quantites<br />

18 9.00 4 0.5 324.00<br />

324.00 Cum 61.00 19764.00<br />

4 3.7.4 Extra for watering the earth to bring the earth upto<br />

required O.M.C excluding rolling<br />

for Widening of Road (5.5-7.00) 18 9.00 4 0.5 324.00<br />

324.00 cum 11.00 3564.00


5 3.7.5 Extra for rolling to specification with the use of<br />

Vibratory roller when earth is at suitable moisture<br />

content with desired field density not less than 95%<br />

of maximum dry density (Modify Heavy Proctor<br />

test), excluding watering.<br />

6 R-<br />

3/6<br />

9 R-<br />

10/2<br />

10 R-<br />

10/<br />

10.10<br />

.1<br />

324.00 cum 24.00 0.00<br />

Compaction of original ground with maximum of<br />

six passes of 8-10 tonnes power roller including<br />

filling depression occurring during rolling [MoRTH<br />

for Widening of Road (5.5-7.00) 18 9.00 4 648.00<br />

Total= 6.48 sqm 199.00 1290.00<br />

Providing and laying Plain cement concrete M15<br />

mix with stone aggregate 20mm nominal size<br />

mechanically mixed and vibrated, in foundation up<br />

to a depth of 1.50 below Ground level and or 1.50<br />

meters above ground/bed level.<br />

PCC grade M 15 18 9.00 4.00 0.15 97.20 Cum 2742.00 266523.00<br />

Providing and laying Random Rubble stone<br />

masonry in cement sand mortar 1:3, in foundation<br />

up to a depth of 1.50 meters and also 1.50 meters<br />

above Ground /Bed level [MoRTH Specification :<br />

Toe wall 44 9.00 0.60 0.30 71.28<br />

44 9.00 0.45 0.30 53.46<br />

44 3.40 0.60 0.30 26.93<br />

1020 * 6.7 = 1608 44 3.55 0.45 0.30 21.09<br />

Total =<br />

172.76 cum 2747.00 474557.99


11 R- Random Rubble masonry in cement sand mortar<br />

10/1 1:3 in superstructures upto a height of 4 metres or<br />

0.12+ part thereof above 1.50m level from Ground/Bed<br />

10.13 level.[MoRTH Specfication : Clause 1000/1400]<br />

12 R-<br />

10/1<br />

4<br />

11 R-<br />

7/47.<br />

3<br />

Toe Wall 44 9.00 0.30 0.50 59.40<br />

At Shoulders 20 3.70 0.30 0.50 11.10<br />

Providing Cement plaster 12mm thick in cement<br />

mortar (1:3) at all levels [MoRTH Specification:<br />

Clause:1000/1300]<br />

Providing and fixing of Precast concrete<br />

interlocking blocks of 100 mm thick manufactured<br />

from fully <strong>com</strong>puterized automatic stationery<br />

hydraulic vibro pressed machine & full<br />

<strong>com</strong>puterized automatic batching plant of class A-1<br />

as per BS : 6717-2001. The C.C. interlocking paving<br />

blocks be laid on average 25 mm thick bed of<br />

coarse sand and the joint is to be filled with fine<br />

sand. Laying procedure on <strong>com</strong>pacted sub base as<br />

defined. Complete job is to be executed as per the<br />

instructions of Engineer-in-charge. The rates to be<br />

inclusive of all lead, lift, lifts & taxes general<br />

specifications of blocks.<br />

1. Shape : As specified by Engineer-in-charge.<br />

Total =<br />

36 9.00 1.00 324.00<br />

36 4.00 1.00 144.00<br />

Total =<br />

70.50 cum 2945.00 207622.50<br />

468.00 sqm 99.00 46332.00<br />

18 9.00 4.00 648.00 Sqm 587.00 380376.00


2. Tensile splitting strength and breaking load as<br />

per BS : 6717-2001<br />

3. Colour : Grey cement natural colour<br />

4. Variation in Dimension : Less than 1.6mm.<br />

5. Variation in thickness : Less than 3.2mm<br />

12 Construction of FOB's at Osian 2 2 Each 1500000 3000000.00<br />

Total = 6838168.99


PART 'K' LANDSCAPING & TREE PLANTATION<br />

S.<br />

No.<br />

Improvement of Jodhpur - Osian - Phalodi Road km 2/000 to 121/500 (SH-61) under BOT Annuity<br />

Abstract of Quantites<br />

BSR<br />

No.<br />

1 R-<br />

9/16<br />

Item No. No. L B H Quantity Unit Rate Amount<br />

Planting permanent hedges including digging of<br />

trenches 60cm wide and 45cm deep refilling the<br />

excavted earth mixed with farm yard manure<br />

supplied at the rate of 4.65 cum per 100 metres and<br />

suppling and planting hedge plants at 30 cm apart.<br />

2 5000.0 100.00 100 Metres 12100.00 1210000.00<br />

2 9.17 Maintaining the hedges for the first two years<br />

including waterning etc. <strong>com</strong>plete.<br />

17.1 For first year 10000.00 Metres 106.00 1060000.00<br />

17.2 For second year 10000.00 Metres 92.00 920000.00<br />

3 R-<br />

9/14<br />

4 R-<br />

9/18<br />

Turfing lawn with fine grassing including<br />

ploughing, dressing including breaking of clods,<br />

removal of rubbish, dressing and supplying and<br />

spreading of farm yard manure at rate 0.60 cum<br />

per 100 Sqm.<br />

Manintance of lawns with fine grassing for the first<br />

year including watering etc.<br />

5 9.28 Supply & Planting of Shady plants (Neem, Peepal,<br />

Goolar, jamun, Imli or other specified) along road<br />

side including follwing activities:<br />

(15m c/c)<br />

4 100 5 20.00 100 Sqm 4800 96000.00<br />

20.00 100 Sqm 9500 190000.00<br />

2 117650.0 15.00 15686.67 Nos. 975 15294500.00<br />

Total = 18770500.00


S. No.<br />

Culvert /<br />

Bridge No.<br />

Improvement of Jodhpur - Osian - Phalodi Road km 2/000 to 121/500 (SH-61) under BOT Annuity Scheme (Jodhpur - Osian -<br />

Phalodi)<br />

Chainage<br />

Length<br />

(A - A)<br />

Width<br />

(P-P) (m)<br />

No. of Span<br />

Span<br />

Length (c/c)<br />

1 3/1 2500 15 7.5 1 -<br />

2 3/2 2900 12 7.5 1 -<br />

3 4/1 3050 15 7.5 1 -<br />

4 4/2 3700 15 7.5 1 -<br />

5 9/1 8350 20 7.5 1 -<br />

6 31/1 30075 25 7.5 1 -<br />

7 34/1 33400 20 7.5 1 -<br />

8 37/1 36850 15 7.5 1 -<br />

9 50/1 49200 35 7.5 1 -<br />

10 54/1 53825 12 12 1 1.2<br />

11 56/1 55525 11.1 12 1 2<br />

12 56/2 55800 30 7.5 1 -<br />

13 58/1 57400 8 12 2 1.2<br />

14 58/2 57625 5.1 7.5 2 1.5<br />

PART 'B' List of Existing CD works & Requirement of Widening<br />

Pier Type<br />

(Masonry<br />

/RCC)<br />

RR Stone<br />

Masonry<br />

RR Stone<br />

Masonry<br />

RR Stone<br />

Masonry<br />

RR Stone<br />

Masonry<br />

RR Stone<br />

Masonry<br />

RR Stone<br />

Masonry<br />

RR Stone<br />

Masonry<br />

RR Stone<br />

Masonry<br />

RR Stone<br />

Masonry<br />

RR Stone<br />

Masonry<br />

RR Stone<br />

Masonry<br />

RR Stone<br />

Masonry<br />

RR Stone<br />

Masonry<br />

RR Stone<br />

Masonry<br />

Foundation<br />

Type<br />

RR Stone<br />

Masonry<br />

RR Stone<br />

Masonry<br />

RR Stone<br />

Masonry<br />

RR Stone<br />

Masonry<br />

RR Stone<br />

Masonry<br />

RR Stone<br />

Masonry<br />

RR Stone<br />

Masonry<br />

RR Stone<br />

Masonry<br />

RR Stone<br />

Masonry<br />

RR Stone<br />

Masonry<br />

RR Stone<br />

Masonry<br />

RR Stone<br />

Masonry<br />

RR Stone<br />

Masonry<br />

RR Stone<br />

Masonry<br />

Type<br />

Slab / Box /<br />

Pipe<br />

Protection<br />

Work<br />

Available<br />

Width of<br />

Run off<br />

Condition<br />

of Bridge<br />

Remark<br />

Average<br />

Height<br />

(m)<br />

FCW No 15 OK Nala 1<br />

FCW No 15 OK Nala 1<br />

FCW No 15 OK Nala 1<br />

FCW No 15 OK Nala 1<br />

FCW No 15 OK Nala 1<br />

FCW No 15 OK Nala 1<br />

FCW No 15 OK Nala 1<br />

FCW No 15 OK Nala 1<br />

FCW No 15 OK Nala 1<br />

RCC<br />

Pipe<br />

RCC<br />

Slab<br />

Whether<br />

Widening is<br />

required<br />

(m)<br />

New<br />

Culvert<br />

New<br />

Culvert<br />

New<br />

Culvert<br />

New<br />

Culvert<br />

New<br />

Culvert<br />

New<br />

Culvert<br />

New<br />

Culvert<br />

New<br />

Culvert<br />

New<br />

Culvert<br />

Estimated<br />

cost for<br />

repair and<br />

extension<br />

No 2 OK Nala 1.6 No -<br />

No 4 OK Nala 2 No -<br />

FCW No 15 OK Nala 1<br />

RCC<br />

Pipe<br />

RCC<br />

Slab<br />

New<br />

Culvert<br />

No 6 OK Nala 1.6 No -<br />

No 6 OK Nala 1.5 Yes 322132.28<br />

-<br />

-<br />

-<br />

-<br />

-<br />

-<br />

-<br />

-<br />

-<br />

-


15 59/1 58050 8 12 2 0.9<br />

16 59/1 58350 10 7.5 1 -<br />

17 60/1 59900 30 7.5 1 -<br />

18 60/2 59500 35 7.5 1 -<br />

19 61/1 60700 12.2 12 3 0.9<br />

20 65/1 65600 35 7.5 1 -<br />

21 68/1 67600 28 7.5 1 -<br />

22 80/1 79350 30 8 1 -<br />

23 80/2 79800 30 8 1 -<br />

24 80/1 79900 30 8 1 -<br />

25 81/1 80010 45 8 1 -<br />

26 81/2 80400 35 8 1 -<br />

27 82/1 81150 50 8 1 -<br />

27A 81/1 80200 50 8 1 -<br />

28 104/1 103420 12 7.5 4 3<br />

29 115/1 114900 25 8 1 -<br />

30 118/2 117500 12 7.5 2 4<br />

31 121/1 120000 37 9.4 15 0.9<br />

31a 112/1 116600 8.5 8 5 0.9<br />

RR Stone<br />

Masonry<br />

RR Stone<br />

Masonry<br />

RR Stone<br />

Masonry<br />

RR Stone<br />

Masonry<br />

RR Stone<br />

Masonry<br />

RR Stone<br />

Masonry<br />

RR Stone<br />

Masonry<br />

RR Stone<br />

Masonry<br />

RR Stone<br />

Masonry<br />

RR Stone<br />

Masonry<br />

RR Stone<br />

Masonry<br />

RR Stone<br />

Masonry<br />

RR Stone<br />

Masonry<br />

RR Stone<br />

Masonry<br />

RR Stone<br />

Masonry<br />

RR Stone<br />

Masonry<br />

RR Stone<br />

Masonry<br />

RR Stone<br />

Masonry<br />

RR Stone<br />

Masonry<br />

RR Stone<br />

Masonry<br />

RR Stone<br />

Masonry<br />

RR Stone<br />

Masonry<br />

RR Stone<br />

Masonry<br />

RR Stone<br />

Masonry<br />

RR Stone<br />

Masonry<br />

RR Stone<br />

Masonry<br />

RR Stone<br />

Masonry<br />

RR Stone<br />

Masonry<br />

RR Stone<br />

Masonry<br />

RR Stone<br />

Masonry<br />

RR Stone<br />

Masonry<br />

RR Stone<br />

Masonry<br />

RCC<br />

Pipe<br />

No 68 OK Nala 1.6 No -<br />

FCW No 15 OK Nala 1<br />

FCW No 15 OK Nala 1<br />

FCW No 15 OK Nala 1<br />

RCC<br />

Pipe<br />

New<br />

Culvert<br />

New<br />

Culvert<br />

New<br />

Culvert<br />

No 69 OK Nala 1.75 No -<br />

FCW No 15 OK Nala 1<br />

FCW No 15 OK Nala 1<br />

FCW No 70 OK Nala 1<br />

FCW No 70 OK Nala 1<br />

FCW No 70 OK Nala 1<br />

FCW No 50 OK Nala 1<br />

FCW No 45 OK Nala 1<br />

FCW No 70 OK Nala 1<br />

PCC FCW No 50 OK Nala 1<br />

RR Stone<br />

Masonry<br />

RR Stone<br />

Masonry<br />

RR Stone<br />

Masonry<br />

RR Stone<br />

Masonry<br />

PCC<br />

RCC<br />

Slab<br />

New<br />

Culvert<br />

New<br />

Culvert<br />

New<br />

Culvert<br />

New<br />

Culvert<br />

New<br />

Culvert<br />

New<br />

Culvert<br />

New<br />

Culvert<br />

New<br />

Culvert<br />

New<br />

Culvert<br />

No 16 OK Nala 2.5 Yes 1288529.13<br />

FCW No 45 OK Nala 1<br />

RCC<br />

Slab<br />

RCC<br />

Pipe<br />

R.C.C<br />

Pipe<br />

New<br />

Culvert<br />

No 71 OK Nala 2.5 Yes 859019.42<br />

No 69 OK Nala 1.75<br />

No 4.5 OK<br />

Atiya<br />

Nala<br />

2.5<br />

New<br />

Culvert<br />

New<br />

Culvert<br />

-<br />

-<br />

-<br />

-<br />

-<br />

-<br />

-<br />

-<br />

-<br />

-<br />

-<br />

-<br />

-<br />

-<br />

-


32 118/1 117100 10.2 12 6 0.9<br />

33 120/1 119375 3.4 8 2 0.9<br />

34 122/1 121425 10.2 12 6 0.9<br />

35 122/2 121700 1.7 9 1 0.6<br />

RR Stone<br />

Masonry<br />

RR Stone<br />

Masonry<br />

RR Stone<br />

Masonry<br />

RR Stone<br />

Masonry<br />

PCC<br />

PCC<br />

PCC<br />

PCC<br />

R.C.C<br />

Pipe<br />

R.C.C<br />

Pipe<br />

R.C.C<br />

Pipe<br />

R.C.C<br />

Pipe<br />

No 5.4 OK Nala 1.5 - -<br />

No 1.8 OK Nala 1.5<br />

New<br />

Culvert<br />

No 5.4 OK Nala 1.5 - -<br />

No 5.4 OK Nala 2.5<br />

New<br />

Culvert<br />

-


New Culverts<br />

S. No.<br />

Culvert / Bridge<br />

No.<br />

Chainage<br />

Prop.Length<br />

Prop. Width<br />

No. of Span<br />

Span Length<br />

(c/c)<br />

Pier Type<br />

(Masonry /RCC)<br />

Foundation<br />

Type<br />

Type<br />

Slab / Box / Pipe<br />

Prop. Protection<br />

Work<br />

Width of Run<br />

off<br />

Condition of<br />

Bridge<br />

Remark<br />

Average Height<br />

(m)<br />

Width is<br />

required (m)<br />

Estimated cost<br />

for repair and<br />

extension<br />

1 3/1 2500 9 12 6 1 - PCC RCC Box Yes New Nala 1.25 12.00 727841.00<br />

2 3/2 2900 6 12 4 1 - PCC RCC Box Yes New Nala 1.25 12.00 690427.00<br />

3 4/1 3050 9 12 6 1 - PCC RCC Box Yes New Nala 2.5 12.00 727841.00<br />

4 4/2 3700 9 12 6 1 - PCC RCC Box Yes New Nala 2.5 12.00 727841.00<br />

5 9/1 8350 9 12 6 1 - PCC RCC Box Yes New Nala 2.5 12.00 727841.00<br />

6 31/1 30075 12 12 8 1 - PCC RCC Box Yes New Nala 2.5 12.00 1315853.00<br />

7 34/1 33400 9 12 6 1 - PCC RCC Box Yes New Nala 2.5 12.00 727841.00<br />

8 37/1 36850 9 12 6 1 - PCC RCC Box Yes New Nala 2.5 12.00 727841.00<br />

9 50/1 49200 15 12 10 1 - PCC RCC Box Yes New Nala 2.5 12.00 1607880.00<br />

10 53/1 52500 3 12 2 1 - PCC RCC Box Yes New Nala 1.25 12.00 383765.00<br />

11 53/2 52600 3 12 2 1 - PCC RCC Box Yes New Nala 1.25 12.00 383765.00<br />

12 79/1 78550 15 12 10 1.5 - PCC RCC Box Yes New Nala 2.5 12.00 1607880.00<br />

13 79/2 78725 15 12 10 1.5 - PCC RCC Box Yes New Nala 2.5 12.00 1607880.00<br />

14 79/3 78935 15 12 10 1.5 - PCC RCC Box Yes New Nala 2.5 12.00 1607880.00<br />

15 80/1 79175 15 12 10 1.5 - PCC RCC Box Yes New Nala 2.5 12.00 1607880.00<br />

16 80/2 79435 12 12 8 1.5 - PCC RCC Box Yes New Nala 2.5 12.00 1315853.00


17 80/3 79725 15 12 10 1.5 - PCC RCC Box Yes New Nala 2.5 12.00 1607880.00<br />

18 81/1 80200 12 12 8 1.5 - PCC RCC Box Yes New Nala 2.5 12.00 1607880.00<br />

19 120/1 119650 15 12 10 1.5 - PCC RCC Box Yes New Nala 2.5 12.00 1607880.00<br />

20<br />

21<br />

22<br />

23<br />

Mathania<br />

By Pass<br />

Mathania<br />

By Pass<br />

Mathania<br />

By Pass<br />

Mathania<br />

By Pass<br />

40.4 12 6 6 - PCC RCC Box Yes New Nala 3 12.00 6791801.46<br />

20.6 12 3 6 - PCC RCC Box Yes New Nala 3 12.00 3964705.01<br />

20.6 12 3 6 - PCC RCC Box Yes New Nala 3 12.00 3964705.01<br />

20.6 12 3 6 - PCC RCC Box Yes New Nala 3 12.00 3964705.01<br />

24 15 12 10 1.5 - PCC RCC Box Yes New Nala 2.5 12.00 3964705.01<br />

25 15 12 10 1.5 - PCC RCC Box Yes New Nala 2.5 12.00 3964705.01<br />

26 15 12 10 1.5 - PCC RCC Box Yes New Nala 2.5 12.00 3964705.01<br />

27 12 12 8 1.5 - PCC RCC Box Yes New Nala 2.5 12.00 1315853.00<br />

28 15 12 10 1.5 - PCC RCC Box Yes New Nala 2.5 12.00 3964705.01<br />

29 12 12 8 1.5 - PCC RCC Box Yes New Nala 2.5 12.00 3964705.01<br />

30 15 12 10 1.5 - PCC RCC Box Yes New Nala 2.5 12.00 1607880.00<br />

408.2 G. Total = 62752924.00


Improvement of Jodhpur - Osian - Phalodi Road km 2/000 to 121/500 (SH-61) under BOT Annuity Scheme<br />

(Jodhpur - Osian - Phalodi)<br />

Abstract of Quantites<br />

PART 'D' (D) Protection Work & Diversion for Construction of CD Works<br />

S.No. Item<br />

No.<br />

Description No. L B H Q Unit Rate Amount<br />

1 R-<br />

10/10.<br />

1.2a<br />

Providing and laying mechnically mixed and vibrated<br />

Cement Concrete in foundation upto a depth of 1.5<br />

metres below ground level and 1.50 metres above<br />

Ground/Bed level.[MoRTH Specification : Clause<br />

1000/1700]<br />

Cement concrete 1:3:6 mix crushed stone aggregates<br />

20mm nominal size.<br />

Floor Protection 30 125 0.15 562.50<br />

Total= 562.50 cum 2217.00 1247063.00<br />

2 R-10/ Providing and laying Random Rubble masonry in<br />

10.12.1 foundation upto a depth of 1.50 metres and 1.50<br />

metres above Ground /Bed level.[MoRTH<br />

Specfication: Clause 1000/1400]<br />

10.12.1 in 1:3 cement mortar<br />

Parapet 8 12 0.4 0.5 19.20 cum<br />

Total= 19.20 cum 2024.00 38861.00<br />

3 10.13 Extra for Random Rubble masonry in cement sand<br />

mortar 1:3 in superstructures upto a height of 4<br />

metres or part thereof above 1.50m level from<br />

Ground/Bed level.[MoRTH Specfication : Clause<br />

1000/1400]<br />

I Random rubble masonry<br />

Parapet 8 12 0.4 0.5 19.20<br />

Total= 19.20 cum 156.00 2996.00<br />

4 R-10<br />

/10.16<br />

Plaster on new surface with cement mortar (1:3)<br />

including racking of joint etc. <strong>com</strong>plete fine finished<br />

12mm thick.<br />

Parapet 16 12 0.5 96


5 R-10/<br />

10.4<br />

Sides 16 0.5 0.4 3.2<br />

Total= 99.20 sqm 84.00 8333.00<br />

Providing and laying RCC M20 mix with stone<br />

aggregate 20mm (nominal size) mechnically mixed<br />

and vibrated for RCC work in slab in superstru-cture<br />

upto 4 metre above 1.5 metre level from Bed/ Ground<br />

level, excluding steel reinforcement but including<br />

centeri<br />

Parapet wall 8 12 0.4 0.075 2.88<br />

Total= 2.88 cum 2838.00 8174.00<br />

6 13.11 Providing and applying 2 coats of water based<br />

cement paint to unplastered concrete surface after<br />

cleaning the surface of dirt, dust, oil, grease,<br />

efflorescense and applying paint @ of 1 litre for 2<br />

Sqm.<br />

Parapet 99.20<br />

7 Dismantling of Structures<br />

Total= 99.20 Sqm 16.00 1587.20<br />

R-2/4 Dismantling upto 1.5m in foundation and/or 1.5m<br />

above ground level including T&P and scaffolding<br />

wherever necessary, sorting the dismantled material,<br />

disposal of unserviceable material, and stacking<br />

serviceable material with in a lead of 1000m.<br />

(ii)<br />

[MoRTH Specification clause 202]<br />

By Mechanical Means<br />

4.1.1.2 Cement Concrete M-15 & M-20 LS 20.00<br />

Total= 20.00 cum 243.00 4860.00<br />

4.1.1.3 Prestressed / Reinforced Cement Concrete grade M- LS<br />

20 & Above<br />

25.00<br />

Total= 25.00 cum 644.00 16100.00<br />

4.3.2 RR Masonry in cement mortar 408.2 0.4 0.4 65.31<br />

408.2 0.65 1.85 490.86<br />

Total= 556.17 cum 167.00 92881.00


8 R-<br />

2/2.4.<br />

10<br />

9 R-3/<br />

3.1<br />

Dismantling of Flexible Pavements<br />

Dismantling of flexible pavements and disposal of<br />

dismantled materials upto a lead of 1000 metres,<br />

stacking serviceable and unserviceable materials<br />

separately as per MORTH specification clause 202.<br />

For CC Pavement Section + New Bituminous Road<br />

By Mechanical Means<br />

(A) Bituminous Courses 1 510.25 5.5 0.05 140.32<br />

Total= 140.32 cum 151.00 21189.00<br />

(B) Granular courses (From Verticle Curve Improvement) 1 510.25 5.5 0.225 631.43<br />

Earth work in excavation, including<br />

stacking/disposal of surplus material with all lifts<br />

and lead upto 495 metres, exclusive of <strong>com</strong>pensation<br />

of earth [MoRTH specification : Clause 301 to 305]<br />

3.1.1.3 Mechanically by power shovel, including mechanical<br />

loading and carriage by tipper/dumper (6T capacity)<br />

Total= 631.43 cum 271.00 171119.00<br />

for Diversion for Construction of CD Works 30 125.00 5.5 0.5 10312.50<br />

For Diversion for Construction of Road 1 5550.00 5.5 0.5 15262.50<br />

25575.00 Cum 61.00 1560075.00<br />

10 3.7 Extra for laying earth as per specification for<br />

<strong>com</strong>paction in 200 mm thick loose layers and dressing<br />

[MoRTH Specification Clause 305.3.5].<br />

BY MECHANICAL MEANS, using Motor Grader,<br />

from earth in stock piles with all lead and lift but<br />

excluding rolling and watering.<br />

for Diversion for Construction of CD Works 30 125.00 5.5 0.5 10312.50<br />

For Diversion for Construction of Road 1 5550.00 5.5 0.5 15262.50<br />

25575.00 Cum 24.00 613800.00<br />

11 3.7.4 Extra for watering the earth to bring the earth upto<br />

required O.M.C excluding rolling<br />

for Diversion for Construction of CD Works 30 125.00 7.5 0.5 14062.50<br />

For Diversion for Construction of Road 1 5550.00 7.5 0.5 20812.50<br />

34875.00 cum 11.00 383625.00


12 R-3/6 Compaction of original ground with maximum of six<br />

passes of 8-10 tonnes power roller including filling<br />

depression occurring during rolling [MoRTH<br />

Specification : Clause 305.3.4]<br />

for Diversion for Construction of CD Works 30 125.00 7.5 28125.00<br />

For Diversion for Construction of Road 1 5550.00 7.5 41625.00<br />

Total= 697.50 sqm 199.00 138803.00<br />

13 R-3/4 Box cutting/Trenching the Sub Grade to proper slope,<br />

camber and removing inequalities including<br />

removing deleterious stuff and depositing on the road<br />

side slopes (cutting of earth shall be paid separately in<br />

the respective item on the basis of classification of the<br />

excavation done by the Engineer (MoRTH<br />

specification clause 301 to 305)<br />

for Diversion for Construction of CD Works 30 125.00 7.5 28125.00<br />

For Diversion for Construction of Road 1 5550.00 7.5 41625.00<br />

697.50 100<br />

sqm<br />

41.00 28598.00<br />

15 4.2 Providing and laying granular sub-base material<br />

having P.I.not more than 6, including spreading in<br />

layers not exceeding 150 mm <strong>com</strong>pacted thickness<br />

and consolidation by 8-10 tonne power roller to<br />

required camber and grade including cost of water<br />

and hire charges of machinery, including T&P with all<br />

lead (Compacted thickness to be measured).as per<br />

MORTH specification table 400-1, 400-2 :<br />

For grading-II with CBR value not less than 25.<br />

(i) to attain 100% proctor density.<br />

for Diversion for Construction of CD Works 30 125.00 5.50 0.15 3093.75<br />

For Diversion for Construction of Road 1 5550.00 5.5 0.15 4578.75<br />

Total= 7672.50 cum 275.00 2109938.00


R-5 Water Bound Macadam<br />

16 5.3 Providing, laying, spreading and <strong>com</strong>pacting stone<br />

aggregate of specfic as per table 400-7 to Water<br />

Bound Macadam specifi-cation including spreading<br />

in uniform thickness, hand packing roll-ing with<br />

vibratory roller in stages to proper grade and camber,<br />

applying and brooming requisite type of screening<br />

and binding materials to fill-up the interstices of<br />

coarse aggregates watering (with water browser) and<br />

rolling making necessary earthen bund to protect<br />

edegs, lighting, guarding, barricading and<br />

maintenance of diversion etc. [MoRTH specfication :<br />

Clause 404] ( By ma-nual means).<br />

5.2.2 Grading II , 63 mm to 45 mm @ 0.91 cum per 10 Sqm<br />

for <strong>com</strong>pacted thickness of 75 mm. (Crusher broken)<br />

Stone screening type 'B'<br />

for Diversion for Construction of CD Works 30 125.00 5.5 0.075 1546.88<br />

For Diversion for Construction of Road 1 5550.00 5.5 0.075 2289.38<br />

Total= 3836.25 cum 861.00 3303012.00<br />

5.2.3 Grading <strong>III</strong>, 53 mm to 22.4 mm, @ 0.91 cum per 10<br />

Sqm for <strong>com</strong>pacted thickness of 75 mm. (Crusher<br />

broken)<br />

Stone screening type 'B'<br />

for Diversion for Construction of CD Works 30 125.00 5.5 0.075 1546.88<br />

For Diversion for Construction of Road 1 5550.00 5.5 0.075 2289.38<br />

Total= 3836.25 cum 919.00 3525514.00<br />

B Hard shoulders<br />

17 R-4/2 Providing and laying granular sub-base material<br />

having P.I.not more than 6, including spreading in<br />

layers not exceeding 150 mm <strong>com</strong>pacted thickness<br />

and consolidation by 8-10 tonne power roller to<br />

required camber and grade including cost of water<br />

and hire charges of machinery, including T&P with all<br />

lead (Compacted thickness to be measured).as per<br />

MORTH specification table 400-1, 400-2 :<br />

2.1 For grading-II with CBR value not less than 25.


to attain 100% proctor density. 60 125.00 1 0.15 1125.00<br />

For Diversion for Construction of Road 2 5550.00 1 0.15 1665.00<br />

Total= 2790.00 Cum 275.00 767250.00<br />

R-6 Prime Coat<br />

18 6.1 Providing and applying primer coat over prepared<br />

surface or granular base with bitumen emulsion as<br />

per IS: 8887 & manufacturer’s specifications @ 6 kg<br />

/10 sqm with a self propelled or towed bitumen<br />

pressure sprayer equipped for spraying the material<br />

uniformly at specified rates and temperatures as per<br />

MoRTH specification CI 502 & 112 ( Including<br />

cleaning of road surface )<br />

for Diversion for Construction of CD Works 30 125.00 5.5 20625.00<br />

For Diversion for Construction of Road 1 5550.00 5.5 30525.00<br />

Total= 51150.00 sqm 21.00 1074150.00<br />

19 6.11 Providing and laying open graded premix carpet<br />

20mm thick (<strong>com</strong>pacted) on prepared surface in a<br />

single course as wearing course aggregates as per<br />

Table 500-23, heating bituminous binder @ 14.6<br />

Kg/10 Sqm.(60/70 grade) and aggregates in Hot Mix<br />

Plant (including cost of antistripping <strong>com</strong>pound ,<br />

wherever required), transporting the mixed material<br />

with tipper and laying with paver finisher to the<br />

required level and grade, rolling with power roller, 8-<br />

10 tonne but excluding cost of tack and seal coat with<br />

lead for mix of material 1 Km.[MORTH Specification :<br />

Clause 511,112]<br />

6.11.1 In Hot Mix Plant 100-120 TPH, including loading of<br />

aggregates with F.E loader with 60/70 bitumen.<br />

for Diversion for Construction of CD Works 30 125 5.5 20625.00<br />

For Diversion for Construction of Road 1 5550.00 5.5 30525.00<br />

Total= 51150.00 sqm 74.00 3785100.00


20 6.13 Providing and laying seal coat for sealing the<br />

voids in a bituminous surface laid to the<br />

specified levels, grade and cross fall, including<br />

rolling with a smooth wheeled roller 8 - 10 tonne<br />

capacity finished to required level and grades,<br />

<strong>com</strong>plete as per MORTH specification clause 513<br />

Laying by Manual Means<br />

6.13.2 Type B - <strong>com</strong>prising of 2.36 mm to 180 micron size<br />

aggregate @ 0.06 Cum per 10 Sqm and bitumen<br />

binder (60/70 grade) @ 6.8 Kg / 10 sqm<br />

for Diversion for Construction of CD Works 30 125 5.5 20625.00<br />

For Diversion for Construction of Road 1 5550.00 5.5 30525.00<br />

Total= 51150.00 sqm 29.00 1483350.00<br />

21 NBSR Silt Clearance from the CD works and for training of 10000.00 Cum 65.00 650000.00<br />

Stone Pitching on Slope<br />

22 R-11 /<br />

1.1.1<br />

Earth work in excavation for foundation of structure<br />

<strong>com</strong>plete with all lift, dewatering shoring and<br />

shuttering etc .including refilling of trenches in<br />

25.mm layers, ramming, watering and disposal of<br />

surplus soil within a lead of 1000 meters, as per<br />

drawing and technical specification.[MoRTH<br />

Specification : Clause : 304]<br />

For Embankment above 2.0m high 1.00 3200.00 2.50 0.60 4800.00<br />

Sloped length 4.47m taken for 2.0m average height<br />

embankment. C/c of CHhutes taken 5.0m. =1400/5 =<br />

640<br />

23 14.5 Providing and laying graded stone aggregate Filter<br />

Material underneath pitching on slopes <strong>com</strong>plete as<br />

per drawing and technical Specification [MoRTH<br />

Specification : Clause 2504]<br />

640.0 4.47 0.85 0.45 1094.26<br />

Total =<br />

5894.26 Cum 95.00 559954.32<br />

1.00 2656.00 4.47 0.15 1780.85 cum 617.00 1098783.22


24 14.4.2 Providing and laying Pitching on slopes <strong>com</strong>plete as<br />

per drawing and technical -specification. [MOST<br />

Specification : Clause : 2504]<br />

With R.R.Stone , weighing not less than 40 Kg,<br />

thickness not less than 150 mm (Specific gravity not<br />

less than 2.65).<br />

25 R-10/2 Providing and laying Plain cement concrete M15 mix<br />

with stone aggregate 20mm nominal size<br />

mechanically mixed and vibrated, in foundation up to<br />

a depth of 1.50 below Ground level and or 1.50 meters<br />

above ground/bed level.<br />

1.00 2656.00 4.47 0.30 3561.70 cum 754.00 2685518.78<br />

M15 Grade Mix 1.00 3200.00 0.45 0.15 216.00<br />

26 R-10/10Providing and laying Coursed / Random Rubble<br />

stone masonry in cement sand mortar 1:3, in<br />

foundation up to a depth of 1.50 meters and also 1.50<br />

meters above Ground /Bed level [MoRTH<br />

640.0 4.47 0.85 0.15 364.75<br />

640.0 4.47 0.60 0.08 128.74<br />

1.00 3200.00 0.45 0.08 115.20<br />

1.00 3104.00 0.45 0.75 1047.60<br />

1020 * 6.7 = 6834 2.00 2860.80 0.30 0.45 772.42<br />

27 10.16 Providing Cement plaster 12mm thick in cement<br />

mortar (1:3) at all levels [MoRTH Specification:<br />

Clause:1000/1300]<br />

28 R-<br />

14/2<br />

Stone Pitching on Shoulder<br />

Providing and laying graded stone aggregate Filter<br />

Material underneath pitching on slopes <strong>com</strong>plete as<br />

per drawing and technical Specification [MoRTH<br />

Specification : Clause 2504]<br />

Total =<br />

Total =<br />

2.0 640.00 4.47 1.05 6007.68<br />

Total =<br />

824.69 cum 2742.00 2261294.50<br />

1820.02 cum 2747.00 4999583.95<br />

6007.68 sqm 99.00 594760.32<br />

1.00 3104.00 2.05 0.15 954.48 sqm 617.00 588914.16


29 R-14/<br />

3.1<br />

Providing and laying Pitching on slopes <strong>com</strong>plete as<br />

per drawing and technical -specification. [MOST<br />

Specification : Clause : 2504]<br />

With R.R.Stone , weighing not less than 40 Kg,<br />

thickness not less than 150 mm (Specific gravity not<br />

less than 2.65).<br />

1.00 3104.00 2.05 0.30 1908.96 cum 754.00 1439355.84<br />

Cost of CD works 62752924.00<br />

G.Total<br />

=<br />

98017467.29


Improvement of Jodhpur - Osian - Phalodi Road km 2/000 to 121/500 (SH-61) under BOT Annuity Scheme<br />

(Jodhpur - Osian - Phalodi)<br />

Abstract of Quantites<br />

PART 'D' (D) SLAB CULVERTS -6 x 6.00 m span<br />

S.No. Item<br />

No.<br />

Description No. L B H Q Unit Rate Amount<br />

Exacavation for Structure<br />

1 R-11/ Earth work in excavation for foundation of structure<br />

<strong>com</strong>plete with all lift, dewatering shoring and<br />

shuttering etc. including refilling of trenches in 25mm<br />

layers, ramming, watering and disposal of surplus<br />

soil within a lead of 1000 meters, as per drawing and<br />

technical specification.[MoRTH Specification : Clause<br />

: 304]<br />

11.2 In hard Soil [MoRTH Specification : Clause : 301]<br />

2 R-<br />

10/10.<br />

1.2a<br />

At Mathania By Pass<br />

Abutments 2 14.5 3.6 1.5 156.60<br />

Pier 5 14.5 3.6 1.5 391.50<br />

Return wall 4 5 2.53 1.5 75.90<br />

Total= 624.00 cum 117.00 73008.00<br />

Providing and laying mechnically mixed and vibrated<br />

Cement Concrete in foundation upto a depth of 1.5<br />

metres below ground level and 1.50 metres above<br />

Ground/Bed level.[MoRTH Specification : Clause<br />

1000/1700]<br />

Cement concrete 1:3:6 mix crushed stone aggregates<br />

20mm nominal size.<br />

Abutment 2 14.5 3.6 0.4 41.76<br />

Pier 5 14.5 3.6 0.4 391.5<br />

Return wall 4 5 2.53 0.4 20.24<br />

Total= 453.50 cum 2217.00 1005410.00


3 R-10/ Providing and laying Random Rubble masonry in<br />

10.12.1 foundation upto a depth of 1.50 metres and 1.50<br />

metres above Ground /Bed level.[MoRTH<br />

Specfication: Clause 1000/1400]<br />

10.12.1 in 1:3 cement mortar<br />

Abutment stepI 2 14.5 2.8 0.8 64.96 cum<br />

Abutment stepII (2.4+.8)/2 2 14.5 1.6 2.5 116.00<br />

Deduction -4 14.5 0.2 0.2 -2.32<br />

-1 14.5 0.4 0.4 -2.32<br />

-2 14.5 0.3 0.4 -3.48<br />

Pier 5 14.5 3.2 0.4 92.80<br />

5 14.5 2.8 0.4 81.20<br />

5 14.5 2.4 0.4 69.60<br />

5 14.5 1.05 2.1 159.86<br />

Return wall 4 5 1.73 0.4 13.84<br />

4 5 1.115 2.5 55.75<br />

Parapet 2 42 0.4 0.5 16.80<br />

Raising of pier & Abutment 6 13 0.8 1 62.40<br />

Deduction -2 5 0.4 0.4 -1.60<br />

Total= 723.49 cum 2024.00 1464349.00<br />

4 10.13 Extra for Random Rubble masonry in cement sand<br />

mortar 1:3 in superstructures upto a height of 4<br />

metres or part thereof above 1.50m level from<br />

Ground/Bed level.[MoRTH Specfication : Clause<br />

1000/1400]<br />

I Random rubble masonry<br />

Parapet 2 48.4 0.4 0.5 19.36<br />

Total= 19.36 cum 156.00 3021.00<br />

5 R-10<br />

/10.16<br />

Plaster on new surface with cement mortar (1:3)<br />

including racking of joint etc. <strong>com</strong>plete fine finished<br />

12mm thick.<br />

Parapet 2 48.4 0.5 48.4<br />

Sides 4 0.5 0.4 0.8<br />

Total= 49.20 sqm 84.00 4133.00


6 R-10/<br />

10.14<br />

7 R-10/<br />

10.2<br />

Providing Cement pointing 1:2, flush on Brick-on -<br />

edge floor at all levels.[MoRTH Specfication: Clause<br />

1000/1300]<br />

Abutment 2 14.5 1.5 43.5<br />

2 11 3 66<br />

Pier 5 14.5 1.5 108.75<br />

5 11 3 165<br />

Return wall 4 5 1.25 25.0<br />

Parapet 2 48.4 0.5 48.4<br />

Total= 456.65 sqm 63.00 28769.00<br />

Providing and filling in foundation trenches, and at<br />

the back of abutments wing walls etc.and below pipe<br />

bed in layers not exceeding 150mm thick including<br />

watering and <strong>com</strong>pacting, including all lead and lifts.<br />

10.20.2 Selected granular material in filling [MoRTH<br />

Specification Clause :1500]<br />

Backfill on side wall 2 14.5 0.3 1.5 13.05<br />

Return wall 4 5 0.3 1.5 9<br />

Total= 22.05 cum 174.00 3837.00<br />

8 R-10/<br />

10.4<br />

Providing and laying RCC M20 mix with stone<br />

aggregate 20mm (nominal size) mechnically mixed<br />

and vibrated for RCC work in slab in superstru-cture<br />

upto 4 metre above 1.5 metre level from Bed/ Ground<br />

level, excluding steel reinforcement but including<br />

centeri<br />

Parapet wall 2 48.4 0.4 0.05 1.94<br />

Return wall 4 5 0.5 0.05 0.50<br />

Total= 2.44 cum 2838.00 6914.00<br />

9 10.23 Reinforced cement concrete M30 mix with stone<br />

aggregate 20mm nominal size mechnically mixed and<br />

vibrated for reinforced concrete work in slab in<br />

superstructure at any level excluding steel<br />

reinforcement but including center-ing and shuttering<br />

laid in posi


Slab 6 12 7 0.525 264.60<br />

Footpath & Kerb 2 42 0.55 0.375 17.33<br />

2 42 0.525 0.05 2.21<br />

Bed Plate 6 13 0.8 0.3 18.72<br />

Total= 302.85 cum 3530.00 1069061.00<br />

10 10.6.2 Providing and fabricating steel reinforcement fot<br />

R.C.C works including cutting, bending, placingin<br />

position and binding <strong>com</strong>plete including cost of<br />

binding wire .[MoRTH Specification : Clause<br />

1000/1600]<br />

Cold twisted bars<br />

80 kg/ cum 1 302.85 80 24228 Kg<br />

Total= 24.23 t 48787.00 1182012.00<br />

11 12.19 Slab seal type of expansion joint <strong>com</strong>plete as per<br />

drawing and technical specification including<br />

accptance testing as specified, to be installed under<br />

supervision of a specialist manufacture [MoRTH<br />

Specification 2600(N)]<br />

12 13.9 PCC M-15 grade levelling course below approach slab<br />

<strong>com</strong>plete as per drawing and MoRTH specifications<br />

clause 14.10.<br />

13 13.10 Reinforced cement concrete approach slab including<br />

reinforcement and formwork <strong>com</strong>plete as per<br />

drawing and MoRTH specifications section 1500,<br />

1600, 1700, 2704.<br />

7 12 84.00<br />

2 13 3.5 0.08 27.3<br />

2 13 3.5 0.3 27.30<br />

Total= 84.00 Metre 12717.00 1068228.00<br />

Total= 27.30 Cum 2327.00 63527.10<br />

Total= 27.30 Cum 5069.00 138383.70


14 13.11 Providing and applying 2 coats of water based<br />

cement paint to unplastered concrete surface after<br />

cleaning the surface of dirt, dust, oil, grease,<br />

efflorescense and applying paint @ of 1 litre for 2<br />

Sqm.<br />

15 R-2<br />

/2.4.1<br />

Parapet 2 48.4 0.9 87.12<br />

Dismantling upto 1.5m in foundation and / or 1.5m<br />

above ground level including T&P and scaffolding<br />

wherever necessary, sorting the dismantled material,<br />

disposal of unserviceable material, and stacking<br />

serviceable material with in a lead of 1000m.<br />

[MoRTH Specification clause 202]<br />

4 0.5 0.4 0.80<br />

Total= 87.92 Sqm 16.00 1406.72<br />

(ii) By Mechanical Means<br />

2.4.1.1. Reinforced Cement Concrete<br />

3<br />

Slab 5 8 7 0.4 112.00<br />

Total= 112.00 cum 534.00 59808.00<br />

16 2.4.3.2 RR Masonry in cement mortar<br />

Pier & Abutment 4 9 1.2 2.8 120.96<br />

2 8 1.6 2.8 71.68<br />

4 9.75 2.45 1.5 143.33<br />

2 9 2.65 1.5 71.55<br />

Parapet 2 48.4 0.5 0.4 19.36<br />

Total= 19.36 cum 129.00 2497.44<br />

G.Total = 6791801.46


Improvement of Jodhpur - Osian - Phalodi Road km 2/000 to 121/500 (SH-61) under BOT Annuity Scheme<br />

(Jodhpur - Osian - Phalodi)<br />

Abstract of Quantites<br />

PART 'D' (D) SLAB CULVERTS -3 x 6.00 m span<br />

S.No. Item<br />

No.<br />

Description No. L B H Q Unit Rate Amount<br />

Exacavation for Structure<br />

1 R-11/ Earth work in excavation for foundation of structure<br />

<strong>com</strong>plete with all lift, dewatering shoring and<br />

shuttering etc. including refilling of trenches in 25mm<br />

layers, ramming, watering and disposal of surplus<br />

soil within a lead of 1000 meters, as per drawing and<br />

technical specification.[MoRTH Specification : Clause<br />

: 304]<br />

11.2 In hard Soil [MoRTH Specification : Clause : 301]<br />

2 R-<br />

10/10.<br />

1.2a<br />

At Mathania By Pass<br />

Abutments 2 14.5 3.6 1.5 156.60<br />

Pier 2 14.5 3.6 1.5 156.60<br />

Return wall 4 5 2.53 1.5 75.90<br />

Total= 389.10 cum 117.00 45525.00<br />

Providing and laying mechnically mixed and vibrated<br />

Cement Concrete in foundation upto a depth of 1.5<br />

metres below ground level and 1.50 metres above<br />

Ground/Bed level.[MoRTH Specification : Clause<br />

1000/1700]<br />

Cement concrete 1:3:6 mix crushed stone aggregates<br />

20mm nominal size.<br />

Abutment 2 14.5 3.6 0.4 41.76<br />

Pier 2 14.5 3.6 0.4 156.6<br />

Return wall 4 5 2.53 0.4 20.24<br />

Total= 218.60 cum 2217.00 484637.00


3 R-10/ Providing and laying Random Rubble masonry in<br />

10.12.1 foundation upto a depth of 1.50 metres and 1.50<br />

metres above Ground /Bed level.[MoRTH<br />

Specfication: Clause 1000/1400]<br />

10.12.1 in 1:3 cement mortar<br />

Abutment stepI 2 14.5 2.8 0.8 64.96 cum<br />

Abutment stepII (2.4+.8)/2 2 14.5 1.6 2.5 116.00<br />

Deduction -4 14.5 0.2 0.2 -2.32<br />

-1 14.5 0.4 0.4 -2.32<br />

-2 14.5 0.3 0.4 -3.48<br />

Pier 2 14.5 3.2 0.4 37.12<br />

2 14.5 2.8 0.4 32.48<br />

2 14.5 2.4 0.4 27.84<br />

2 14.5 1.05 2.1 63.95<br />

Return wall 4 5 1.73 0.4 13.84<br />

4 5 1.115 2.5 55.75<br />

Parapet 2 42 0.4 0.5 16.80<br />

Raising of pier & Abutment 6 13 0.8 1 62.40<br />

Deduction -2 5 0.4 0.4 -1.60<br />

Total= 481.42 cum 2024.00 974384.00<br />

4 10.13 Extra for Random Rubble masonry in cement sand<br />

mortar 1:3 in superstructures upto a height of 4<br />

metres or part thereof above 1.50m level from<br />

Ground/Bed level.[MoRTH Specfication : Clause<br />

1000/1400]<br />

I Random rubble masonry<br />

Parapet 2 29.2 0.4 0.5 11.68<br />

Total= 11.68 cum 156.00 1823.00<br />

5 R-10<br />

/10.16<br />

Plaster on new surface with cement mortar (1:3)<br />

including racking of joint etc. <strong>com</strong>plete fine finished<br />

12mm thick.<br />

Parapet 2 29.2 0.5 29.2<br />

Sides 4 0.5 0.4 0.8<br />

Total= 30.00 sqm 84.00 2520.00


6 R-10/<br />

10.14<br />

7 R-10/<br />

10.2<br />

Providing Cement pointing 1:2, flush on Brick-on -<br />

edge floor at all levels.[MoRTH Specfication: Clause<br />

1000/1300]<br />

Abutment 2 14.5 1.5 43.5<br />

2 11 3 66<br />

Pier 2 14.5 1.5 43.5<br />

2 11 3 66<br />

Return wall 4 5 1.25 25.0<br />

Parapet 2 29.2 0.5 29.2<br />

Total= 273.2 sqm 63.00 17212.00<br />

Providing and filling in foundation trenches, and at<br />

the back of abutments wing walls etc.and below pipe<br />

bed in layers not exceeding 150mm thick including<br />

watering and <strong>com</strong>pacting, including all lead and lifts.<br />

10.20.2 Selected granular material in filling [MoRTH<br />

Specification Clause :1500]<br />

Backfill on side wall 2 14.5 0.3 1.5 13.05<br />

Return wall 4 5 0.3 1.5 9<br />

Total= 22.05 cum 174.00 3837.00<br />

8 R-10/<br />

10.4<br />

Providing and laying RCC M20 mix with stone<br />

aggregate 20mm (nominal size) mechnically mixed<br />

and vibrated for RCC work in slab in superstru-cture<br />

upto 4 metre above 1.5 metre level from Bed/ Ground<br />

level, excluding steel reinforcement but including<br />

centeri<br />

Parapet wall 2 29.2 0.4 0.05 1.17<br />

Return wall 4 5 0.5 0.05 0.50<br />

Total= 1.67 cum 2838.00 4734.00<br />

12 10.23 Reinforced cement concrete M30 mix with stone<br />

aggregate 20mm nominal size mechnically mixed and<br />

vibrated for reinforced concrete work in slab in<br />

superstructure at any level excluding steel<br />

reinforcement but including center-ing and shuttering<br />

laid in posi


Slab 3 12 7 0.525 132.30<br />

Footpath & Kerb 2 21 0.55 0.375 8.66<br />

2 21 0.525 0.05 1.10<br />

Bed Plate 6 13 0.8 0.3 18.72<br />

Total= 160.79 cum 3530.00 567572.00<br />

13 10.6.2 Providing and fabricating steel reinforcement fot<br />

R.C.C works including cutting, bending, placingin<br />

position and binding <strong>com</strong>plete including cost of<br />

binding wire .[MoRTH Specification : Clause<br />

1000/1600]<br />

Cold twisted bars<br />

80 kg/ cum 1 160.785 80 12862.8 Kg<br />

Total= 12.86 t 48787.00 627538.00<br />

14 12.19 Slab seal type of expansion joint <strong>com</strong>plete as per<br />

drawing and technical specification including<br />

accptance testing as specified, to be installed under<br />

supervision of a specialist manufacture [MoRTH<br />

Specification 2600(N)]<br />

15 13.9 PCC M-15 grade levelling course below approach slab<br />

<strong>com</strong>plete as per drawing and MoRTH specifications<br />

clause 14.10.<br />

16 13.10 Reinforced cement concrete approach slab including<br />

reinforcement and formwork <strong>com</strong>plete as per<br />

drawing and MoRTH specifications section 1500,<br />

1600, 1700, 2704.<br />

17 13.11 Providing and applying 2 coats of water based<br />

cement paint to unplastered concrete surface after<br />

cleaning the surface of dirt, dust, oil, grease,<br />

efflorescense and applying paint @ of 1 litre for 2<br />

4 12 48.00<br />

2 13 3.5 0.08 27.3<br />

2 13 3.5 0.3 27.30<br />

Total= 48.00 Metre 12717.00 610416.00<br />

Total= 27.30 Cum 2327.00 63527.10<br />

Total= 27.30 Cum 5069.00 138383.70


18 R-2<br />

/2.4.1<br />

Parapet 2 29.2 0.9 52.56<br />

Dismantling upto 1.5m in foundation and / or 1.5m<br />

above ground level including T&P and scaffolding<br />

wherever necessary, sorting the dismantled material,<br />

disposal of unserviceable material, and stacking<br />

serviceable material with in a lead of 1000m.<br />

[MoRTH Specification clause 202]<br />

4 0.5 0.4 0.80<br />

Total= 53.36 Sqm 16.00 853.76<br />

(ii) By Mechanical Means<br />

2.4.1.1. Reinforced Cement Concrete<br />

3<br />

Slab 5 8 7 0.4 112.00<br />

Total= 112.00 cum 534.00 59808.00<br />

2.4.3.2 RR Masonry in cement mortar<br />

Pier & Abutment 4 9 1.2 2.8 120.96<br />

2 8 1.6 2.8 71.68<br />

4 9.75 2.45 1.5 143.33<br />

2 9 2.65 1.5 71.55<br />

Parapet 2 29.2 0.5 0.4 11.68<br />

Total= 11.68 cum 129.00 1506.72<br />

G.Total = 3964705.01


Improvement of Jodhpur - Osian - Phalodi Road km 2/000 to 121/500 (SH-61) under BOT Annuity Scheme (Jodhpur - Osian -<br />

Phalodi)<br />

PART 'D' (A)- New Culverts 2 x 1.0 * 1.0 RCC Box<br />

S.<br />

No.<br />

Item<br />

No.<br />

1 Exacavation for Structure<br />

2 R-10/<br />

10.1.2a<br />

3 R-10/<br />

10.12<br />

Description No. L B H Q Unit Rate Amount<br />

R -11 Earth work in excavation for foundation of structure<br />

<strong>com</strong>plete with all lift, dewatering shoring and shuttering<br />

etc.including refilling of trenches in 25.mm layers,<br />

ramming, watering and disposal of surplus soil within a<br />

lead of 1000 metres, as per drawing and technical<br />

specfication.[MoRTH Specification : Clause : 304]<br />

11.2 In Hard Soil [MoRTH Specification : Clause : 301]<br />

upto 3.0m depth<br />

For Side Walls 2 9.00 1.50 1.20 32.40<br />

Total= 32.40 cum 140.00 4536.00<br />

Providing and laying mechanically mixed and vibrated<br />

Cement Concrete in foundation upto a depth of 1.5 metres<br />

below ground level and 1.50 metres above Ground/Bed<br />

level.[MoRTH Specification : Clause 1000/1700]<br />

Cement concrete 1:3:6 mix crushed stone aggregates 20mm<br />

nominal size.<br />

For Side Walls 2 9.00 1.50 0.15 4.05<br />

Total= 4.05 cum 2526.00 10231.00<br />

Providing and laying Random Rubble masonry in<br />

foundation upto a depth of 1.50 metres and 1.50 metres<br />

above Ground /Bed level.[MoRTH Specfication: Clause<br />

1000/1400]<br />

Abstract of Quantites<br />

10.12.1 in 1:3 cement mortar<br />

Side Walls 2 9.00 0.8 1.5 21.60<br />

Above Box 2 3.00 0.6 1.5 5.40<br />

Parapet 2 3.20 0.4 0.6 1.54


Total= 28.54 cum 2586.00 73795.00<br />

4 10.13 Extra for Random Rubble masonry in cement sand mortar<br />

1:3 in superstructures upto a height of 4 metres or part<br />

thereof above 1.50m level from Ground/Bed level.[MoRTH<br />

Specfication : Clause 1000/1400]<br />

Parapet 2 3.20 0.40 0.6 1.54 cum<br />

Total= 1.54 cum 198.00 305.00<br />

5 10.32 /<br />

Jp<br />

Providing and laying Precast reinforced cement concrete<br />

Box culvert section of M-40 grade designed for 'AA' class<br />

loading as per IRC specifications including to effect of<br />

impact, EQ etc. <strong>com</strong>plete on form base of 200mm thick lean<br />

concrete of M-10 grade with aggregate of size 40mm<br />

nominal of following internal size the work includes<br />

required safety measures construction of drain for<br />

diversion of flowing water cost of design of RCC Precast<br />

Box and its proof checking from IIT/MNIT Jaipur <strong>com</strong>plete<br />

in all respect as per specifications<br />

10.32.7 Size 1.00 M x 1.00 M 2 12 24<br />

Total= 24 m 11604.00 278496.00<br />

6 10.16 Providing Cement plaster 12mm thick in cement mortar<br />

(1:3) at all levels [MoRTH Specification: Clause:1000/1300]<br />

Parapet inner face 4 3.20 0.9 11.52<br />

Sides 4 9.00 0.5 18<br />

Total= 29.52 sqm 99.00 2923.00<br />

7 10.14 Providing Cement pointing 1:2 deep variety (cut or<br />

weather) on brick, stone and tile work at all levels.[MoRTH<br />

Specfication : Clause 1000/1300]<br />

Side Walls 2 9.0 2.4 42.3<br />

Above Box 2 10.40 1.5 31.2<br />

Total= 73.5 sqm 73.00 5366.00


8 10.20.2 Providing and filling in foundation trenches, and at the<br />

back of abutments wing walls etc. and below pipe bed in<br />

layers not exceeding 150mm thick including watering and<br />

<strong>com</strong>pacting, including all lead and lifts.<br />

Selected granular material in filling [MoRTH Specification<br />

Clause :1500]<br />

Filling Behind Wing Walls 2 9.0 1.5 0.45 12.15<br />

Filling Behind Box 2 12 1.5 0.45 16.2<br />

9 10.5 Providing and laying Reinforced cement concrete M20 mix<br />

with stone aggregate 20mm nominal size mechanically<br />

mixed and vibrated for bed plates excluding steel<br />

reinforcement but including centering and shuttering, laid<br />

in position .[MoRTH Specification : Clause 1000/700]<br />

Total= 28.35 cum 194.00 5500.00<br />

Wing Wall Coping 2 9.0 0.45 0.075 0.6075<br />

Parapet coping 2 3.20 0.45 0.075 0.216<br />

0.8235 Cum 3,172.00 2613.00<br />

G.Total = 383765.00


Improvement of Jodhpur - Osian - Phalodi Road km 2/000 to 121/500 (SH-61) under BOT Annuity Scheme (Jodhpur - Osian -<br />

Phalodi)<br />

PART 'D' (A)- New Culverts 4 x 1.0 * 1.0 RCC Box<br />

S.<br />

No.<br />

Item<br />

No.<br />

1 Exacavation for Structure<br />

2 R-10/<br />

10.1.2a<br />

3 R-10/<br />

10.12<br />

Description No. L B H Q Unit Rate Amount<br />

R -11 Earth work in excavation for foundation of structure<br />

<strong>com</strong>plete with all lift, dewatering shoring and shuttering<br />

etc.including refilling of trenches in 25.mm layers,<br />

ramming, watering and disposal of surplus soil within a<br />

lead of 1000 metres, as per drawing and technical<br />

specfication.[MoRTH Specification : Clause : 304]<br />

11.2 In Hard Soil [MoRTH Specification : Clause : 301]<br />

upto 3.0m depth<br />

For Side Walls 2 10.00 1.50 1.20 36.00<br />

Total= 36.00 cum 140.00 5040.00<br />

Providing and laying mechanically mixed and vibrated<br />

Cement Concrete in foundation upto a depth of 1.5 metres<br />

below ground level and 1.50 metres above Ground/Bed<br />

level.[MoRTH Specification : Clause 1000/1700]<br />

Cement concrete 1:3:6 mix crushed stone aggregates 20mm<br />

nominal size.<br />

For Side Walls 2 10.00 1.50 0.15 4.50<br />

Total= 4.50 cum 2526.00 11367.00<br />

Providing and laying Random Rubble masonry in<br />

foundation upto a depth of 1.50 metres and 1.50 metres<br />

above Ground /Bed level.[MoRTH Specfication: Clause<br />

1000/1400]<br />

Abstract of Quantites<br />

10.12.1 in 1:3 cement mortar<br />

Side Walls 2 10.00 0.8 1.5 24.00<br />

Above Box 2 6.00 0.6 1.5 10.80<br />

Parapet 2 6.00 0.4 0.6 2.88


Total= 37.68 cum 2586.00 97441.00<br />

4 10.13 Extra for Random Rubble masonry in cement sand mortar<br />

1:3 in superstructures upto a height of 4 metres or part<br />

thereof above 1.50m level from Ground/Bed level.[MoRTH<br />

Specfication : Clause 1000/1400]<br />

Parapet 2 6.00 0.40 0.6 2.88 cum<br />

Total= 2.88 cum 198.00 571.00<br />

5 10.32 /<br />

Jp<br />

Providing and laying Precast reinforced cement concrete<br />

Box culvert section of M-40 grade designed for 'AA' class<br />

loading as per IRC specifications including to effect of<br />

impact, EQ etc. <strong>com</strong>plete on form base of 200mm thick lean<br />

concrete of M-10 grade with aggregate of size 40mm<br />

nominal of following internal size the work includes<br />

required safety measures construction of drain for<br />

diversion of flowing water cost of design of RCC Precast<br />

Box and its proof checking from IIT/MNIT Jaipur <strong>com</strong>plete<br />

in all respect as per specifications<br />

10.32.7 Size 1.00 M x 1.00 M 4 12 48<br />

Total= 48 m 11604.00 556992.00<br />

6 10.16 Providing Cement plaster 12mm thick in cement mortar<br />

(1:3) at all levels [MoRTH Specification: Clause:1000/1300]<br />

Parapet inner face 4 6.00 0.9 21.6<br />

Sides 4 10.00 0.5 20<br />

Total= 41.6 sqm 99.00 4119.00<br />

7 10.14 Providing Cement pointing 1:2 deep variety (cut or<br />

weather) on brick, stone and tile work at all levels.[MoRTH<br />

Specfication : Clause 1000/1300]<br />

Side Walls 2 10.0 2.4 47.0<br />

Above Box 2 10.40 1.5 31.2<br />

Total= 78.2 sqm 73.00 5709.00


8 10.20.2 Providing and filling in foundation trenches, and at the<br />

back of abutments wing walls etc. and below pipe bed in<br />

layers not exceeding 150mm thick including watering and<br />

<strong>com</strong>pacting, including all lead and lifts.<br />

Selected granular material in filling [MoRTH Specification<br />

Clause :1500]<br />

Filling Behind Wing Walls 2 10.0 1.5 0.45 13.5<br />

Filling Behind Box 2 12 1.5 0.45 16.2<br />

9 10.5 Providing and laying Reinforced cement concrete M20 mix<br />

with stone aggregate 20mm nominal size mechanically<br />

mixed and vibrated for bed plates excluding steel<br />

reinforcement but including centering and shuttering, laid<br />

in position .[MoRTH Specification : Clause 1000/700]<br />

Total= 29.7 cum 194.00 5762.00<br />

Wing Wall Coping 2 10.0 0.45 0.075 0.675<br />

Parapet coping 2 6.00 0.45 0.075 0.405<br />

1.08 Cum 3,172.00 3426.00<br />

G.Total = 690427.00


Improvement of Jodhpur - Osian - Phalodi Road km 2/000 to 121/500 (SH-61) under BOT Annuity Scheme (Jodhpur - Osian -<br />

Phalodi)<br />

PART 'D' (A)- New Culverts 6 x 1.0 * 1.0 RCC Box<br />

S.<br />

No.<br />

Item<br />

No.<br />

1 Exacavation for Structure<br />

2 R-10/<br />

10.1.2a<br />

3 R-10/<br />

10.12<br />

Description No. L B H Q Unit Rate Amount<br />

R -11 Earth work in excavation for foundation of structure<br />

<strong>com</strong>plete with all lift, dewatering shoring and shuttering<br />

etc.including refilling of trenches in 25.mm layers,<br />

ramming, watering and disposal of surplus soil within a<br />

lead of 1000 metres, as per drawing and technical<br />

specfication.[MoRTH Specification : Clause : 304]<br />

11.2 In Hard Soil [MoRTH Specification : Clause : 301]<br />

upto 3.0m depth<br />

For Side Walls 2 12.00 1.50 1.20 43.20<br />

Total= 43.20 cum 140.00 6048.00<br />

Providing and laying mechanically mixed and vibrated<br />

Cement Concrete in foundation upto a depth of 1.5 metres<br />

below ground level and 1.50 metres above Ground/Bed<br />

level.[MoRTH Specification : Clause 1000/1700]<br />

Cement concrete 1:3:6 mix crushed stone aggregates 20mm<br />

nominal size.<br />

For Side Walls 2 12.00 1.50 0.15 5.40<br />

Total= 5.40 cum 2526.00 13641.00<br />

Providing and laying Random Rubble masonry in<br />

foundation upto a depth of 1.50 metres and 1.50 metres<br />

above Ground /Bed level.[MoRTH Specfication: Clause<br />

1000/1400]<br />

Abstract of Quantites<br />

10.12.1 in 1:3 cement mortar<br />

Side Walls 2 12.00 0.8 1.5 28.80<br />

Above Box 2 9.00 0.6 1.5 16.20<br />

Parapet 2 9.00 0.4 0.6 4.32


Total= 49.32 cum 2586.00 127542.00<br />

4 10.13 Extra for Random Rubble masonry in cement sand mortar<br />

1:3 in superstructures upto a height of 4 metres or part<br />

thereof above 1.50m level from Ground/Bed level.[MoRTH<br />

Specfication : Clause 1000/1400]<br />

Parapet 2 9.00 0.40 0.6 4.32 cum<br />

Total= 4.32 cum 198.00 856.00<br />

5 10.32 /<br />

Jp<br />

Providing and laying Precast reinforced cement concrete<br />

Box culvert section of M-40 grade designed for 'AA' class<br />

loading as per IRC specifications including to effect of<br />

impact, EQ etc. <strong>com</strong>plete on form base of 200mm thick lean<br />

concrete of M-10 grade with aggregate of size 40mm<br />

nominal of following internal size the work includes<br />

required safety measures construction of drain for<br />

diversion of flowing water cost of design of RCC Precast<br />

Box and its proof checking from IIT/MNIT Jaipur <strong>com</strong>plete<br />

in all respect as per specifications<br />

10.32.7 Size 1.00 M x 1.00 M 4 12 48<br />

Total= 48 m 11604.00 556992.00<br />

6 10.16 Providing Cement plaster 12mm thick in cement mortar<br />

(1:3) at all levels [MoRTH Specification: Clause:1000/1300]<br />

Parapet inner face 4 9.00 0.9 32.4<br />

Sides 4 12.00 0.5 24<br />

Total= 56.4 sqm 99.00 5584.00<br />

7 10.14 Providing Cement pointing 1:2 deep variety (cut or<br />

weather) on brick, stone and tile work at all levels.[MoRTH<br />

Specfication : Clause 1000/1300]<br />

Side Walls 2 12.0 2.4 56.4<br />

Above Box 2 10.40 1.5 31.2<br />

Total= 87.6 sqm 73.00 6395.00


8 10.20.2 Providing and filling in foundation trenches, and at the<br />

back of abutments wing walls etc. and below pipe bed in<br />

layers not exceeding 150mm thick including watering and<br />

<strong>com</strong>pacting, including all lead and lifts.<br />

Selected granular material in filling [MoRTH Specification<br />

Clause :1500]<br />

Filling Behind Wing Walls 2 12.0 1.5 0.45 16.2<br />

Filling Behind Box 2 12 1.5 0.45 16.2<br />

9 10.5 Providing and laying Reinforced cement concrete M20 mix<br />

with stone aggregate 20mm nominal size mechanically<br />

mixed and vibrated for bed plates excluding steel<br />

reinforcement but including centering and shuttering, laid<br />

in position .[MoRTH Specification : Clause 1000/700]<br />

Total= 32.4 cum 194.00 6286.00<br />

Wing Wall Coping 2 12.0 0.45 0.075 0.81<br />

Parapet coping 2 9.00 0.45 0.075 0.6075<br />

1.4175 Cum 3,172.00 4497.00<br />

G.Total = 727841.00


Improvement of Jodhpur - Osian - Phalodi Road km 2/000 to 121/500 (SH-61) under BOT Annuity Scheme (Jodhpur - Osian -<br />

Phalodi)<br />

PART 'D' (A)- New Culverts 8 x 1.0 * 1.0 RCC Box<br />

S.<br />

No.<br />

Item<br />

No.<br />

1 Exacavation for Structure<br />

2 R-10/<br />

10.1.2a<br />

3 R-10/<br />

10.12<br />

Description No. L B H Q Unit Rate Amount<br />

R -11 Earth work in excavation for foundation of structure<br />

<strong>com</strong>plete with all lift, dewatering shoring and shuttering<br />

etc.including refilling of trenches in 25.mm layers,<br />

ramming, watering and disposal of surplus soil within a<br />

lead of 1000 metres, as per drawing and technical<br />

specfication.[MoRTH Specification : Clause : 304]<br />

11.2 In Hard Soil [MoRTH Specification : Clause : 301]<br />

upto 3.0m depth<br />

For Side Walls 2 15.00 1.50 1.20 54.00<br />

Total= 54.00 cum 140.00 7560.00<br />

Providing and laying mechanically mixed and vibrated<br />

Cement Concrete in foundation upto a depth of 1.5 metres<br />

below ground level and 1.50 metres above Ground/Bed<br />

level.[MoRTH Specification : Clause 1000/1700]<br />

Cement concrete 1:3:6 mix crushed stone aggregates 20mm<br />

nominal size.<br />

For Side Walls 2 15.00 1.50 0.15 6.75<br />

Total= 6.75 cum 2526.00 17051.00<br />

Providing and laying Random Rubble masonry in<br />

foundation upto a depth of 1.50 metres and 1.50 metres<br />

above Ground /Bed level.[MoRTH Specfication: Clause<br />

1000/1400]<br />

Abstract of Quantites<br />

10.12.1 in 1:3 cement mortar<br />

Side Walls 2 15.00 0.8 1.5 36.00<br />

Above Box 2 12.00 0.6 1.5 21.60<br />

Parapet 2 12.00 0.4 0.6 5.76


Total= 63.36 cum 2586.00 163849.00<br />

4 10.13 Extra for Random Rubble masonry in cement sand mortar<br />

1:3 in superstructures upto a height of 4 metres or part<br />

thereof above 1.50m level from Ground/Bed level.[MoRTH<br />

Specfication : Clause 1000/1400]<br />

Parapet 2 12.00 0.40 0.6 5.76 cum<br />

Total= 5.76 cum 198.00 1141.00<br />

5 10.32 /<br />

Jp<br />

Providing and laying Precast reinforced cement concrete<br />

Box culvert section of M-40 grade designed for 'AA' class<br />

loading as per IRC specifications including to effect of<br />

impact, EQ etc. <strong>com</strong>plete on form base of 200mm thick lean<br />

concrete of M-10 grade with aggregate of size 40mm<br />

nominal of following internal size the work includes<br />

required safety measures construction of drain for<br />

diversion of flowing water cost of design of RCC Precast<br />

Box and its proof checking from IIT/MNIT Jaipur <strong>com</strong>plete<br />

in all respect as per specifications<br />

10.32.7 Size 1.00 M x 1.00 M 8 12 96<br />

Total= 96 m 11604.00 1113984.00<br />

6 10.16 Providing Cement plaster 12mm thick in cement mortar<br />

(1:3) at all levels [MoRTH Specification: Clause:1000/1300]<br />

Parapet inner face 4 12.00 0.9 43.2<br />

Sides 4 0.00 0.5 0<br />

Total= 43.2 sqm 99.00 4277.00<br />

7 10.14 Providing Cement pointing 1:2 deep variety (cut or<br />

weather) on brick, stone and tile work at all levels.[MoRTH<br />

Specfication : Clause 1000/1300]<br />

Side Walls 2 0.0 2.4 0.0<br />

Above Box 2 10.40 1.5 31.2<br />

Total= 31.2 sqm 73.00 2278.00


8 10.20.2 Providing and filling in foundation trenches, and at the<br />

back of abutments wing walls etc. and below pipe bed in<br />

layers not exceeding 150mm thick including watering and<br />

<strong>com</strong>pacting, including all lead and lifts.<br />

Selected granular material in filling [MoRTH Specification<br />

Clause :1500]<br />

Filling Behind Wing Walls 2 0.0 1.5 0.45 0<br />

Filling Behind Box 2 12 1.5 0.45 16.2<br />

9 10.5 Providing and laying Reinforced cement concrete M20 mix<br />

with stone aggregate 20mm nominal size mechanically<br />

mixed and vibrated for bed plates excluding steel<br />

reinforcement but including centering and shuttering, laid<br />

in position .[MoRTH Specification : Clause 1000/700]<br />

Total= 16.2 cum 194.00 3143.00<br />

Wing Wall Coping 2 0.0 0.45 0.075 0<br />

Parapet coping 2 12.00 0.45 0.075 0.81<br />

0.81 Cum 3,172.00 2570.00<br />

G.Total = 1315853.00


Improvement of Jodhpur - Osian - Phalodi Road km 2/000 to 121/500 (SH-61) under BOT Annuity Scheme (Jodhpur - Osian -<br />

Phalodi)<br />

PART 'D' (A)- New Culverts 10 x 1.0 * 1.0 RCC Box<br />

S.<br />

No.<br />

Item<br />

No.<br />

1 Exacavation for Structure<br />

2 R-10/<br />

10.1.2a<br />

3 R-10/<br />

10.12<br />

Description No. L B H Q Unit Rate Amount<br />

R -11 Earth work in excavation for foundation of structure<br />

<strong>com</strong>plete with all lift, dewatering shoring and shuttering<br />

etc.including refilling of trenches in 25.mm layers,<br />

ramming, watering and disposal of surplus soil within a<br />

lead of 1000 metres, as per drawing and technical<br />

specfication.[MoRTH Specification : Clause : 304]<br />

11.2 In Hard Soil [MoRTH Specification : Clause : 301]<br />

upto 3.0m depth<br />

For Side Walls 2 15.00 1.50 1.20 54.00<br />

Total= 54.00 cum 140.00 7560.00<br />

Providing and laying mechanically mixed and vibrated<br />

Cement Concrete in foundation upto a depth of 1.5 metres<br />

below ground level and 1.50 metres above Ground/Bed<br />

level.[MoRTH Specification : Clause 1000/1700]<br />

Cement concrete 1:3:6 mix crushed stone aggregates 20mm<br />

nominal size.<br />

For Side Walls 2 15.00 1.50 0.15 6.75<br />

Total= 6.75 cum 2526.00 17051.00<br />

Providing and laying Random Rubble masonry in<br />

foundation upto a depth of 1.50 metres and 1.50 metres<br />

above Ground /Bed level.[MoRTH Specfication: Clause<br />

1000/1400]<br />

Abstract of Quantites<br />

10.12.1 in 1:3 cement mortar<br />

Side Walls 2 15.00 0.8 1.5 36.00<br />

Above Box 2 10.40 0.6 1.5 18.72<br />

Parapet 2 15.00 0.4 0.6 7.20


Total= 61.92 cum 2586.00 160126.00<br />

4 10.13 Extra for Random Rubble masonry in cement sand mortar<br />

1:3 in superstructures upto a height of 4 metres or part<br />

thereof above 1.50m level from Ground/Bed level.[MoRTH<br />

Specfication : Clause 1000/1400]<br />

Parapet 2 15.00 0.40 0.6 7.20 cum<br />

Total= 7.20 cum 198.00 1426.00<br />

5 10.32 /<br />

Jp<br />

Providing and laying Precast reinforced cement concrete<br />

Box culvert section of M-40 grade designed for 'AA' class<br />

loading as per IRC specifications including to effect of<br />

impact, EQ etc. <strong>com</strong>plete on form base of 200mm thick lean<br />

concrete of M-10 grade with aggregate of size 40mm<br />

nominal of following internal size the work includes<br />

required safety measures construction of drain for<br />

diversion of flowing water cost of design of RCC Precast<br />

Box and its proof checking from IIT/MNIT Jaipur <strong>com</strong>plete<br />

in all respect as per specifications<br />

10.32.5 Size 1.00 M x 1.00 M 10 12 120<br />

Total= 120 m 11604.00 1392480.00<br />

6 10.16 Providing Cement plaster 12mm thick in cement mortar<br />

(1:3) at all levels [MoRTH Specification: Clause:1000/1300]<br />

Parapet inner face 4 15.00 0.9 54<br />

Sides 4 15.00 0.5 30<br />

Total= 84 sqm 99.00 8316.00<br />

7 10.14 Providing Cement pointing 1:2 deep variety (cut or<br />

weather) on brick, stone and tile work at all levels.[MoRTH<br />

Specfication : Clause 1000/1300]<br />

Side Walls 2 15.0 2.4 70.5<br />

Above Box 2 10.40 1.5 31.2<br />

Total= 101.7 sqm 73.00 7425.00


8 10.20.2 Providing and filling in foundation trenches, and at the<br />

back of abutments wing walls etc. and below pipe bed in<br />

layers not exceeding 150mm thick including watering and<br />

<strong>com</strong>pacting, including all lead and lifts.<br />

Selected granular material in filling [MoRTH Specification<br />

Clause :1500]<br />

Filling Behind Wing Walls 2 15.0 1.5 0.45 20.25<br />

Filling Behind Box 2 12 1.5 0.45 16.2<br />

9 10.5 Providing and laying Reinforced cement concrete M20 mix<br />

with stone aggregate 20mm nominal size mechanically<br />

mixed and vibrated for bed plates excluding steel<br />

reinforcement but including centering and shuttering, laid<br />

in position .[MoRTH Specification : Clause 1000/700]<br />

Total= 36.45 cum 194.00 7072.00<br />

Wing Wall Coping 2 15.0 0.45 0.075 1.0125<br />

Parapet coping 2 15.00 0.45 0.075 1.0125<br />

2.025 Cum 3,172.00 6424.00<br />

G.Total = 1607880.00


Improvement of Jodhpur - Osian - Phalodi Road km 2/000 to 121/500 (SH-61) under BOT Annuity Scheme (Jodhpur - Osian -<br />

Phalodi)<br />

PART 'M' Pick up Bus Stop<br />

S. Item No.<br />

No.<br />

Description No. L B H factor Q Unit Rate Amount<br />

1 Clearing and Grubbing Road Land<br />

R-2/3 Clearing and grubbing road land including uprooting rank<br />

vegetation, grass, Truckhes, shrubs, saplings and trees girth<br />

upto 300 mm, removal of stumps of trees cut earlier and<br />

disposal of unserviceable materials and stacking of<br />

serviceable material upto a lead of 1000m including removal<br />

and disposal of top organic soil not exceeding in 150 mm<br />

thickness as per MORTH specification clause 201<br />

(ii) By Mechanical Means<br />

(A) In Area of light jungle<br />

Abstract of Quantites<br />

2 R-3/ 3.1 Earth work in excavation, including stacking/disposal of<br />

surplus material with all lifts and lead upto 495 metres,<br />

exclusive of <strong>com</strong>pensation of earth [MoRTH specification :<br />

Clause 301 to 305]<br />

3.1.1.3 Mechanically by power shovel, including mechanical<br />

loading and carriage by tipper/dumper (6T capacity)<br />

2 165 10 1 3300.00<br />

Total=<br />

0.33 hect 24895.0 8216.00<br />

2 45 10.5 1 0.5 472.50<br />

(0.0+10.5)/2=5.25 2 80 5.25 1 0.5 420.00<br />

(0.0+10.5)/2=5.25 2 40 5.25 1 0.5 210.00<br />

2 82 1.5 0.43 0.5 52.89<br />

2 82 1 0.58 0.5 47.56<br />

2 42 1.5 0.43 0.5 27.09<br />

2 42 1 0.58 0.5 24.36<br />

Total=<br />

1254.40 cum 168.00 210740.00<br />

3 3.7 Extra for laying earth as per specification for <strong>com</strong>paction in<br />

200 mm thick loose layers and dressing [MoRTH<br />

Specification Clause 305.3.5].


BY MECHANICAL MEANS, using Motor Grader, from<br />

earth in stock piles with all lead and lift but excluding<br />

rolling and watering.<br />

Same Qty. as above 1 1254.40<br />

1254.40 Cum 24.00 30106.00<br />

4 3.7.4 Extra for watering the earth to bring the earth upto required<br />

O.M.C excluding rolling<br />

Same Qty. as above 1 1254.40<br />

1254.40 cum 11.00 13799.00<br />

5 R-3/6 Compaction of original ground with maximum of six passes<br />

of 8-10 tonnes power roller including filling depression<br />

occurring during rolling [MoRTH Specification : Clause<br />

305.3.4]<br />

6 R-3/4 Box cutting/Trenching the Sub Grade to proper slope,<br />

camber and removing inequalities including removing<br />

deleterious stuff and depositing on the road side slopes<br />

(cutting of earth shall be paid separately in the respective<br />

item on the basis of classification of the excavation done by<br />

the Engineer (MoRTH specification clause 301 to 305)<br />

2 165.00 10 3300.00<br />

Total= 33.00 sqm 199.00 6567.00<br />

2 165.00 10 3300.00<br />

33.00 100<br />

sqm<br />

41.00 1353.00


R-4 Granular Sub -base with Well Graded Material (Table<br />

400.1)<br />

7 3.1 Providing laying spreading and <strong>com</strong>pacting specified<br />

graded sand, gravel as per Table 400-1,400-2 or any other<br />

course material as per design mix, as per CBR in sub base<br />

course including premixing the material at OMC in wet mix<br />

plant, carriage of mixed material spreading in uniform<br />

layers with motor grader F.E loader on a prepared base and<br />

<strong>com</strong>pacting with vibratory roller to achieve desired density<br />

(as per I.S.2720) including all material, labor, machinery,<br />

lighting guarding, barricading and maintenance of diversion<br />

<strong>com</strong>plete.[MoRTH specification : Clause 401]. By mechanical<br />

means with lead up to 1 km<br />

(i)<br />

By mechanical means with lead upto 1 km<br />

For Grading I Material<br />

1 45 7 0.2 1 63.00<br />

(8.5+1.50)/2=5.00 1 80 5 0.2 1 80.00<br />

(8.5+1.50)/2=5.00 1 40 5 0.2 1 40.00<br />

Total= 183.00 cum 490.00 89670.00


R-5 Wet Mix Macadam<br />

8 2 Providing, laying, spreading and <strong>com</strong>pacting stone<br />

aggregate for Wet Mix Macadam (as per table 400-10 and<br />

400-11) specification including premixing the material with<br />

water to OMC in wet mix plant as per approved design mix,<br />

carriage of mixed material by Tipper to site, laying in<br />

uniform layers with motor grader/Front end Loader/paver<br />

finisher, in sub base/ base course on a well prepared under<br />

base and <strong>com</strong>pacting with vibratory roller to achieve the<br />

desired density including lighting, guarding, barricading<br />

and maintenance of diversion etc. (MoRTH specification :<br />

Clause 406) by mechanical means with lead up to 1 Km.<br />

By Mechanical Means with 1 km lead<br />

1 45 7 0.25 1 78.75<br />

(8.5+1.50)/2=5.00 1 80 5 0.25 1 100.00<br />

(8.5+1.50)/2=5.00 1 40 5 0.25 1 50.00<br />

Total= 228.75 cum 765.00 174994.00<br />

9 2.1 Extra rate for carriage of mixed material additional lead<br />

from :-<br />

2.1.1 2nd km to 30th km 1 228.75 9 2058.75 Cum<br />

/Km<br />

B Hard shoulders<br />

10 R-4/2 Providing and laying granular sub-base material having<br />

P.I.not more than 6, including spreading in layers not<br />

exceeding 150 mm <strong>com</strong>pacted thickness and consolidation<br />

by 8-10 tonne power roller to required camber and grade<br />

including cost of water and hire charges of machinery,<br />

including T&P with all lead (Compacted thickness to be<br />

measured).as per MORTH specification table 400-1, 400-2 :<br />

2.1 For grading-I with CBR value not less than 30.<br />

to attain 100% proctor density.<br />

92.35 190126.00<br />

1 82 1.5 0.15 1 18.45<br />

1 42 1.5 0.15 1 9.45<br />

Total= 27.90 Cum 286.00 7980.00


Prime Coat<br />

11 R-6/4 Providing and applying primer coat over prepared surface<br />

or granular base with bitumen emulsion as per IS: 8887 &<br />

manufacturer’s specifications @ 6 kg /10 sqm with a self<br />

propelled or towed bitumen pressure sprayer equipped for<br />

spraying the material uniformly at specified rates and<br />

temperatures as per MoRTH specification CI 502 & 112 (<br />

Including cleaning of road surface )<br />

1 45 7 1 315.00<br />

(8.5+1.50)/2=5.00 1 80 5 1 400.00<br />

(8.5+1.50)/2=5.00 1 40 5 1 200.00<br />

Total= 915.00 sqm 21.00 19215.00<br />

12 4.1 Add extra to item No. 1 for 1 Kg / 10 Sqm emulsion 1 915.00 915.00<br />

Total= 915.00 sqm 2.00 1830.00<br />

Tack Coat<br />

13 r-6/5 Providing and applying tack coat on the prepared surface,<br />

with bitumen emulsion as per IS : 8887 & manufacturer’s<br />

specifications @ 2 kg /10sqm. With a self propelled or towed<br />

bitumen pressure sprayer equipped for spraying the<br />

material uniformly at specified rates and temperatures as<br />

per MoRTH specification Clause 503 & 112 ( Including<br />

cleaning of bituminous road surface )<br />

2 45 7 1 630.00<br />

(8.5+1.50)/2=5.00 2 80 5 1 800.00<br />

(8.5+1.50)/2=5.00 2 40 5 1 400.00<br />

Total=<br />

1830.00 sqm 8.00 14640.00<br />

14 5.1 Add extra for 0.5Kg / 10 Sqm emulsion 0.5 1830.00 sqm 2.00 1830.00


Dense Bituminous Macadam<br />

15 6.3 Providing and laying bituminous macadam on prepared<br />

surface with specified graded crushed aggregate as per table<br />

500 - 4, grading -1for base / binder course including loading<br />

of aggregates with F.E loader and heating and mixing of<br />

stone aggregate and bitumen ( including cost of antstripping<br />

<strong>com</strong>pound wherever required) in hot mix plant transporting<br />

the mixed material in tipper to paver and laying mixed<br />

material with sansor paver finisher to the required level and<br />

grade rolling by power roller & vibratory <strong>com</strong>pactor to<br />

achieve the desired density (approved by the department<br />

)excluding cost of primer /tack coat [MoRTH Specification :<br />

Clause 504,112] 50-100 mm <strong>com</strong>pacted thickness with 3.30%<br />

bitumen 60/70 grade with lead of mix 1 Km.<br />

1 45 7 0.05 1 15.75<br />

(8.5+1.50)/2=5.00 1 80 5 0.05 1 20.00<br />

(8.5+1.50)/2=5.00 1 40 5 0.05 1 10.00<br />

Total=<br />

45.75 cum 3649.00 166942.0<br />

16 9.2.1 Extra rate for carriage of mixed material additional lead<br />

average 30 km. -Same as Above<br />

17 6.8 Providing , laying and consolidation Semi Dense Bituminous<br />

Concrete, as per Design Mix, on prepared surface with<br />

specified graded crushed aggregates(as per table 500-15) for<br />

wearing coarse including loading aggregates with F.E<br />

loader, heating aggregate and binder in Hot Mix Plant 100-<br />

120 TPH (including cost of antistripping <strong>com</strong>pound<br />

wherever required ) and transporting the mixed material<br />

with tipper and laying with paver finisher with Sensor to the<br />

required level rolling with Vibratory Compactor or 150 to<br />

250 KN pneumatic tyred roller with TP=0.7 Mpa and power<br />

roller to achieve the desired density (as per approved job<br />

mix), but excluding primer/tack coat [MORTH Specification<br />

Clause 508,112]<br />

12.1 Bitumen @ 5 % of mix With lead of mix material 1 KM<br />

12.1.3 60/70 Grade<br />

45.750 cum 92.35 4226.00


1 45 7 0.04 1 12.60<br />

(8.5+1.50)/2=5.00 1 80 5 0.04 1 16.00<br />

(8.5+1.50)/2=5.00 1 40 5 0.04 1 8.00<br />

Total= 36.60 cum 6745.00 246867.00<br />

18 12.3 Extra rate for carriage of mixed material additional lead<br />

average 30 km. -Same as Above<br />

36.60 cum 92.35 3381.00<br />

R-11/1 Earth work in excavation for foundation of structure<br />

1.2<br />

<strong>com</strong>plete with all lift, dewatering shoring and shuttering etc<br />

.including refilling of trenches in 25.mm layers, ramming,<br />

watering and disposal of surplus soil within a lead of 1000<br />

meters, as per drawing and technical specification.[MoRTH<br />

Specification : Clause : 304]<br />

In hard Soil [MoRTH Specification : Clause : 301]<br />

1.2.1 Depth up to 3m<br />

Raise Kerb 2 45 0.3 0.15 4.05<br />

4 10 0.3 0.15 1.80<br />

2 2.5 0.3 0.15 0.23<br />

6.08 Cum 85.00 516.38<br />

19 R-<br />

10/1.3<br />

Providing and laying mechanically mixed and vibrated<br />

Cement Concrete in foundation up to a depth of 1.5 meters<br />

below ground level and 1.50 meters above Ground/Bed<br />

level.[MoRTH Specification : Clause 1000/1700]<br />

Cement concrete 1:3:6 mix crushed stone aggregates 20mm<br />

nominal size.<br />

Raise Kerb 2 45 0.3 0.1 2.70<br />

4 10 0.3 0.1 1.20<br />

2 2.5 0.3 0.1 0.15<br />

1 15 1.1 0.15 2.48<br />

(1.1+0.0)/2=0.55 1 20 0.55 0.15 1.65<br />

(1.1+0.0)/2=0.55 1 10 0.55 0.15 0.83<br />

2 9.8 2.1 0.15 6.17<br />

15.17 Cum 2217.00 33640.76


20 R-7/3.5 S & F cement concrete pre cast Kerb or Dand up to 60 cm<br />

length over 20 mm thick base of cement mortar1:4 including<br />

jointing earth work, pointing & jointing with cement mortar<br />

1:4 of size<br />

25 X 25 (22.5+25)/2X30 and (20+25)/2X30 cm<br />

Using Concrete Mixer<br />

21 R-<br />

7/49.3<br />

Providing and fixing of Precast concrete interlocking blocks<br />

of 100 mm thick manufactured from fully <strong>com</strong>puterized<br />

automatic stationery hydraulic vibro pressed machine & full<br />

<strong>com</strong>puterized automatic batching plant of class A-2 as per<br />

BS : 6717-2001. The C.C. interlocking paving blocks be laid<br />

on average 25 mm thick bed of coarse sand and the joint is to<br />

be filled with fine sand. Laying procedure on <strong>com</strong>pacted sub<br />

base as defined. Complete job is to be executed as per the<br />

instructions of Engineer-in-charge. The rates to be inclusive<br />

of all lead, lift, lifts & taxes general specifications of blocks.<br />

2 45 90.00<br />

4 10 40.00<br />

2 2.5 5.00<br />

Total= 135.00 Mtr 285.00 38475.00<br />

1. Shape : As specified by Engineer-in-charge.<br />

2. Tensile splitting strength and breaking load as per BS :<br />

6717-2001<br />

3. Colour : Grey cement natural colour<br />

4. Variation in Dimension : Less than 1.6mm.<br />

5. Variation in thickness : Less than 3.2mm<br />

1 15 1.1 16.50<br />

(1.1+0.0)/2=0.55 1 20 0.55 11.00<br />

(1.1+0.0)/2=0.55 1 10 0.55 5.50<br />

2 9.8 2.1 41.16<br />

Total= 74.16 Sqm 587.00 43531.92


22 R-7B/6 Providing and laying of hot applied thermoplastic<br />

<strong>com</strong>pound inclusive type I reflectrosing glass beads as per<br />

table 800-3, 800-4 applied in uniform thickness of at least 2.5<br />

mm and spread uniformly with reflectorising glass beads<br />

type II in addition @ 250 gms per Sqm with a road marking<br />

machine as per IRC: 35 <strong>com</strong>plete with traffic diversion<br />

arrangement as per MORTH specification clause 803.4.<br />

Centre Line 2 80.00 0.10 16.00<br />

Centre Line 2 40.00 0.10 8.00<br />

Edge Line 4 7.00 0.15 4.20<br />

Zebra 28 2.00 0.50 28.00<br />

Total 56.20 Sqm 543.00 30516.60<br />

23 R-7B/1.4Parapets, Kerbs, railings, guide stones, guard stones, tree<br />

guards & posts etc.<br />

2 45 0.45 40.50<br />

4 10 0.45 18.00<br />

2 2.5 0.45 2.25<br />

Total= 60.75 Sqm 36.00 2187.00<br />

Total = 1341349.65


Improvement of Jodhpur - Osian - Phalodi Road km 2/000 to 121/500 (SH-61) under<br />

BOT Annuity Scheme (Jodhpur - Osian - Phalodi)<br />

PART -'M' : Pick Up Bus Stop<br />

Abstract of Cost<br />

S.No. Description Qty. Unit Rate Amount<br />

1 Lordia 2 EACH 1341349.65 2682699.31<br />

2 Lohawat 2 EACH 1341349.65 2682699.31<br />

3 Balaji 2 EACH 1341349.65 2682699.31<br />

4 Bhikamkor 2 EACH 1341349.65 2682699.31<br />

5 Osian 4 EACH 1341349.65 5365398.61<br />

6 Nagaur Tiraha 2 EACH 1341349.65 2682699.31<br />

7 Mathania 2 EACH 1341349.65 2682699.31<br />

8 Manaklao 2 EACH 1341349.65 2682699.31<br />

18 Total 24144293.75


Improvement of Jodhpur - Osian - Phalodi Road km 2/000 to 121/500 (SH-61) under BOT<br />

Annuity Scheme (Jodhpur - Osian - Phalodi)<br />

PART -'M' : Existing Facilty / Utilities along the Road<br />

S.No. Chainage S.No. Chainage S.No. Chainage S.No. Chainage<br />

Petrol Pump<br />

School Temples<br />

Police Station / Others<br />

1 9/600 1 10/300 1 12/400 1 59/000<br />

2 16/000 2 60/300 2 28/450 2 74/000<br />

3 29/050 3 75/800 3 52/450<br />

4 70/700 4 76/700 4 57/800<br />

5 73/200 5 83/600 5 64/700 4<br />

6 77/400 6 84/900 6 74/300<br />

7 77/800 7 86/800 7 75/400<br />

8 87/975 8 90/450 8 76/600<br />

9 102/950 9 97/900 9 79/600<br />

10 103/400 10 106/900 10 81/300<br />

11 104/800 11 108/500 11 84/950<br />

12 108/150 12 114/100 12 85/025<br />

13 109/450 13 120/000 13 93/300<br />

14 118/900 14 96/900<br />

15 103/000<br />

16 111/200<br />

17 113/150<br />

18 113/650<br />

19 116/700<br />

20 119/800<br />

120/400 (Police<br />

Line)<br />

30/000 (Power<br />

House)<br />

Total 14.00 Total 13.00 Total 20.00 Total 4.00<br />

3