GDF SUEZ E&P Deutschland GmbH<br />
Waldstraße 39 – D-49808 Lingen<br />
(Ems)<br />
Telefon +49 (0) 591 / 612 – 0<br />
www.gdfsuezep.de<br />
Cofely Noord bv<br />
Exportweg 1 - 9301 ZV Roden<br />
The Netherlands<br />
Telefon +31 (0)50 502 35 82<br />
www.cofely.nl<br />
MoM# Item# Subject Action Due date<br />
MOM-5<br />
4-3-13<br />
MOM-5<br />
4-3-13<br />
MOM-5<br />
4-3-13<br />
MOM-5<br />
4-3-13<br />
MOM-5<br />
4-3-13<br />
MOM-5<br />
4-3-13<br />
MOM-5<br />
4-3-13<br />
MOM-5<br />
4-3-13<br />
MOM-5<br />
4-3-13<br />
MOM-5<br />
4-3-13<br />
MOM-5<br />
4-3-13<br />
MOM-5<br />
4-3-13<br />
MOM-5<br />
4-3-13<br />
MOM-5<br />
4-3-13<br />
MOM-5<br />
4-3-13<br />
MOM-5<br />
4-3-13<br />
should after approval be included during the detail engineering phase. ENG.<br />
4-18 8.8 Spoolpieces interconnecting pipelines. The connections of the<br />
pipelines should be flanged with compensators. The compensators will<br />
take care of the possible height differences which could occur during<br />
the site erection. During the detail engineering one and another will be<br />
embedded.<br />
4-19 8.8 HG Adsorber: Cofely confirms that the HG filter is equipped with a<br />
with active coal adsorption.<br />
8.9 Sand Cather: Cofely confirms that for filtering sand out of the oil a<br />
double sand catcher will be installed.<br />
4-20 8.10 Evacuation pumping system:<br />
4-21 GDF request to install on the suction side of the pumps a so-called run<br />
drain dry safety. Furthermore a so-called presence button when the<br />
truck is loading is required. The operator should every minute press<br />
the button for not interrupting the loading process.<br />
4-22 Truck loading. Only on truck can be loaded in the same time.<br />
Detail<br />
ENG.<br />
4-23 Connection. The connection on the loading truck is 3” or 4”. ABl will<br />
provide Cofely with the details of this connection.<br />
ABl Week 11<br />
4-24 The loading capacity of one truck is 30m 3 . The loading rate of 90 m3/h Detail<br />
gives a flow velocities of 5 m/sec. This flow velocity is to high and<br />
should be kept, if possible below, 2,5m/sec. For double walled loading<br />
hoses, DN80 inner hose, the flow velocity shall not exceed 4 m/s. Flow<br />
rate: The design flow rate must not exceed 4m/s.<br />
ENG.<br />
4-25 The loading truck has also pump facilities. We discussed to implement<br />
a by-pass connection for having the ability to load the truck without<br />
the use of the unloading skid. During the detail engineering one and Detail<br />
another will be embedded.<br />
ENG.<br />
4-26 GDF request Cofely to give more information of the pumps which are<br />
selected during the tender phase.<br />
MPa 3-11-13<br />
4-27 Loading arm. Loading arms are chosen as connection between the Detail<br />
pumps and loading truck. We have to clarify with TÜV if we need an<br />
impermeable surface for the loading facility. Otherwise it is perhaps<br />
better and cheaper to go for double walled hoses with leak detection.<br />
ENG.<br />
4-28 The unloading skid the should be provided with a drip pan and leak Detail<br />
detection. This change should after approval be included during the<br />
detail engineering phase.<br />
ENG.<br />
4-29 8.11 Oil circulation: GDF wants to have more information how the<br />
required oil circulation is achieved.<br />
MPa 3-11-13<br />
4-30 8.12 Control container: For generation of electricity two diesel<br />
Detail<br />
generator of 20kVA are installed. In the main distribution board an<br />
additional field must be implement in the case of grid voltage on a<br />
certain location is available.<br />
ENG.<br />
4-31 GDF request for more information regarding the air compressor. MPa 3-11-13<br />
4-32 GDF request for more information regarding the fuel heated boiler. MPa 3-11-13<br />
4-32 Connections for future emulsion breaking or chemical injections<br />
facilities should be available. This will be provided in the flow line just<br />
before the choke valve and on the wellhead both outside scope of <strong>EPU</strong><br />
project.<br />
Detail<br />
ENG.<br />
Bereich / Abteilung / Anlage Status Projekt-Nr. Dokumentennummer Blatt Rev.<br />
TTI - Ingenieurleistungen Entwurf 0975/11.07-0060 TT-0975-0400-005 4 von 5 A