Fibreglass Sand Filter - Bianco Pumpz
Fibreglass Sand Filter - Bianco Pumpz
Fibreglass Sand Filter - Bianco Pumpz
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
A PVC valve socket can be screwed onto this fitting using Teflon thread tape and the other end of<br />
the socket glued to PVC pressure pipe.<br />
O rings and sealing surfaces must be clean.<br />
Connect pipe from pump discharge to multi-port valve port labelled “PUMP”.<br />
Connect pipe from pool return to multi-port valve port marked “RETURN”.<br />
Connect pipe from waste to multi-port valve port marked “WASTE”.<br />
4. Commissioning.<br />
Hazardous pressures. Ensure that all clamps, fittings and connections are secure before<br />
starting pump.<br />
Never change multi-port valve settings or adjust clamps while the pump is operating or<br />
equipment damage and personal injury may result.<br />
Relieve all pressure from the system before undertaking any work on filter or pump.<br />
Open valves and make sure pump is filled with water. Make sure pool water level is at least<br />
50mm above bottom of skimmer opening.<br />
Set multi-port valve to ‘BACKWASH’ position.<br />
Start the pump with water going through filter to waste.<br />
To prevent pump from running dry, be sure that the water level is above the bottom of skimmer<br />
inlet. Add water to the pool if necessary to keep the skimmer box flooded while back-washing and<br />
rinsing.<br />
Continue on backwash until the water is clear, about 5 minutes.<br />
Stop the pump and set multi-port valve to ‘RINSE’ position.<br />
Run the pump for 1 minute.<br />
If using Zelbrite repeat the above operation three times.<br />
Stop the pump and set multi-port valve to ‘FILTER’ position.<br />
Run the pump with the multi-port valve set to “FILTER” position and record the filter pressure<br />
gauge reading as a reference.<br />
For new pools, backwash once a day until pool water is clear.<br />
Backwash when pressure gauge shows 5 to 7 psi (35 to 50kPa) higher than the pressure<br />
recorded during commissioning.<br />
BIA FGSF08.2 4