25.03.2013 Views

Lean Valemon hits the fast track - Heerema Fabrication Group ...

Lean Valemon hits the fast track - Heerema Fabrication Group ...

Lean Valemon hits the fast track - Heerema Fabrication Group ...

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

FIEld dEvElOpmENt<br />

2<br />

One of four roll-ups<br />

of large frames for<br />

<strong>the</strong> <strong>Valemon</strong> jacket<br />

at HFG’s Vlissingen<br />

yard.<br />

<strong>Lean</strong> <strong>Valemon</strong><br />

<strong>hits</strong> <strong>the</strong> <strong>fast</strong> <strong>track</strong><br />

An impressive example of lean design and <strong>fast</strong>-<strong>track</strong><br />

construction of a major offshore structure is now standing in<br />

133m of water in <strong>the</strong> Norwegian North Sea. Adrian Cottrill<br />

looks at <strong>the</strong> technology-stretching jacket at <strong>the</strong> heart of Statoil’s<br />

NKr20.4 billion valemon field development and <strong>the</strong> new<br />

lift-installation record it has established.<br />

Every unnecessary kilogramme<br />

of steel in <strong>the</strong> jacket for Statoil’s<br />

<strong>Valemon</strong> platform has been<br />

pared away by design and fabrication<br />

contractor <strong>Heerema</strong> <strong>Fabrication</strong> <strong>Group</strong><br />

(HFG). The vital driver for this crusade<br />

has been <strong>the</strong> need to keep <strong>the</strong> structure’s<br />

final weight within <strong>the</strong> capabilities of <strong>the</strong><br />

world’s largest offshore crane vessel and<br />

so enable a record-breaking lift into place<br />

at location.<br />

The 8800 tonne jacket (plus ano<strong>the</strong>r<br />

800te of temporary rigging) placed on<br />

<strong>the</strong> seabed at <strong>Valemon</strong> has also been<br />

built in admirably quick time at HFG’s<br />

yard at Vlissingen in <strong>the</strong> south of <strong>the</strong><br />

Ne<strong>the</strong>rlands. ‘It took us just 50 weeks of<br />

fabrication, from cutting our first steel<br />

on 6 June last year to ready for sailaway<br />

on 26 May,’ says Aren Bezuyen, project<br />

manager at <strong>the</strong> yard.<br />

Pre-production drilling is due to start<br />

at <strong>the</strong> platform this month. But <strong>the</strong> main<br />

topside – due to weigh about 10,000te<br />

and being built by Samsung – will not<br />

be lifted on until 2014. By that time four<br />

production wells will have been<br />

pre-drilled through <strong>the</strong> jacket from<br />

a jackup tender rig that will stand<br />

alongside for <strong>the</strong> next two years.<br />

Without <strong>the</strong> intense design effort<br />

put in by in-house design company<br />

HFG Engineering at its Zwijndrecht<br />

headquarters, a more normal jacket to<br />

meet <strong>Valemon</strong> requirements would likely<br />

have consumed a fur<strong>the</strong>r 1000te of steel<br />

reckons Cees Spaans, <strong>the</strong> company’s VP<br />

for technology.<br />

The <strong>Valemon</strong> jacket is <strong>the</strong> heaviest ever<br />

to be lift-installed reckons HFG, and by<br />

far <strong>the</strong> heaviest of <strong>the</strong> half dozen large<br />

jackets so far built by <strong>the</strong> company at<br />

Vlissingen. And it is <strong>the</strong> first large jacket<br />

built by <strong>the</strong> company for Statoil.<br />

The vessel that lifted it into place on<br />

18 June was Thialf, operated by sister<br />

company <strong>Heerema</strong> Marine Contractors.<br />

This semisubmersible shares <strong>the</strong> title of<br />

world’s most powerful crane barge with<br />

rival S7000, operated by Saipem. Each<br />

of <strong>the</strong>se two units sports a pair of main<br />

cranes that provide a maximum tandem<br />

lift capacity of a little over 14,000te.<br />

In <strong>the</strong> particular configuration needed<br />

for Thialf to lift-install <strong>the</strong> <strong>Valemon</strong><br />

jacket, <strong>the</strong> HFG team needed to keep<br />

several thousand tonnes below that<br />

for <strong>the</strong> combined weight of jacket and<br />

temporary rigging hanging off <strong>the</strong> vessel’s<br />

hooks during <strong>the</strong> big lift.<br />

Not without considerable effort, and<br />

certainly with one or two periods of some<br />

pain, <strong>the</strong>y have managed to achieve just<br />

that. The company won <strong>the</strong> 20-month EPC<br />

contract – rumoured to be worth about<br />

$80 million – from Statoil in October<br />

2010. This followed <strong>the</strong> detail design<br />

contract won in <strong>the</strong> preceding month.<br />

Earlier competitive FEED studies by<br />

O F F S H O R E E N G I N E E R | a u g u s t 2 0 1 2 w w w. o f f s h o r e - e n g i n e e r. c o m


HFG and Aker had already established<br />

lift-installation as <strong>the</strong> road ahead for <strong>the</strong><br />

project.<br />

If a jacket is too heavy for this<br />

approach <strong>the</strong> main alternative is to skid<br />

it lengthways into <strong>the</strong> water off a launchbarge.<br />

However, as Cees Spaans points<br />

out, ‘if you can lift-install you should do<br />

so’.<br />

‘Of course, launching is not only an<br />

issue of weight,’ he continues. ‘You need<br />

to have extra strength in <strong>the</strong> jacket to<br />

undergo <strong>the</strong> launch, skid rails on your<br />

barge, along with ballast systems and<br />

buoyancy tanks, and favourable wea<strong>the</strong>r,<br />

all adding to risk.’<br />

Client Statoil has a long pedigree in<br />

lift-installation of big jackets. Indeed<br />

<strong>the</strong> company’s man on <strong>the</strong> job here,<br />

Kjell Arvid Tuen, with <strong>the</strong> title ‘Statoil<br />

representative, <strong>Valemon</strong> jacket EPC’ is<br />

very familiar with <strong>the</strong> concept. He has<br />

been involved with half a dozen such<br />

projects in his 20 years with <strong>the</strong> oil<br />

company.<br />

Ways to lose weight<br />

For <strong>Valemon</strong> <strong>the</strong> sights were always<br />

set on lift-installation, and <strong>the</strong>refore on<br />

minimum structural weight. Spaans lists<br />

some of <strong>the</strong> measures adopted to achieve<br />

that at an offshore location where <strong>the</strong><br />

100-year design wave has a peak height of<br />

28m. (Under this extreme condition it is<br />

calculated <strong>the</strong> platform top will displace<br />

about 750mm laterally.)<br />

High strength steel is one of <strong>the</strong><br />

measures to keep weight down, he says.<br />

Though not particularly unusual, grades<br />

such as 420 and 460 made a helpful<br />

contribution.<br />

‘The weight of anodes required for<br />

corrosion protection has been reduced<br />

by painting <strong>the</strong> whole of <strong>the</strong> jacket,’ he<br />

continues. ‘And <strong>the</strong> diameter of tubular<br />

members is kept as small as possible, only<br />

ballooning out at end connection nodes<br />

where extra strength is needed to meet<br />

fatigue demands.<br />

‘In addition we have braces that are<br />

flooded so <strong>the</strong>y do not have to resist<br />

hydrostatic collapse.’ This is not normal<br />

practice because buoyant braces lend<br />

<strong>the</strong>mselves to flood detection systems<br />

to indicate fatigue damage, but is an<br />

acceptable trade-off here. Also, ‘instead of<br />

designing in additional strength to meet<br />

demands during <strong>the</strong> temporary transport<br />

phase at sea, we have dealt with that in<br />

o<strong>the</strong>r ways’, says Spaans. For example,<br />

a system of bracing wires to <strong>the</strong> inner<br />

members dampened any tendency for<br />

<strong>the</strong>m to vibrate in high winds.<br />

Once HMC won <strong>the</strong> installation<br />

contract, that phase could be designed<br />

specifically around Thialf. One of <strong>the</strong><br />

differences from S7000 for example<br />

is that Thialf’s main hook is allowed<br />

underwater, avoiding <strong>the</strong> need to find<br />

w w w. o f f s h o r e - e n g i n e e r. c o m O F F S H O R E E N G I N E E R | a u g u s t 2 0 1 2<br />

courtesy heerema<br />

3<br />

FIEld dEvElOpmENt


FIEld dEvElOpmENt<br />

4<br />

adrian cottrill<br />

adrian cottrill<br />

extra buoyancy to avoid that limitation.<br />

Above all, says Spaans, ‘we worked<br />

steadily towards our weight target by<br />

doing far more than <strong>the</strong> normal one or<br />

two cycles of engineering to get weight<br />

down. We analysed again and again and<br />

again.’<br />

Both Spaans and Bezuyen speak of<br />

<strong>the</strong> benefits of having so many aspects<br />

of <strong>the</strong> whole project within <strong>the</strong> <strong>Heerema</strong><br />

group and <strong>the</strong> quality of <strong>the</strong> resulting<br />

interaction between <strong>the</strong> design and<br />

construction sides. They also underline<br />

<strong>the</strong> very effective communication with<br />

client Statoil and certifying authority<br />

DNV right from <strong>the</strong> beginning.<br />

Statoil’s Kjell Arvid Tuen agrees. His<br />

own involvement with <strong>the</strong> project began<br />

The completed <strong>Valemon</strong> jacket, loaded on<br />

transport barge at Vlissingen yard quayside<br />

sailed away from <strong>the</strong> Ne<strong>the</strong>rlands early<br />

on <strong>the</strong> morning of 26 May.<br />

‘We worked steadily towards our<br />

weight target . . . we analysed<br />

again and again and again’<br />

Cees Spaans, HFG<br />

in <strong>the</strong> very earliest days when <strong>the</strong> design<br />

basis was being evolved. Then, when<br />

<strong>the</strong> contract was awarded, Tuen went on<br />

to spend two years in <strong>the</strong> Ne<strong>the</strong>rlands,<br />

starting in HFG’s design offices and<br />

ending with close to four weeks on board<br />

Thialf for <strong>the</strong> offshore installation.<br />

Clearly he enjoyed <strong>the</strong> experience.<br />

‘The Dutch and Norwegians have <strong>the</strong><br />

same cultural attitudes,’ he says, ‘and<br />

communication has been very effective.<br />

We started working toge<strong>the</strong>r from day<br />

one of <strong>the</strong> contract, and that’s one of <strong>the</strong><br />

reasons for <strong>the</strong> success I think.’<br />

Two challenging issues<br />

Certainly <strong>the</strong> emphasis on lean design,<br />

with maximum input as early as possible,<br />

courtesy heerema<br />

The dominant design factors for HFG at<br />

various points of <strong>the</strong> jacket are shown<br />

below.<br />

In place – Strength<br />

In place – Fatigue<br />

Accidental – Boat impact<br />

temporary – lift and transport<br />

O F F S H O R E E N G I N E E R | a u g u s t 2 0 1 2 w w w. o f f s h o r e - e n g i n e e r. c o m<br />

courtesy heerema


adrian cottrill<br />

paid useful dividends, says Cees Spaans.<br />

However, it did not prevent <strong>the</strong> design<br />

process going through a couple of painful<br />

periods.<br />

The first of <strong>the</strong>se came during design<br />

of <strong>the</strong> two mighty trunnion nodes in<br />

<strong>the</strong> jacket’s lower legs. These huge steel<br />

castings, weighing 110te each, formed <strong>the</strong><br />

all-important pivot points when <strong>the</strong> jacket<br />

was dangling from Thialf’s hooks during<br />

installation offshore and was rotated from<br />

horizontal to vertical.<br />

Built by specialist company Vulcan<br />

Sheffield Forgemasters, <strong>the</strong>y are <strong>the</strong><br />

largest cast nodes ever produced. ‘The<br />

challenge of designing <strong>the</strong>se castings was<br />

definitely a little bit underestimated,’<br />

concedes Spaans. ‘In fact in <strong>the</strong> end it<br />

took us nearly three months instead of<br />

<strong>the</strong> two or three weeks expected.’<br />

‘The rotating hub is a very tight fit –<br />

with just 3mm of clearance,’ he explains,<br />

‘and <strong>the</strong> challenge was to prevent it<br />

deforming too much under load.’ There<br />

are also ano<strong>the</strong>r two smaller cast nodes at<br />

<strong>the</strong> lift points in <strong>the</strong> upper legs. Happily<br />

<strong>the</strong>se proved less difficult to design.<br />

Not long after this <strong>the</strong> designers<br />

encountered ano<strong>the</strong>r unpleasant surprise.<br />

In autumn last year <strong>the</strong>y discovered that<br />

in <strong>the</strong>ir bid to get <strong>the</strong> thinnest possible<br />

steel wall in <strong>the</strong> main legs, those legs had<br />

been left too weak to prevent deformation<br />

during <strong>the</strong> sea journey at two of <strong>the</strong> main<br />

support points on <strong>the</strong> grillage aboard <strong>the</strong><br />

transport barge.<br />

The only solution at this stage was<br />

to add local streng<strong>the</strong>ning. Just over<br />

40 ring stiffeners were welded inside<br />

<strong>the</strong> 3.5m diameter lower legs at <strong>the</strong> two<br />

affected points. This brought <strong>the</strong> triple<br />

inconveniences of about 60te of extra<br />

steel weight, a large amount of planning,<br />

and ‘a tremendous lot of hours needed<br />

to weld <strong>the</strong>m in’. However, ‘that’s all<br />

part of <strong>the</strong> EPC risk’, observes Spaans<br />

philosophically.<br />

A fur<strong>the</strong>r area of challenge for both<br />

designers and fabricators was <strong>the</strong> grillage<br />

and sea-<strong>fast</strong>ening for <strong>the</strong> journey to <strong>the</strong><br />

offshore location. The demanding North<br />

Sea environment to be designed for (a<br />

maximum wave height of nearly 11m<br />

during sea transport) meant high loads<br />

and large reactions between barge and<br />

jacket. It was difficult to find an example<br />

‘It took us just fifty weeks<br />

of fabrication, from<br />

cutting our first steel to<br />

being ready for sailaway.’<br />

Aren Bezuyen, HFG<br />

from a different project and ‘that was a<br />

challenge we solved toge<strong>the</strong>r with HMC’,<br />

says Spaans.<br />

‘What did go very well was <strong>the</strong> whole<br />

certification process,’ he notes. ‘I thought<br />

<strong>the</strong> main challenge would be to meet<br />

fatigue criteria with DNV, not least<br />

because when different organisations do<br />

<strong>the</strong> same analysis, <strong>the</strong>y are bound to use<br />

different kinds of software.’<br />

However, <strong>the</strong> verification process with<br />

DNV went amazingly smoothly, he says.<br />

‘This was a lot to do with <strong>the</strong>m being<br />

involved early.’<br />

Boat impact and foundations<br />

Designing against boat impact is clearly<br />

ano<strong>the</strong>r area where HFG is proud of its<br />

efforts. ‘This generated a very interesting<br />

technical discussion,’ notes Spaans.<br />

The criteria for <strong>Valemon</strong> are unusually<br />

high. Because <strong>the</strong> platform sits in a<br />

shipping lane it could potentially be hit<br />

by vessels as big as a large supply boat<br />

weighing up to 7500te and moving at up<br />

to 5 knots. In addition, a vessel like that<br />

can have more complicated aspects to its<br />

shape, such as a bulb at <strong>the</strong> bow, which<br />

influence <strong>the</strong> way it could penetrate a<br />

platform.<br />

In more standard locations, <strong>the</strong><br />

One of <strong>the</strong> two<br />

huge trunnion<br />

nodes cast<br />

by Vulcan<br />

Sheffield<br />

Forgemasters.<br />

requirements are based on a 5000te<br />

vessel moving at up to 4 knots. All this<br />

translates into <strong>Valemon</strong> having to cater<br />

for 35MJ of impact energy. This figure is<br />

close to three times what is more usually<br />

called for.<br />

‘In general, you want <strong>the</strong> jacket to be as<br />

open as possible to minimise wave load,’<br />

Spaans points out. ‘But in <strong>the</strong> area where<br />

a boat could impact (between about 12m<br />

above and below water level) members<br />

need to be more closely packed to prevent<br />

a boat penetrating too far into <strong>the</strong> jacket.<br />

‘Industry guidelines are based simply<br />

on impact energy and point load,’ he says.<br />

‘They don’t look at <strong>the</strong> physical shape of<br />

<strong>the</strong> boat, nor where you can enter or what<br />

you can hit.’<br />

‘So we engaged in a more probabalistic<br />

approach to define <strong>the</strong> real challenge and<br />

find <strong>the</strong> right balance. We went through<br />

a question and answer process, asking<br />

ourselves just how far a boat could<br />

penetrate into <strong>the</strong> body of <strong>the</strong> jacket.’<br />

To do this, HFG engaged in ‘a very<br />

sophisticated study’ jointly with Dutch<br />

research organisation TNO which has<br />

done considerable work in this field. At<br />

<strong>the</strong> same time Statoil undertook a similar<br />

study through Trondheim’s University of<br />

Science & Technology. > overleaf<br />

All rigged up in <strong>the</strong> yard: huge slings in place round one of <strong>the</strong> pair of trunnion nodes<br />

that provide vital pivot points for rotation. The sling is made of steel rope of nearly<br />

300mm diameter and over 6500te breaking strength.<br />

w w w. o f f s h o r e - e n g i n e e r. c o m O F F S H O R E E N G I N E E R | a u g u s t 2 0 1 2<br />

adrian cottrill<br />

5<br />

FIEld dEvElOpmENt


FIEld dEvElOpmENt<br />

8<br />

courtesy heerema<br />

<strong>the</strong> valemon field<br />

<strong>the</strong> valemon gas and condensate<br />

accumulation, a 1985 discovery 160km<br />

off <strong>the</strong> coast from Bergen, has estimated<br />

recoverable reserves equivalent to<br />

210 million barrels of oil. development<br />

is currently priced at NKr20.4 billion by<br />

operator Statoil and its partners petoro,<br />

Centrica and Enterprise.<br />

<strong>the</strong> valemon platform is designed to<br />

In <strong>the</strong> platform’s foundations one<br />

novelty is <strong>the</strong> inclusion of cages of 16mm<br />

steel reinforcing bar within <strong>the</strong> annulus<br />

of grout that connects each pile to its<br />

sleeve once it has been driven. This is<br />

part of <strong>the</strong> latest DNV codes on grouted<br />

connections.<br />

The jacket stands on a group of four<br />

84in diameter piles at <strong>the</strong> base of each of<br />

its four main legs. These piles are driven<br />

59m into <strong>the</strong> medium seabed soil at this<br />

site.<br />

produce about 85,000boe/d. <strong>the</strong> bulk of<br />

reserves – about 80% – take <strong>the</strong> form<br />

of natural gas, with <strong>the</strong> remainder as<br />

condensate and natural gas liquids.<br />

two years of pre-drilling is due to start this<br />

month to provide four of <strong>the</strong> 11 production<br />

wells currently planned, using a jackup tender<br />

rig standing alongside <strong>the</strong> jacket and <strong>the</strong> small<br />

wellhead module placed on it. <strong>the</strong>re will also<br />

be two injection wells – one for drill cuttings<br />

and <strong>the</strong> o<strong>the</strong>r for produced water.<br />

Design codes now require steel bar reinforcement in <strong>the</strong> grout<br />

annulus in <strong>the</strong> pile to sleeve connection.<br />

Wellhead module<br />

To cater for <strong>the</strong> pre-drilling operations due to<br />

run for two years from July until <strong>the</strong> platform’s<br />

main topside arrives, <strong>the</strong> <strong>Valemon</strong> jacket carries<br />

a wellhead module which will later be partly<br />

integrated into <strong>the</strong> main topsides. This has<br />

also been designed and built by HFG in just six<br />

months, fabricating at a smaller yard near its main<br />

Vlissingen site.<br />

Athough relatively small, at 190te, 25m long<br />

and just 3m high, it was also not without its<br />

challenges. Rapid action had to be taken last<br />

October when Statoil called for <strong>the</strong> design to be<br />

completely changed: from two-deck to single<br />

deck. Also, to enable adjustments when <strong>the</strong> main<br />

topside arrives in two years, it is fixed by some<br />

2000 bolts because of <strong>the</strong> ban on hot work once<br />

drilling has started.<br />

In mid-2014 <strong>the</strong> topside being built<br />

by Samsung, and likely to weigh about<br />

10,000te, will be lifted on. <strong>the</strong> completed<br />

platform is due onstream by <strong>the</strong> end of<br />

that year. It will be able to treat gas and<br />

condensate from future discoveries in <strong>the</strong><br />

area as well as valemon itself.<br />

<strong>the</strong> installation is classed as ‘not<br />

normally manned’ once drilling is<br />

completed, although it will have 40 cabins<br />

of accommodation. It will be remotely<br />

The move to add rebar cages to <strong>the</strong><br />

grout follows a certain amount of<br />

trouble with foundations in <strong>the</strong> offshore<br />

wind sector, perhaps too economically<br />

designed. There are reports of grout<br />

‘crunching’ and tube damage. In effect <strong>the</strong><br />

addition of rebar cages turns <strong>the</strong> grout<br />

layer into straightforward reinforced<br />

concrete.<br />

In <strong>the</strong> yard<br />

Summarising <strong>the</strong> jacket construction<br />

work at Vlissingen, HFG project manager<br />

Aren Bezuyen describes <strong>the</strong> rapid pace<br />

of early procurement on this <strong>fast</strong>-<strong>track</strong><br />

project as ‘especially necessary with<br />

certain specialist suppliers like Vulcan<br />

Sheffield Forgemasters for <strong>the</strong> highlydemanding<br />

cast nodes’. He also outlines<br />

<strong>the</strong> weight uncertainties and puzzles<br />

confronted as fabrication proceeded. ‘We<br />

did as much work as possible at ground<br />

level, building <strong>the</strong> jacket in four main<br />

parts which could be rolled up,’ says<br />

Bezuyen. The heaviest lifts at height were<br />

two 400te leg base sections. Late delivery<br />

in certain areas meant that ‘we had to<br />

do more work at height than we’d hoped.<br />

For example we were not able to get all<br />

<strong>the</strong> risers and caissons in place before<br />

roll-up.’<br />

Ano<strong>the</strong>r delaying factor, he adds,<br />

was <strong>the</strong> information provided by HMC,<br />

controlled from <strong>the</strong> Kvitebjorn platform<br />

11km away, which will also supply power by<br />

cable. Kvitebjorn will also be <strong>the</strong> recipient<br />

of valemon’s condensate via a new pipeline<br />

between <strong>the</strong> two, with onward transport<br />

through <strong>the</strong> existing network to mongstad<br />

refinery.<br />

<strong>the</strong> main flow of rich gas from valemon<br />

will go through a new 27km pipe to connect<br />

with an existing line and <strong>the</strong>n be transported<br />

onward to Heimdal.<br />

One of <strong>the</strong> main support points on <strong>the</strong> transport barge. Ring<br />

stiffeners had to be added inside <strong>the</strong> jacket legs at two such points.<br />

<strong>the</strong>mselves wrestling with a jacket that<br />

was bringing Thialf to <strong>the</strong> limits of its<br />

capacity. But after less than a year of<br />

physical construction work, all was ready<br />

by mid-May for <strong>the</strong> completed jacket to<br />

start moving from <strong>the</strong> yard. In a two-part<br />

operation <strong>the</strong> combination of jacket,<br />

support grillage and temporary<br />

attachments (a total load of 10,790te) was<br />

first moved 35m sideways by load-out<br />

subcontractor Mammoet on a massive<br />

wheeled array of 400 axles. > overleaf<br />

In <strong>the</strong> drive to minimise steel weight, jacket<br />

braces only balloon out in diameter at <strong>the</strong>ir<br />

ends to meet fatigue requirements at nodes.<br />

O F F S H O R E E N G I N E E R | a u g u s t 2 0 1 2 w w w. o f f s h o r e - e n g i n e e r. c o m<br />

adrian cottrill adrian cottrill


FIEld dEvElOpmENt<br />

10<br />

courtesy woldcam as, anette westgård<br />

‘Effective<br />

communication a<br />

major reason for<br />

project success’<br />

Kyell Arvid Tuen,<br />

Statoil<br />

Then it was moved 160m forwards<br />

onto <strong>the</strong> barge which would take it to<br />

location. Total rolling time was about<br />

five hours. Next came ten days of fixing<br />

sea-<strong>fast</strong>enings, guy-lines to braces and<br />

suchlike, leading up to sailaway of barge<br />

and cargo early on 26 May.<br />

Altoge<strong>the</strong>r HFG’s <strong>Valemon</strong> jacket<br />

project has notched up half a million<br />

manhours. A fifth of that was divided<br />

equally between engineering and<br />

management. Ano<strong>the</strong>r fifth was by<br />

subcontractors.<br />

The remaining 300,000 manhours<br />

went to fabrication in <strong>the</strong> Vlissingen<br />

yard.<br />

Statoil’s Tuen sums it up. ‘The big goal<br />

right from <strong>the</strong> start was of course to make<br />

<strong>the</strong> jacket liftable,’ he says, ‘and in my<br />

mind HFG has done a very good job, both<br />

technically and commercially.’<br />

He has sympathy with HFG over <strong>the</strong><br />

difficult stages it had to overcome. ‘It’s<br />

always good to finish as much analysis<br />

as possible before you order steel. But it’s<br />

also important to work as <strong>fast</strong> as possible.<br />

I think HFG did as well as <strong>the</strong>y could.<br />

They had to finish by a certain date, so<br />

<strong>the</strong>y had to order <strong>the</strong> steel in <strong>the</strong> way <strong>the</strong>y<br />

did.’<br />

As to value for money, Tuen reckons<br />

‘<strong>Valemon</strong> is more or less <strong>the</strong> best we’ve<br />

had. This was helped by our timing in<br />

<strong>the</strong> market, but also by <strong>the</strong> fact that<br />

HFG wanted to show Statoil <strong>the</strong>y were a<br />

professional jacket EPC contractor.<br />

‘It’s <strong>the</strong> first <strong>the</strong>y have ever built for us,<br />

and now we have no doubt that <strong>the</strong>y can<br />

do it.’<br />

Statoil’s vice president for <strong>Valemon</strong>,<br />

Bjørn Laastad, notes: ‘We are very<br />

pleased with this delivery from <strong>Heerema</strong><br />

<strong>Fabrication</strong> <strong>Group</strong>, which is a new<br />

supplier to Statoil for steel jackets of this<br />

size.’<br />

As <strong>the</strong> bright yellow jacket sailed away<br />

in <strong>the</strong> pale dawn light on 26 May, both<br />

<strong>the</strong> designers and <strong>the</strong> builders in HFG<br />

could reflect on a good job done. They had<br />

derived all <strong>the</strong> in-house advantages <strong>the</strong>y<br />

could in integrating <strong>the</strong> engineering and<br />

fabrication processes, placed<br />

fruitful emphasis on constructability,<br />

and been greatly aided by effective<br />

communication with <strong>the</strong>ir client Statoil<br />

and partners. OE<br />

Lift-installation’s<br />

latest benchmark<br />

After two weeks of waiting on<br />

wea<strong>the</strong>r, Thialf could at last get to<br />

work on <strong>the</strong> <strong>Valemon</strong> jacket.<br />

O F F S H O R E E N G I N E E R | a u g u s t 2 0 1 2 w w w. o f f s h o r e - e n g i n e e r. c o m


w w w. o f f s h o r e - e n g i n e e r. c o m O F F S H O R E E N G I N E E R | a u g u s t 2 0 1 2<br />

courtesy woldcam as, anette westgård<br />

courtesy heerema<br />

All <strong>the</strong> careful planning and<br />

refinement of <strong>the</strong> <strong>Valemon</strong> jacket<br />

design finally paid off on 18 June<br />

when <strong>the</strong> structure’s record-breaking<br />

offshore lift-installation was completed.<br />

At 03.00 hours, <strong>the</strong> base of <strong>the</strong> 160m high<br />

steel frame finally touched <strong>the</strong> seabed, on<br />

target and perfectly upright.<br />

The sequence had started with vessel<br />

operator HMC first bringing <strong>the</strong> transport<br />

barge into position at <strong>the</strong> stern of Thialf.<br />

Then, with <strong>the</strong> twin cranes hooked to <strong>the</strong><br />

jacket’s pre-installed lifting slings, <strong>the</strong><br />

transport barge could be slowly ballasted<br />

lower in <strong>the</strong> water, sea <strong>fast</strong>enings cut and<br />

<strong>the</strong> jacket raised above its deck.<br />

Once <strong>the</strong> free-floating cargo barge had<br />

been towed away, <strong>the</strong> bottom end of <strong>the</strong><br />

jacket could be steadily lowered into <strong>the</strong><br />

water, with <strong>the</strong> structure just as steadily<br />

rotating from horizontal to vertical as it<br />

went.<br />

The procedure did however suffer a late<br />

interruption when a mechanical problem<br />

stopped one of <strong>the</strong> main cranes and<br />

caused <strong>the</strong> whole lift operation to halt.<br />

At that point <strong>the</strong> jacket had been fully<br />

rotated but still had ano<strong>the</strong>r 7m to go to<br />

reach <strong>the</strong> seabed 133m below water. So<br />

<strong>the</strong> last stage of set-down was achieved by<br />

a combination of booming down <strong>the</strong> crane<br />

and ballasting of Thialf.<br />

Thirteen days later, HMC had stabbed,<br />

driven and grouted all 16 foundation piles<br />

and finished with <strong>the</strong> small lifts of five<br />

caissons and <strong>the</strong> 190te wellhead module.<br />

On 1 July <strong>the</strong> vessel was able to sail away<br />

from a highly demanding job well done<br />

for client Statoil.<br />

Waiting on wea<strong>the</strong>r<br />

The immediate run-up to this, <strong>the</strong> world’s<br />

heaviest lift-installation, had been a stark<br />

contrast to all that activity. Before <strong>the</strong>y<br />

were at last able to swing into action,<br />

<strong>the</strong> team onboard Thialf had to sit out a<br />

frustrating 15 days of inactivity, waiting<br />

on wea<strong>the</strong>r and hoping for sea conditions<br />

to calm down enough for <strong>the</strong>m to start <strong>the</strong><br />

delicate jacket lift.<br />

When that window did open, says HMC<br />

project manager Carol Granneman, ‘<strong>the</strong><br />

wea<strong>the</strong>r was excellent. It was very quiet,<br />

with seas of less than half a metre and<br />

hardly any wind, and that helped us a lot.’<br />

The total load on <strong>the</strong> hooks of Thialf’s<br />

11<br />

FIEld dEvElOpmENt


FIEld dEvElOpmENt<br />

12<br />

twin cranes as <strong>the</strong> jacket rose off its<br />

transport barge was 9600te. This included<br />

some 800te of temporary equipment such<br />

as spreader bars and slings.<br />

Thialf has lifted heavier loads than this<br />

a number of times in <strong>the</strong> past. Largest of<br />

<strong>the</strong>se to date has been <strong>the</strong> 11,800te topside<br />

for <strong>the</strong> Shearwater platform in <strong>the</strong> UK<br />

North Sea, placed in 2000.<br />

But a large jacket is a ra<strong>the</strong>r different<br />

proposition. It may not be as susceptible<br />

to wind forces as a big topside, but it does<br />

call for <strong>the</strong> delicate and complicated task<br />

of rotating from horizontal to vertical<br />

once it has been raised from <strong>the</strong> transport<br />

barge.<br />

That lift-off is just as delicate, governed<br />

by <strong>the</strong> relative motion between crane<br />

vessel and <strong>the</strong> transport barge brought<br />

beneath its cranes. ‘Every lift has its own<br />

limits,’ says Granneman, ‘and this one<br />

had probably <strong>the</strong> most stringent limits we<br />

have seen.’<br />

<strong>Valemon</strong> called for sea conditions<br />

below 2m significant wave height. ‘In <strong>the</strong><br />

event we experienced no more than half<br />

that,’ he says. ‘That put us well within<br />

crane limits, still with spare capacity left.’<br />

The movement at crane tips was probably<br />

less than 100mm.<br />

Wea<strong>the</strong>r during <strong>the</strong> preceding 15 days<br />

of standby time was poor ra<strong>the</strong>r than<br />

dramatically bad as Thialf waited on<br />

location and <strong>the</strong> jacket stood off about<br />

5km. ‘The most exciting part of <strong>the</strong> day<br />

was <strong>the</strong> wea<strong>the</strong>r forecaster’s presentation<br />

on what he expected for <strong>the</strong> next week,’<br />

says Granneman.<br />

‘We had one instance where we thought<br />

<strong>the</strong> lift could be possible and got ourselves<br />

ready,’ he continues. ‘But actual<br />

Slowly rotating, <strong>the</strong> lower end<br />

of <strong>the</strong> jacket descends into <strong>the</strong><br />

water. Right: Landed on <strong>the</strong><br />

seabed, <strong>the</strong> jacket awaits <strong>the</strong><br />

first of <strong>the</strong> 16 foundation piles<br />

in foreground to be stabbed<br />

and driven. Below: Hooking<br />

up in a calm sea for a<br />

record-breaking lift.<br />

conditions turned out a little worse than<br />

expected and we had to postpone. You<br />

can’t do anything about <strong>the</strong> wea<strong>the</strong>r.’<br />

When a viable five-day window did<br />

come into view HMC could at<br />

last spring into action.<br />

Once <strong>the</strong> jacket had<br />

been landed on <strong>the</strong> seabed,<br />

foundation work went <strong>fast</strong>er<br />

than expected. About a day<br />

was trimmed from <strong>the</strong> nineday<br />

schedule for driving with<br />

<strong>the</strong> big Menck MHU 2100<br />

underwater hammer and<br />

grouting <strong>the</strong> skirt piles.<br />

Installation of <strong>the</strong> wellhead<br />

module also went well.<br />

‘Our colleagues at <strong>Heerema</strong><br />

<strong>Fabrication</strong> <strong>Group</strong> did a<br />

terrific job in aligning all<br />

those boltholes for connecting to <strong>the</strong><br />

jacket,’ Granneman remarks.<br />

The ‘in-house’ combination of all<br />

aspects from design to installation of <strong>the</strong><br />

<strong>Valemon</strong> jacket – divided between sister<br />

companies HFG and HMC – bore fruit<br />

right from <strong>the</strong> start.<br />

Once Thialf was chosen as installation<br />

vessel, <strong>the</strong> jacket design could be tailored<br />

even more precisely. One difference<br />

from rival vessel S7000 is that <strong>the</strong> blocks<br />

of Thialf’s main cranes are allowed<br />

underwater, even if that does mean a<br />

substantial job of cleaning and greasing<br />

afterwards. In <strong>the</strong> procedure chosen, one<br />

block went about 30m underwater.<br />

As for <strong>the</strong> two large trunnion nodes<br />

that proved such a headache to design,<br />

‘<strong>the</strong> jacket turned very smoothly’, says<br />

Granneman. He also mentions that<br />

because <strong>the</strong> planned operation was so<br />

close to Thialf’s limits, <strong>the</strong> option was<br />

kept open to place counterweights on <strong>the</strong><br />

very top of <strong>the</strong> jacket to modify <strong>the</strong> load<br />

distribution between <strong>the</strong> two cranes. In<br />

<strong>the</strong> end that was not called<br />

for.<br />

‘Small things can have<br />

a great impact on <strong>the</strong><br />

whole operation,’ says<br />

Granneman. He quotes<br />

<strong>the</strong> example of a flooding<br />

pipe whose position could<br />

interfere with <strong>the</strong> piledriving<br />

hammer. ‘We just<br />

adjusted our work method<br />

a little to allow that pipe to<br />

stay <strong>the</strong>re.’ Similarly it was<br />

agreed that guide pins on<br />

<strong>the</strong> top of <strong>the</strong> jacket could be<br />

included in <strong>the</strong> lift and be a<br />

helpful influence on centre of gravity.<br />

<strong>Valemon</strong> has taken jacket<br />

lift-installation procedures ano<strong>the</strong>r<br />

impressive step forward with completion<br />

of this lump sum contract from Statoil,<br />

rumoured to be worth about E150 million.<br />

There may not be any more big jacket<br />

lift-installation operations coming up<br />

this year, but clearly <strong>the</strong> technique will<br />

continue to be seen on some impressively<br />

heavy structures. Right now, Statoil’s<br />

representative through <strong>the</strong> whole<br />

<strong>Valemon</strong> jacket EPC – Kjell Arvid Tuen –<br />

is moving to <strong>the</strong> Dagny project.<br />

Dagny, says Tuen, ‘has a heavier<br />

topside, so <strong>the</strong> jacket is even closer to<br />

<strong>the</strong> maximum lift capacity of <strong>the</strong> two big<br />

crane vessels in <strong>the</strong> market. We are just<br />

about to take a decision on whe<strong>the</strong>r we<br />

should choose lift-installation or bargelaunch<br />

for Dagny.’ OE<br />

O F F S H O R E E N G I N E E R | a u g u s t 2 0 1 2 w w w. o f f s h o r e - e n g i n e e r. c o m<br />

courtesy heerema<br />

courtesy heerema<br />

courtesy woldcam as, anette westgård

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!