IWMP JODHPUR-40 SAI PANCHAYAT SMITI-SHERGARH<br />
ESTIMATE OF VEGETATIVE BUND IN ARABLE LAND<br />
Estimate <strong>of</strong> One ha.<br />
Length per ha. = 80 mtr<br />
S. no. Name <strong>of</strong> work No Length<br />
Width<br />
(TW+BW)<br />
/2 Hight Qty Unit Rate Amount<br />
1 Earth work Excavation for making <strong>of</strong> bund,<br />
laying in layers <strong>of</strong> 15 cm, breaking <strong>of</strong> clods,<br />
sorting <strong>of</strong> grass pebbles, disposal <strong>of</strong><br />
excavated material up to 1.5 mt Hight <strong>and</strong><br />
lead up to 50 m including dressing <strong>and</strong><br />
compaction<br />
1 80 1.85 1 148.00 Cum 85.00 12580.00<br />
2 Sowing <strong>of</strong> seeds on the constructed bund in<br />
three rows<br />
3 80 240 meter 0.60 144.00<br />
3 Supply <strong>of</strong> Stylo/Dhaman seed @ 4 gm / m in<br />
three rows<br />
Construction <strong>of</strong> Waste Weir Work<br />
Earth work Excavation for making <strong>of</strong> bund,<br />
3 80 Cazri Rate 0.96 Kg 150.00 144.00<br />
12868.00<br />
laying in layers <strong>of</strong> 15 cm, breaking <strong>of</strong> clods,<br />
sorting <strong>of</strong> grass pebbles, disposal <strong>of</strong><br />
excavated material up to 1.5 mt Hight <strong>and</strong><br />
lead up to 50 m including dressing <strong>and</strong><br />
compaction<br />
1<br />
{(2X3.55+2.2X.45)/2}+<br />
{(2X1.30+0.40X.30)/2}=3.1<br />
0<br />
3.1 Cum 85 263.5<br />
Dry Stone Pitching work on Earth bund in<br />
(15 to 23cm)<br />
1<br />
{2(.65+.65+2.2)X.23}<br />
=1.61<br />
1.61 Cum 715 1151.15<br />
Total(1+2) per 2 Hac 1414.65<br />
COST PER Hac 707.325<br />
13575.33<br />
Add 3% contingency 407.25975<br />
Total 13982.58<br />
Say 13980<br />
IWMP JODHPUR 42 <strong>TENA</strong>