Tintaya Antapaccay<br />
Approvals granted:<br />
• Positive feasibility completed Oct 2009.<br />
• EIS submitted Dec 2009.<br />
• Public consultation for EIS successfully<br />
completed March 2010.<br />
• EIS approval granted.<br />
• Corporate approvals granted.<br />
• Mining permit granted March 2012<br />
Current status:<br />
• Construction: 3Q10-3Q12.<br />
• Current status: 74% completed<br />
22