Construction<br />
High winds collapsed<br />
the cranes and highline<br />
cable<br />
Completion date pushed<br />
back 2 years<br />
$50 million in damages<br />
300,000 pounds of steel<br />
cable and debris had to<br />
be removed from the<br />
river