Airport<br />
experience<br />
Rehabilitation of runways <strong>–</strong> using<br />
Frankfurt International Airport as an example<br />
<strong>Kirchhoff</strong>’s expertise can be impressively demonstrated<br />
using the rehabilitation of the north<br />
and south runways at Frankfurt International<br />
Airport as an example. The requirements presented<br />
a great challenge to man, machinery<br />
and method:<br />
The runway was renewed without hindrance<br />
to fl ight operations, in a time window of just<br />
7.5 hours each night. Normal fl ights were able<br />
to resume punctually at 06:00 hours every<br />
morning.<br />
The runway was ripped up and renewed in<br />
sections 15 m long and 60 m wide during each<br />
of the so-called excavation nights.<br />
After an adequately large area had been made<br />
ready in the excavation nights, these were followed<br />
at regular intervals, every 5 to 7 weeks,<br />
by the so-called paving nights. The binder<br />
surface already laid was then cut away and<br />
replaced by a new asphalt wearing course.<br />
Flights were able to recommence without<br />
problems just 1.5 hours after the new surface<br />
had been installed.