Project Client / Contract $ Project Description Completed<br />

Port MacKenzie Segment 1 Alaska Railroad Corporation and<br />

Matanuska Susitna Borough<br />

111 W. 16th Avenue, Third Floor<br />

Anchorage, AK 99501<br />

$17.7 million<br />

Sutton Fire Cap Alaska Department of Natural<br />

Resources<br />

$1 million<br />

Wasilla Airport City of Wasilla<br />

Port MacKenzie Bi-Modal Bulk Facility,<br />

Phase I<br />

Heavy Civil Experience<br />

$1 million<br />

Alaska Railroad Corporation<br />

$6 million<br />

Location: Port MacKenzie, Alaska<br />

First segment in a larger project to connect the port to the Alaska<br />

Railroad mainline.<br />

Scope of work included:<br />

- Build 5 miles of embankment<br />

- Expand the existing bi-modal bulk facility<br />

- Land clearing, facility upgrades and culvert installation<br />

- Construction of a three-span bridge<br />

- Excavation and placement of nearly 4 million cubic yards of material.<br />

Location: Sutton, Alaska<br />

Scope of work included:<br />

<br />

N. Jones Road<br />

- Install gravel cover and ditch structures over 2 miles of road to improve<br />

vehicle access and drainage.<br />

Location: Wasilla, Alaska<br />

Phase 2 expansion of Apron D<br />

Scope of work included:<br />

- Clearing and grubbing<br />

- Excavate 42,000 cubic yards, 20,000 tons of subbase<br />

- Drainage improvements<br />

- Place crushed rock base course, paved and installed airplane tiedowns<br />

- Construct a new 0.5-mile access road.<br />

Location: Port MacKenzie, Alaska<br />

The construction of two roadways and an adjacent pad.<br />

Scope of work included:<br />

<br />

- Excavation and grading<br />

- Installation of culverts and permanent stabilization structures<br />

- Vegetation re-establishment.<br />

(877) 563-0013<br />

www.bristol-companies.com<br />

Scheduled for<br />

completion<br />

November 2013<br />

July 2012<br />

April 2012<br />

October 2010


1/7/2013<br />

Project Client / Contract $ Project Description Completed<br />

Advanced Tactical Training Area US Army Corps of Engineers ® ,<br />

Charleston District<br />

111 W. 16th Avenue, Third Floor<br />

Anchorage, AK 99501<br />

Heavy Civil Experience<br />

$3.5 million<br />

Elim Airport Rehabilitation Alaska Department of<br />

Transportation and Public Safety<br />

$6.9 million<br />

New Stuyahok Airport Access Road New Stuyahok Tribal Council<br />

$1 million<br />

Location: Department of Energy’s Savannah River Site, N.C.<br />

Scope of work included:<br />

<br />

Advanced Tactical Training Area<br />

<br />

and various concrete control structures.<br />

Location: Elim, Alaska<br />

Repair and reconstruct a public airport located in a remote area of<br />

Northwest Alaska in Norton Bay, about 100 miles east of Nome.<br />

Scope of work included:<br />

- Repair and reconstruction of a public airport<br />

- Extend an existing 3,000-foot long runway to 3,400 feet, and widen it<br />

from 60 feet to 75 feet<br />

- Install a new lighted wind-cone and segmented circle<br />

- Install new airport lighting, a rotating beacon and an electrical<br />

equipment enclosure.<br />

Location: New Stuyahok, Alaska<br />

Construction of the New Stuyahok Airport Access Road.<br />

Scope of work included:<br />

- Construction of 2.9 kilometers of road, beginning at the existing runway<br />

and heading northwest to the location of the new airport.<br />

(877) 563-0013<br />

www.bristol-companies.com<br />

September 2007<br />

September 2005<br />

June 2004


2/12/2013<br />

Project Client / Contract $ Project Description Completed<br />

Airborne Training Facility US Army Corps of Engineers ® ,<br />

Alaska District<br />

111 W. 16th Avenue, Third Floor<br />

Anchorage, AK 99501<br />

Site Preparation Experience<br />

$5.4 million<br />

Child Development Center US Army Corps of Engineers ® ,<br />

Alaska District<br />

$13.4 million<br />

Troop Health Clinic US Army Corps of Engineers ® ,<br />

Alaska District<br />

$2 million<br />

Location: Joint Base Elmendorf-Richardson, Alaska<br />

Civil construction work required to construct an organizational classroom<br />

building.<br />

Scope of work includes:<br />

- Aircraft mockups<br />

- Relocate an existing galvanized jump tower, one existing C130 mockup<br />

and one existing C17 mockup<br />

- Construction of new C130 and C17 mockups<br />

- Construction of jump pits as a training facility<br />

- Construction of eight parachute landing fall pits, and one C130 aircraft<br />

mockup<br />

<br />

one C17.<br />

Location: Joint Base Elmendorf-Richardson, Alaska<br />

Project was the civil construction phase of the $13.7 million project.<br />

Scope of work included:<br />

- Clear forested area for the 23,000-square-foot facility<br />

- Utility tie-ins for water, sewer and storm drain<br />

<br />

<br />

- Pave access and parking.<br />

Location: Joint Base Elmendorf-Richardson, Alaska<br />

The civil construction activities consisted of demo of two buildings, concrete<br />

wash stand and associated utilities.<br />

Scope of work included:<br />

- Demo of existing parking lot prior to excavation<br />

- Subgrade prep completed for construction<br />

- New parking facility, parking surface and fence<br />

- Clearing and grubbing<br />

<br />

stockpile activities.<br />

(877) 563-0013<br />

www.bristol-companies.com<br />

November 2011<br />

November 2010<br />

January 2009


1/7/2013<br />

Project Client / Contract $ Project Description Completed<br />

F-22 Low Observable Infrastructure US Army Corps of Engineers ® ,<br />

Alaska District<br />

111 W. 16th Avenue, Third Floor<br />

Anchorage, AK 99501<br />

Site Preparation Experience<br />

$5 million<br />

Location: Joint Base Elmendorf-Richardson, Alaska<br />

Scope of work included:<br />

- Clearing and grubbing of 15 acres<br />

- Export 50,000 cubic yards for hangar and igloo sites<br />

<br />

apron, tow way and building construction<br />

<br />

<br />

<br />

munication<br />

systems, and several road bores to tie in to existing utilities.<br />

(877) 563-0013<br />

www.bristol-companies.com<br />

Summer 2008


2/12/2013<br />

Project Client / Contract $ Project Description Completed<br />

Point Lay Long Range Radar Station<br />

<br />

111 W. 16th Avenue, Third Floor<br />

Anchorage, AK 99501<br />

AECOM<br />

$1.9 million<br />

Federal Aviation<br />

Administration<br />

Bethel Readiness Center Site<br />

Preparation<br />

Remote Capabilities<br />

$14.3 million<br />

Alaska Department of<br />

Transportation and<br />

Public Facilities<br />

$1.6 million<br />

Adak Dewatering System Rehabilitation Alaska Department of<br />

Transportation and Public<br />

Facilities<br />

$375,916<br />

Location: Point Lay, Alaska<br />

Scope of work included:<br />

- Excavate waste and segregate in to clean, reusable material<br />

- Excavate and stockpile clean material<br />

<br />

- Excavate and bag contaminated materials<br />

<br />

Location: Cape Yakataga, Alaska<br />

nated<br />

soil would have to be removed as well.<br />

Location: Bethel, Alaska<br />

Site preparation in anticipation of the construction of a National Guard<br />

complex.<br />

Scope of work included:<br />

- Brush clearing<br />

- Debris excavation<br />

- Roughly 110,000 tons of material brought in, compacted and brought to<br />

grade<br />

- Erosion control implemented with hydro-seeding<br />

- Soil compacted and contoured.<br />

Location: Adak Island, Alaska<br />

Replace a stormwater pumping station to keep Sleeper Creek from over-<br />

<br />

Scope of work included:<br />

- Replace pumps and associated piping<br />

- Upgrade the facility that housed the pumps.<br />

(877) 563-0013<br />

www.bristol-companies.com<br />

Scheduled for<br />

completion in<br />

June 2013<br />

September 2008<br />

October 2006<br />

May 2006


1/7/2013<br />

Project Client / Contract $ Project Description Completed<br />

White Alice Tram and Waterline<br />

<br />

111 W. 16th Avenue, Third Floor<br />

Anchorage, AK 99501<br />

Remote Capabilities<br />

US Army Corps of Engineers ® ,<br />

Alaska District<br />

$5.2 million<br />

Location: St. Lawrence Island, Northeast Cape, Alaska<br />

Remove Cold War-era communications equipment and restore area.<br />

Scope of work included:<br />

- Prepare plans and reports<br />

- Mobilize/demobilize to/from the Northeast Cape site<br />

- Provide and improve access to the work sites<br />

- Excavate and dispose of soils contaminated with polychlorinated biphenyls<br />

(PCBs)<br />

- Mitigatie concrete slabs contaminated with PCBs<br />

- Clean up miscellaneous items and debris<br />

- Remove a water collector and former power and communication poles<br />

and wires<br />

- Demo a former tram and a waterline<br />

- Reseed disturbed areas.<br />

(877) 563-0013<br />

www.bristol-companies.com<br />

September 2005


2/12/2013<br />

Project Client / Contract $ Project Description Completed<br />

Texas State University Demo Tower Texas State University<br />

111 W. 16th Avenue, Third Floor<br />

Anchorage, AK 99501<br />

Demolition<br />

$537,500<br />

Bassett Army Helipad US Army Corps of Engineers ® ,<br />

Alaska District<br />

$2.8 million<br />

White Alice Site Removal Action Department of the Army<br />

US Army Corps of Engineers ® ,<br />

Alaska District<br />

$12.2 million<br />

Location: San Marcos, Texas<br />

Demo tower and related facilities.<br />

Scope of work included:<br />

- Demo and remove debris, including existing sky spiral tower, two cable<br />

ride towers and adjoining ticket booth<br />

- Remove and replace fencing<br />

<br />

Location: Fort Wainwright, Alaska<br />

Demo of helipad, including hazard control.<br />

Scope of work included:<br />

- Site clearing<br />

- Reroute existing drainage swale located northwest of the new heli-pad<br />

- Pad and subgrade preparation<br />

<br />

- Placement of pavement asphalt<br />

- Asbestos and lead abatement<br />

- Demo and remove a 995-square-meter building, located east of the<br />

new hospital<br />

- Special construction included asbestos hazard control activities, lead in<br />

construction, handling of lighting ballasts and lamps containing polychlorinated<br />

biphenyls (PCBs) and mercury.<br />

Location: St. Lawrence Island, Northeast Cape, Alaska<br />

Demo and removal of Cold War-era communications system.<br />

Scope of work included:<br />

- Prepare planning documents<br />

- Mobilize/demobilize and overall project logistics, including establishing<br />

and maintaining a temporary construction camp, providing air support,<br />

and deploying a satellite communications system<br />

- Provide and improve access to the work sites<br />

- Demo and remove more than 30 buildings and structures, fuel lines and<br />

fuel storage facilities, as well as approximately 60 miles of power and<br />

communications poles and wires, three septic systems, and more than<br />

4,000 linear feet of utilidors<br />

- Remove and dispose of containerized hazardous and toxic waste<br />

(Con-HTW), drums, and miscellaneous items and debris<br />

- <strong>Of</strong>f-island transport and disposal of more than 5,000 tons of inert and<br />

contaminated demolition debris.<br />

(877) 563-0013<br />

www.bristol-companies.com<br />

July 2012<br />

October 2007<br />

September 2003


1/7/2013<br />

Project Client / Contract $ Project Description Completed<br />

ROTHR Facilities Demolition Engineering Field Activity,<br />

Northwest<br />

111 W. 16th Avenue, Third Floor<br />

Anchorage, AK 99501<br />

Demolition<br />

$11.8 million<br />

Roberts Demolition Naval Engineering Field Activity,<br />

Northwest<br />

$1.4 million<br />

Location: Amchitka, Alaska<br />

Scope of work included:<br />

- Demo of 56 structures<br />

- Remove 46 aboveground storage tanks (ASTs) and 22,000 gallons of<br />

off-speculation fuel<br />

- Remove six regulated underground storage tanks (USTs)<br />

<br />

7,000 gallons of transformer oil<br />

- Drain, inert, demo, and dispose of approximately 3,500 feet of fuel<br />

pipeline<br />

- Transport and dispose of 32,000 cubic yards (26,000 tons) of demo<br />

<br />

<br />

Location: Adak Island, Alaska<br />

Demo of old and new Roberts housing units.<br />

Scope of work included:<br />

- Demo and dispose 68 duplex-housing units at three sites in support of<br />

the Navy’s efforts to reduce the infrastructure footprint on Adak —<br />

<br />

- Utilize an “air curtain” incineration unit to help achieve high levels of<br />

waste reduction (80 percent to 90 percent).<br />

(877) 563-0013<br />

www.bristol-companies.com<br />

December 2001<br />

July 2000


1/7/2013<br />

Project Client / Contract $ Project Description Completed<br />

Pendleton Boulevard & Exterior<br />

Roadways Banana Belt<br />

111 W. 16th Avenue, Third Floor<br />

Anchorage, AK 99501<br />

Utilities Experience<br />

US Army Corps of Engineers ® ,<br />

Seattle District<br />

$27 million<br />

South Gambell Street Drainage Municipality of Anchorage<br />

$1.1 million<br />

F-22 Bed Down Infrastructure US Army Corps of Engineers ® ,<br />

Alaska District<br />

$20 million<br />

Location: Joint Base Lewis-McChord, Wash.<br />

Improve the entrance into the military base.<br />

Scope of work included:<br />

- Rebuild roadway at entrance<br />

<br />

- Improve parking and facility access<br />

- Create attractive bike and pedestrian trails<br />

- Install attractive lighting and landscaping.<br />

Location: S. Gambell Street, 120th Avenue to Klatt Road, Anchorage,<br />

Alaska<br />

Scope of work included:<br />

- 1,434 cubic yards of unusable excavation<br />

- 1,000 tons of leveling course<br />

- 890 tons of RAP<br />

- 15 tons of asphalt<br />

- 88 tons of cover aggregate<br />

- 600 lf storm drain pipe<br />

- 1,118 linear feet of 18’ high density polyethylene force main<br />

- Storm water lift station.<br />

Location: Joint Base Elmendorf-Richardson, Alaska<br />

Design/construct the F-22A Fighter Town east infrastructure and taxiway,<br />

taxilanes and apron.<br />

ELM286<br />

Scope of work included:<br />

- Expand infrastructure and utility systems – extension of a looped water<br />

distribution system<br />

- Underground electrical distribution system<br />

- Expand wastewater collection system with pump stations and forced<br />

mains<br />

<br />

- Site grading<br />

<br />

ELM290:<br />

Scope of work included:<br />

<br />

apron, associated taxilanes, taxiway, apron and shoulders<br />

- Pavement markings, taxiway lighting with vault and site improvements.<br />

(877) 563-0013<br />

www.bristol-companies.com<br />

May 2013<br />

October 2011<br />

October 2010


2/12/2013<br />

Project Client / Contract $ Project Description Completed<br />

7&8 Bay Site Civil Frawner Corporation<br />

Repair Sanitary Sewer Lines at<br />

Broadmoor<br />

111 W. 16th Avenue, Third Floor<br />

Anchorage, AK 99501<br />

Utilities Experience<br />

$355,279<br />

US Army Corps of Engineers ® ,<br />

Seattle District<br />

$725,000<br />

Fort Lewis Sewer Replacement US Army Corps of Engineers ® ,<br />

Seattle District<br />

$4.7 million<br />

Location:<br />

<br />

Scope of work included:<br />

<br />

hydrants.<br />

Location: Joint Base Lewis-McChord, Wash.<br />

Scope of work included:<br />

- Replace existing sewer pipe and manholes<br />

- Install new sewer line and manholes parallel to existing structures<br />

- Replace concrete sidewalk, roadway and curb<br />

- Install Americans with Disabilities Act ramp<br />

- Replace grass and topsoil<br />

- Remove and replace playground equipment.<br />

Location: Joint Base Lewis-McChord, Wash.<br />

Scope of work included:<br />

- Removal and replacement of 6,000 feet of sewer main<br />

<br />

- Rehabilitation of 14 existing manholes<br />

- Installation of a sludge-dewatering facility at sewage treatment plant<br />

- Road work performed included grading, drainage, asphalt paving,<br />

<br />

(877) 563-0013<br />

www.bristol-companies.com<br />

October 2009<br />

March 2009<br />

March 2008


2/12/2013<br />

Project Client / Contract $ Project Description Completed<br />

Anchorage Municipal Snow Disposal Municipality of Anchorage<br />

111 W. 16th Avenue, Third Floor<br />

Anchorage, AK 99501<br />

<br />

$2.25 million<br />

Native Village of Ugashik<br />

Traditional Council<br />

$252,734<br />

United States Air Force<br />

$2 million<br />

Location: Anchorage, Alaska<br />

Construction of a snow disposal site on 12 acres.<br />

Scope of work included:<br />

- Clearing and grubbing land<br />

- Excavate and install a settling/dilution pond<br />

- Construct two access roads<br />

- Add landscaping<br />

- Install light poles and lights<br />

- Place 8-foot-tall sound barrier fence.<br />

Location: Ugashik, Alaska<br />

<br />

Location: Shemya, Alaska<br />

<br />

construct a new MSWL and asbestos disposal cell.<br />

Scope of work included:<br />

- Close existing MSWL by placing and grading 112,000 cubic yards of<br />

<br />

topsoil<br />

<br />

yards of peat to develop new borrow area<br />

- Prepare location of new MSWL and asbestos disposal cell<br />

<br />

(877) 563-0013<br />

www.bristol-companies.com<br />

August 2012<br />

July 2006<br />

August 2005


2/12/2013<br />

Project Client / Contract $ Project Description Completed<br />

Caldwell Lane Bank Stabilization US Army Corps of Engineers ® ,<br />

Fort Worth District<br />

111 W. 16th Avenue, Third Floor<br />

Anchorage, AK 99501<br />

$1.2 million<br />

North Forest Acres Levee Road City of Seward<br />

Tidal Surge Damage Shoreline<br />

Restoration and Lowell Creek Bridge<br />

Paving<br />

Levees and Bank Stabilization<br />

$1.2 million<br />

City of Seward<br />

$260,000<br />

Bethel Bank Stabilization US Army Corps of Engineers ® ,<br />

Alaska District<br />

$4.6 million<br />

<br />

Engineering, design and construction of riverbank stabilization on 1,200<br />

feet of riverbank along the Colorado River.<br />

Scope of work included:<br />

<br />

- Place riprap<br />

- Plant native vegetation along upper portions of riverbank<br />

<br />

Location: Seward, Alaska<br />

Scope of work included:<br />

- Clearing and grubbing of 10 acres<br />

<br />

<br />

to the road.<br />

Location: Seward, Alaska<br />

Restore a section of shoreline in Seward.<br />

Scope of work included:<br />

<br />

- Recover and place riprap armor rock<br />

- Repair seawall embankment<br />

- Level and grade parking lot<br />

- Remove and replace curb and gutter<br />

- Place topsoil.<br />

Location: Bethel, Alaska<br />

Stabalize bank along city dock and small boat harbor.<br />

Scope of work included:<br />

<br />

harbor<br />

<br />

seawall.<br />

(877) 563-0013<br />

www.bristol-companies.com<br />

March 2013<br />

September 2011<br />

May 2011<br />

January 2008


2/12/2013<br />

Project Client / Contract $ Project Description Completed<br />

South Naknek Construction Survey Bureau of Indian Affairs<br />

111 W. 16th Avenue, Third Floor<br />

Anchorage, AK 99501<br />

$39,000<br />

Adak Water Design Survey <strong>Bristol</strong> Engineering Services<br />

Corporation<br />

$27,000<br />

Airborne Training Facility <strong>Bristol</strong> Construction Services, LLC<br />

$36,000<br />

Nome Roads Design Survey <strong>Bristol</strong> Engineering Services<br />

Corporation<br />

$28,000<br />

Survey Experience<br />

Location: South Naknek, Alaska<br />

Provide surveying to build Diamond M road and quantities for borrow<br />

source.<br />

Scope of work includes:<br />

- Horizontal and vertical control<br />

- Stake borrow site<br />

- Cross section borrow site before<br />

excavation<br />

- Cross section borrow site after<br />

excavation<br />

Location: Adak, Alaska<br />

Scope of work includes:<br />

- Provide survey for a water line rehabilitation of existing water line<br />

- Locate and map all existing features above ground and below ground<br />

<br />

- Provide a 50 scale drawing for design plan set.<br />

Location: Joint Base Elmendorf-Richardson, Alaska<br />

Scope of work includes:<br />

- Horizontal and vertical control<br />

- Slope stakes<br />

- Clearing limits<br />

- Edge of pavement<br />

- Edge of concrete<br />

- Storm<br />

- Fence<br />

- Striping<br />

Location: Nome, Alaska<br />

Provide design survey of 3,500 existing roads, 25 beyond right-of-way<br />

for road.<br />

Scope of work includes:<br />

- All topographic features above and below ground<br />

- Provision of a 50 scale drawing for design plan set.<br />

(877) 563-0013<br />

www.bristol-companies.com<br />

- Clearing limits<br />

- Slope stakes<br />

- Culverts<br />

- Red tops<br />

- Signs<br />

- Quantity computation.<br />

- Signs<br />

- C-17 aircraft mockup positions<br />

- Jump tower location<br />

- C-130 aircraft mockup positions<br />

- Load centers<br />

- Red tops<br />

- Blue tops<br />

- Light poles.<br />

Ongoing<br />

Ongoing<br />

November 2011<br />

October 2009


2/12/2013<br />

Project Client / Contract $ Project Description Completed<br />

Big Cypress Bayou US Army Corps of Engineers ® ,<br />

Forth Worth District<br />

111 W. 16th Avenue, Third Floor<br />

Anchorage, AK 99501<br />

Eco Restoration<br />

$3 million<br />

Spring Lake US Army Corps of Engineers ® ,<br />

Fort Worth District<br />

$2 million<br />

Location: Jefferson, Texas<br />

Construction and eco restoration efforts.<br />

Scope of work included:<br />

<br />

Wildlife project<br />

- Remove parking lots and walkways<br />

- Remove boat launch<br />

- Build elevated walkways<br />

- Construct water control structure<br />

- Plant vegetation and landscaping.<br />

Location: San Marcos, Texas<br />

Restoration on a 39-acres site.<br />

Scope of work included:<br />

- Demo and remove several structures and hard surfaces<br />

- Habitat restoration<br />

- Remove of invasive and exotic plant species<br />

- Grading and placement of bus turnaround<br />

- Install new bathroom facility.<br />

(877) 563-0013<br />

www.bristol-companies.com<br />

August 2013<br />

September 2012


2/12/2013<br />

Project Client / Contract $ Project Description Completed<br />

Military Ocean Terminal at Sunny Point US Army Corps of Engineers ® ,<br />

Savannah District<br />

111 W. 16th Avenue, Third Floor<br />

Anchorage, AK 99501<br />

Railroad Experience<br />

$40 million<br />

Location: Southport, N.C.<br />

The project was contracted to <strong>Bristol</strong> Construction. Project-wide, we are<br />

removing and reinstalling 78,000 track-feet.<br />

Scope of work included:<br />

- Reshape track subgrade to accommodate larger radius track<br />

- Install new railway, including ballast material, ties, rail, plates, bolts and<br />

switches<br />

- Install 158, No. 10 switches<br />

- Install 350 track-feet of new concrete road crossings<br />

- Install more than 500 linear feet of drainage conduits<br />

- Miscellaneous asphalt paving and clearing.<br />

(877) 563-0013<br />

www.bristol-companies.com<br />

Ongoing