Planning<br />

Approval Action Reference Receive Approve Remarks<br />

State Planning & Research (SPR) Work Program 23 CFR 420.111 FHWA FHWA ADOT annually develops work program<br />

Long-Range Statewide Transportation Plan 23 CFR 450.214 FHWA ADOT FHWA reviews and comments on LRTP. No <strong>of</strong>ficial approval action is taken.<br />

Statewide Transportation Improvement Program (STIP) 23 CFR 450.216 FHWA & FTA FHWA & FTA<br />

MPO Indirect Cost Allocation Plan<br />

23 CFR 420<br />

OMB Circular A-87<br />

5<br />

Covers a 4 year period; update required every 4 years, but ADOT traditionally<br />

updates annually.<br />

ADOT ADOT Annual Submission. ADOT forwards approvals for FHWA information.<br />

MPO Unified Planning Work Programs (UPWP) 23 CFR 450.308 ADOT FHWA & FTA FHWA & FTA MPO annually develops UPWP<br />

Metropolitan 20-Year Long-Range Transportation Plan (LRTP) 23 CFR 450.322 ADOT FHWA & FTA MPO<br />

Metropolitan Transportation Improvement Plan (TIP) 23 CFR 450.324 ADOT FHWA & FTA ADOT<br />

FHWA, FTA & ADOT review and comment on Metropolitan LRTPs but do not<br />

approve. However, FHWA/FTA must make an air quality conformity determination.<br />

Covers a 4 year period; update required every 4 years, however can be updated<br />

more frequently.<br />

Transportation Management Area (TMA) Certification <strong>of</strong> MAG and PAG 23 CFR 450.334 FHWA & FTA FHWA & FTA FHWA and FTA jointly certify every 4 years<br />

<strong>Highway</strong> Performance Monitoring System (HPMS) Annual Data Submittal from<br />

State and Field Verification Review and Report (including Traffic Volume<br />

Monthly ATR Data and Annual Truck Weight Data)<br />

23 CFR 420.105 FHWA FHWA Certifies<br />

<strong>Highway</strong> Statistics: 500 Series Reports 23 CFR 420.105 FHWA None<br />

Certification <strong>of</strong> Public Road Mileage 23 CFR 460.3 FHWA FHWA HQ<br />

Environment<br />

FHWA annually conducts a field verification review for funding apportionment and<br />

allocation purposes. ADOT submits required ATR and other data reports directly to<br />

FHWA HQ<br />

ADOT is required to submit several <strong>Highway</strong> Statistics forms periodically. Form 551-<br />

M for motor fuel is submitted monthly.<br />

Due by June 1 st <strong>of</strong> each year. The Governor has delegated certification authority to<br />

the ADOT Director.<br />

Programmatic approval authority for specific categorical exclusions 23 CFR 771.109 FHWA ADOT ADOT has been granted pre-approved authority for specific categorical exclusions<br />

ADOT acts as FHWA's non-federal representative for Section 7 (Endangered<br />

Species Act) consultation<br />

ADOT acts as FHWA’s non-federal representative for Section 106 (National<br />

Historic Preservation Act) consultation<br />

23 CFR 771.109 FHWA FHWA<br />

23 CFR 771.133 FHWA FHWA<br />

ADOT public involvement procedures 23 CFR 771.111(h)(1) FHWA FHWA Current approved procedures are in the 1988 Action Plan<br />

Noise Abatement Policy<br />

Contract <strong>Administration</strong> and Design<br />

ADOT Contract Award and <strong>Administration</strong> Rules and Procedures (Consultant<br />

Selection Procedures)<br />

Table 1 – Program Responsibility Chart<br />

23 CFR 772<br />

HQ Memo 6/12/95<br />

FHWA FHWA FHWA approves ADOT’s noise abatement policy & updates<br />

23 CFR 172 FHWA FHWA<br />

ADOT ECS Procurement Program 23 CFR 172 FHWA<br />

FHWA<br />

certifies<br />

ADOT Procurement Procedures and standard language 49 CFR 18.36(a) FHWA ADOT<br />

Approval <strong>of</strong> State Consultant Selection Procedures is outlined in 23 CFR 172.9 and<br />

approval takes places as ADOT updates their procedures.<br />

Joint decision between ADOT and FHWA to review the program on a four year<br />

cycle<br />

FHWA reviews and comments to ensure federal terms and conditions are included<br />

in project contracts following the Arizona Procurement Code