Section 3: <strong>Decommissioning</strong> the 48V DC system<br />
Overview:<br />
The 48 V DC system is used to drive the dish movements. There are 5 UPS cabinets in the field – one for<br />
each dish group. Batteries are charged via the 575AC system. System voltage for each UPS can be<br />
monitored in the control room. Cabling runs in trenches throughout the site and will have to be<br />
excavated. Refer to the as built drawing for the trench arrangements and layouts.<br />
Safety Concerns:<br />
575 VAC present. 48VDC present.<br />
MSDS: None<br />
Reference Drawings: As built Electrical Dwgs: E1-3; E1-4. Mortensen as built files.<br />
Go to the UPS cabinets and open the breakers feeding each group of 3 dishes. This will remove<br />
the 48V DC supply to the dishes.