02.03.2014 Views

[322/03] Francke - Ingenia

[322/03] Francke - Ingenia

[322/03] Francke - Ingenia

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

NILS FRANCKE<br />

ØRESUNDBRO KONSORTIET<br />

INFRASTRUCTURE<br />

The Øresund Bridge<br />

– linking<br />

Scandinavia<br />

to the<br />

continent<br />

The Øresund Bridge, one of the<br />

largest infrastructure projects in<br />

the history of Europe, is set to<br />

change southern Scandinavia forever.<br />

A combined tunnel and bridge link<br />

carrying the motorway and railway has<br />

replaced the existing ferry routes<br />

between the Danish capital of<br />

Copenhagen and the Swedish regional<br />

capital of Malmö.<br />

The Øresund Bridge comprises three<br />

major civil works projects: a 4 km<br />

artificial island, the world’s largest<br />

immersed tunnel for both railway and<br />

motorway, as well as the 7.8 km bridge<br />

with a cable-stayed high bridge as the<br />

impressive centrepiece.<br />

Almost five years after the civil works<br />

began the Øresund Bridge was opened<br />

to traffic on 1 July 2000. This 3 billion<br />

USD project was completed on<br />

schedule as well as on budget.<br />

The new and greatly improved<br />

infrastructure will further the integration<br />

of the area now known as the Øresund<br />

Region, a cross-border region with<br />

roughly 3.5 million Danish and Swedish<br />

inhabitants. Combining the best of<br />

Copenhagen and Malmö, the Øresund<br />

Region will have a major impact on<br />

Northern Europe in terms of education,<br />

science, finance and culture. But<br />

before full integration can be achieved,<br />

a substantial amount of legislation has<br />

to be introduced, not least within the<br />

labour market and education.<br />

ingenia<br />

23


INFRASTRUCTURE<br />

Figure 2: The route of the Øresund Bridge<br />

ingenia<br />

The skill with which the contractors<br />

successfully planned and executed the<br />

construction of the tunnel, the bridge<br />

and the major dredging works can<br />

largely be ascribed to the Design-and-<br />

Construct concept which forms a part<br />

of all the major contracts. Optimum use<br />

of prefabrication also played a key role.<br />

As the Design-and-Construct concept<br />

lays down precise functional<br />

requirements for the whole project,<br />

contractors are responsible for the<br />

detailed design as well as for the<br />

construction work.<br />

Rigorous environmental requirements<br />

were in force throughout the<br />

construction period, governing both the<br />

construction of the link and the impact<br />

of the completed link on the<br />

surrounding environment. As the Danish<br />

and Swedish governments had<br />

stipulated that the link must not block<br />

the water flow through Øresund, careful<br />

trimming of the link’s design reduced<br />

the calculated blocking effect from 2.3<br />

per cent of the water flow to 0.5 per<br />

cent prior to final adjustment.<br />

Compensation dredging in and around<br />

the alignment further reduced the<br />

blocking effect.<br />

Dredging and reclamation<br />

The dredging and reclamation contract<br />

included the initial construction works<br />

for the fixed link which began in August<br />

1995. Over four years a total of 7.5<br />

million cubic metres of (mainly) seabed<br />

material was dredged, two thirds in<br />

Danish waters and one third in Swedish<br />

waters. The seabed consists of gravel<br />

and stone, clay till and limestone with<br />

flint layers.<br />

Dredging was carried out by a<br />

number of dredgers, traditional bucket<br />

dredgers as well as a specialised<br />

cutter/suction dredger for the tunnel<br />

trench.<br />

The objective was for the<br />

completed link to have no net effect<br />

on the water flow and on the<br />

movement of salt and dissolved<br />

oxygen through Øresund to the Baltic<br />

Sea. Consequently the size and shape<br />

of the peninsula and the island were<br />

optimised to reduce the blocking of<br />

the water flow through Øresund.<br />

Further reduction to zero blocking was<br />

achieved by compensation dredging.<br />

All dredged seabed material was<br />

reused in the reclaimed areas which<br />

cut sediment spill to a minimum and,<br />

in addition, reduced the need for<br />

dumping sites as well as for import of<br />

sand and gravel.<br />

The dredging works included:<br />

● Work harbours and access channels<br />

at the artificial island and the artificial<br />

peninsula<br />

24


INFRASTRUCTURE<br />

● A trench for the immersed tunnel<br />

● Relocation of the Drogden Channel<br />

● Relocation and deepening of the<br />

Flinte Channel<br />

● Compensation dredging to achieve<br />

zero blocking of the water flow<br />

The reclamation works included:<br />

● The artificial peninsula at Kastrup<br />

● The artificial island which connects<br />

the tunnel and the bridge<br />

The 0.9 km 2 peninsula at Kastrup<br />

serves to bring together the passenger<br />

track from the underground station at<br />

Kastrup Airport with the freight track<br />

running north of the airport. The<br />

motorway along the northern edge of<br />

the peninsula joins the railway at the<br />

entrance to the tunnel portal. The<br />

peninsula also has a track leading to a<br />

railway maintenance area.<br />

The 1.3 km 2 artificial island south of<br />

the natural island of Saltholm forms the<br />

transition between the tunnel and the<br />

bridge. From the tunnel portal on the<br />

western end of the island, the motorway<br />

runs parallel to the railway to the eastern<br />

end, from where the railway runs under<br />

the motorway on to the two level bridge.<br />

The reclamation areas were<br />

constructed as basins surrounded by<br />

coarse pebble bunds lined with a<br />

geotextile membrane. The basins were<br />

then backfilled with clay to prevent the<br />

suspended sediment from escaping.<br />

Reclamation was carried out in stages<br />

as the bunds were completed,<br />

surrounding the individual sections.<br />

During filling at the artificial island, the<br />

traffic corridor for the high-speed<br />

railway was compacted to minimise any<br />

differential settlements which could<br />

interfere with the passage of highspeed<br />

trains. The reclaimed areas were<br />

completed with revetments, comprising<br />

layers of armour stones and filter<br />

stones. The revetments protect the<br />

tunnel against flooding during storms<br />

and high water.<br />

The immersed tunnel<br />

The tunnel extends approximately 4 km<br />

from the Danish coast at Copenhagen<br />

Airport to the artificial island in the<br />

middle of Øresund. The tunnel<br />

comprises five parallel tunnel tubes –<br />

two for the railway, two for the<br />

motorway plus a small tunnel as an<br />

escape gallery. The sheer size of the<br />

tunnel and the shallow waters in this<br />

part of Øresund made an immersed<br />

tunnel the natural choice.<br />

Figure 3: Aerial view of tunnel factory<br />

ingenia<br />

25


INFRASTRUCTURE<br />

ingenia<br />

26<br />

Figure 4: Aerial view of tunnel section being towed to site<br />

The immersed tunnel was<br />

constructed from twenty prefabricated<br />

concrete tunnel elements. The elements<br />

were cast at a purpose-built factory 12<br />

km north of the tunnel site. Each<br />

element was towed to the tunnel site by<br />

four tug boats and lowered into the<br />

tunnel trench with enormous precision,<br />

using GPS satellite navigation.<br />

The fact that casting took place<br />

under cover allowed for efficient and<br />

smooth production, regardless of the<br />

weather. As a positive side effect the<br />

number of work-related accidents was<br />

subsequently reduced.<br />

Each tunnel element is 176 metres<br />

long, 49 metres wide, approximately 9<br />

metres high and weighs around 57,000<br />

tonnes. Each element was cast in eight<br />

sections at the tunnel factory each of<br />

which was cast in one 30 hour cycle.<br />

Each section was cast against the<br />

previous section and the element was<br />

then gradually pushed out of the<br />

casting hall and on to a ramp, in what<br />

was, in effect, a giant lock system.<br />

When all eight sections were cast and<br />

one complete 176 metre element was<br />

ready, a sliding gate was closed behind<br />

the element, and the basin was flooded<br />

until the element floated.<br />

The element could then be pulled<br />

into the deep end of the basin to await<br />

being towed to the tunnel site. After the<br />

water inside the lock had reached sea<br />

level allowing the element to be towed<br />

out, the next two elements would be<br />

cast. Two parallel production lines<br />

allowed for maximum output and<br />

efficiency.<br />

The towing of the elements<br />

demanded great skill and precision. The<br />

57,000 tonne element was almost<br />

completely immersed during towing<br />

and the changing currents in Øresund<br />

had to be calculated in great detail<br />

before the towing-out. This operation<br />

took place in the Drogden Channel in<br />

Western Øresund, which is an<br />

international shipping route used by<br />

some 40,000 ships per year. Early in<br />

the construction phase a radar station<br />

was established to monitor shipping<br />

and guide vessels through the work<br />

areas thus avoiding any major<br />

accidents. During operations only a<br />

handful of collisions and minor incidents<br />

took place involving work vessels and<br />

shipping, causing material damage only.<br />

Not once was a tunnel element<br />

damaged due to a collision. However,<br />

on 4 August 1998, the accident that<br />

everybody was dreading took place: a<br />

tunnel element was flooded while being<br />

positioned in the tunnel trench. Before<br />

tow-out the tunnel tubes in the element<br />

were sealed off with steel bulkheads.<br />

Due to a number of mistakes one<br />

bulkhead was not properly secured and<br />

succumbed to the water pressure. In a<br />

matter of seconds all five tunnel tubes<br />

in the large concrete element filled with<br />

water, and in accordance with<br />

procedures the element was<br />

immediately lowered into the trench,<br />

but several metres out of position. It<br />

took Øresund Tunnel Contractors eight<br />

weeks to inspect, repair and eventually<br />

move the tunnel element into its correct<br />

position.<br />

During this period the lowering gear<br />

and platforms were attached to the<br />

flooded element so the contractor was<br />

unable to save time simply by building<br />

the tunnel from both sides at the same<br />

time. However the tunnel factory<br />

continued to produce the tunnel<br />

elements and once the flooded tunnel<br />

element had been repaired and placed<br />

in the correct position, the tow-out and<br />

construction of the rest of the tunnel<br />

elements was carried out at high<br />

speed. As a result, despite this major<br />

setback, the tunnel was constructed<br />

ahead of schedule.<br />

The Bridge<br />

For the bridge section, which connects<br />

the artificial island with the Swedish<br />

coast at Lernacken, a cable-stay<br />

design was chosen for the high bridge<br />

due to the weight of the combined<br />

railway and motorway link. The entire<br />

bridge is 7.8 km long of which the high<br />

bridge accounts for 1,092 metres. The


INFRASTRUCTURE<br />

Figure 5: Floating crane carrying deck section<br />

The cables of the high bridge are<br />

arranged in a classic harp pattern and<br />

anchored to the superstructure truss at<br />

20 metre intervals. Supported primarily<br />

on two pairs of pillar shafts the bridge is<br />

symmetrical from the centre of the<br />

navigation span. It has intermediate<br />

side span piers to limit the deflections<br />

of the 490 metre main span. Each<br />

pylon consists of twin, cast-in-situ<br />

concrete towers extending to a height<br />

of 204 metres above sea level. Cables<br />

are anchored in the pylons at 12 metre<br />

intervals. The foundations for both the<br />

pylons and the side span piers are<br />

prefabricated concrete caissons,<br />

located in the hard limestone, 14 to 17<br />

metres below sea level.<br />

490 metre long main span of the high<br />

bridge crosses the Flinte navigational<br />

channel, which is used by<br />

approximately 10 per cent of the<br />

vessels passing through Øresund. The<br />

majority of shipping passes through the<br />

Drogden navigational channel along the<br />

Danish coast.<br />

As was the case with the tunnel, a<br />

high level of prefabrication was used in<br />

the construction of the bridge. Apart<br />

from the pylons which were cast in situ,<br />

all other components – caissons, pillar<br />

shafts and bridge girders – were<br />

produced on land and transported to<br />

the bridge by the large floating crane,<br />

the ‘Svanen’. This self-propelled crane,<br />

a unique and highly versatile tool,<br />

positioned the heaviest concrete<br />

caissons and pillar shafts with great<br />

precision. For two years ‘Svanen’ made<br />

regular trips between Sundlink<br />

Contractors’ bridge factory in Malmö<br />

North Harbour and the bridge line,<br />

constructing the two approach bridges<br />

and the high bridge like a giant Lego kit.<br />

The superstructure of the bridge is a<br />

composite steel-concrete structure with<br />

truss girders. The upper deck carries<br />

the motorway and the lower deck<br />

contains the railway. The bridge is the<br />

largest of its kind in the world carrying<br />

both passenger trains, freight trains and<br />

motorway traffic.<br />

Figure 6: View of completed bridge from sea level looking towards tower<br />

ingenia<br />

27


INFRASTRUCTURE<br />

approach bridges were produced by<br />

Dragados in Cadiz in Southern Spain<br />

and subsequently towed to Sweden in<br />

pairs, complete with concrete<br />

motorway deck.<br />

The high bridge is carried by a total<br />

of 80 pairs of cables, ten in each<br />

direction from each pylon leg. Each<br />

cable consists of between 68 and 73<br />

strands. A strand consists of seven 5<br />

mm wires. The wires are galvanised,<br />

waxed and encased in plastic casing.<br />

Each cable has a tensile strength of<br />

2,000 tonnes and the combined length<br />

of all cables is about 25 km. The total<br />

weight is about 2,300 tonnes.<br />

Following the inauguration of the<br />

Øresund Fixed Link on 1 July 2000<br />

approximately 500,000 vehicles<br />

crossed the Øresund Bridge during the<br />

first month. Information about traffic<br />

and toll prices etc. can be seen at<br />

www.oeresundsbron.com. The photo<br />

files of the Øresund Bridge are available<br />

at www.bridgephoto.dk. ■<br />

ingenia<br />

28<br />

Figure 7: Side view of bridge to show cable pattern<br />

With a height of 204 metres above<br />

sea level the pylons of the Øresund<br />

Bridge are the tallest concrete<br />

structures in Sweden. The construction<br />

of the pylons began with the placing of<br />

the pylon caissons which had been<br />

cast in a dry dock in Malmö Harbour<br />

and towed to the bridge line. On top of<br />

the caissons the casting of the pylons<br />

was carried out by means of selfclimbing<br />

formwork. The entire casting<br />

process took seven to ten days for<br />

each 4 metre lift.<br />

About 4,335 m 3 of concrete went<br />

into each pylon leg – 220 m 3 per lift in<br />

the first stage and about 34 m 3 per lift<br />

near the top. The concrete was<br />

provided from a batching plant on a<br />

barge moored next to the pylon<br />

cofferdam. Each pylon leg required 800<br />

tonnes of reinforcement which was<br />

prepared in prefabricated cages, and<br />

then lifted into position. The pentagon<br />

shaped pylon legs are solid for the first<br />

17 metres and hollow above that level.<br />

The reinforcement cages for the<br />

cross beams, which connect the pylon<br />

legs approximately 45 metres above<br />

sea level, were built ashore, then lifted<br />

into position for casting. Steel anchor<br />

boxes were also cast into the pylon<br />

legs, to which the cables are attached.<br />

The eight bridge girders for the high<br />

bridge were produced at Karlskrona<br />

shipyard on the East coast of Sweden<br />

and then towed to Malmö, where the<br />

concrete motorway deck was added.<br />

The forty-nine girders for the two<br />

Main contractors on the<br />

Øresund Bridge<br />

Dredging and Reclamation<br />

Öresund Marine Joint Venture:<br />

● Per Aarselff (DK)<br />

● Ballast Nedam Dredging (NL)<br />

● Great Lakes Dredge and Dock<br />

Co. (USA)<br />

The Tunnel<br />

Øresund Tunnel Contractors:<br />

● NCC International (SE)<br />

● Dumez-GTM International (F)<br />

● John Laing (UK)<br />

● E. Pihl & Søn (DK)<br />

● Boskalis Westminster Dredging<br />

(NL)<br />

The Bridge<br />

Sundlink Contractors:<br />

● Skanska (SE)<br />

● Højgaard & Schultz (DK)<br />

● Monberg & Thorsen (DK)<br />

● Hochtief (D)<br />

The Railway<br />

Banverket Industridivisionen (SE)

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!