TECHNICAL<br />

<strong>IRSE</strong><br />

Figure 5<br />

Details of wiring in the point machine<br />

and point JB during commissioning<br />

MANPOWER PLANNING<br />

This was one of the most important<br />

aspects for the success. Proper planning<br />

was done well in advance for deployment<br />

of staff to achieve the goal of completing<br />

the changeover to new RRI system within<br />

the 24 hr. possession. All the activities<br />

involved, necessary instructions and guidelines<br />

to follow during commissioning were<br />

documented along with distribution of work<br />

to each team, mode of testing & commissioning<br />

within a specified time period.<br />

Competent signalling staff were<br />

arranged from different zonal railways in<br />

order to form a number of teams to take<br />

up work simultaneously at site for<br />

changeover of equipment, followed by<br />

testing and commissioning. Many teams<br />

were formed, viz. 12 points teams, 5 signal<br />

teams, 2 track circuit teams, 3 fringe<br />

teams, 2 crank handle teams, 1 intermediate<br />

CT rack team, 1 new relay room<br />

CT rack team, 2 new relay room teams and<br />

2 central panel teams. Each team was led<br />

by one team leader to communicate with<br />

other teams and to ensure that all guidelines<br />

were strictly followed. Each team<br />

was comprised of 4 to 5 people on<br />

average.<br />

Each team was assigned specific jobs<br />

and was provided with list of equipment to<br />

be commissioned and a change-over<br />

arrangement drawing for each item. Each<br />

and every staff member involved in the<br />

commissioning was asked to report to site<br />

sufficiently in advance and were briefed<br />

about the commissioning programme, the<br />

role of each individual and details of<br />

activities involved during changeover to<br />

new system. An extensive training<br />

including mock trial was also conducted<br />

for the benefit of each of the participant in<br />

order to make them aware of their role<br />

during commissioning and to make them<br />

conversant with the activities involved in<br />

the work allotted to them.<br />

Team Teams Equipment<br />

handled<br />

Point 12 151 point<br />

machines<br />

Activities undertaken<br />

Changeover of wiring of point machine from<br />

non-superimposed to superimposed<br />

detection and connection to new system.<br />

Signal 5 176 signals Disconnection of WAGO links connected to<br />

old system and connection of WAGO links to<br />

new system at the intermediate CT rack.<br />

Track<br />

circuit &<br />

Axle<br />

counter<br />

2 157 track<br />

circuit and<br />

10 axle<br />

counters<br />

Connection and disconnection of track<br />

circuits/axle counters as per plan and<br />

energisation of TR/AXR. Disconnection of<br />

TPR/AXPR of the old system and connection<br />

of TPR/AXPR in the new system.<br />

Fringe 3 5 fringes Changeover of fringe circuits from old to new<br />

system.<br />

Crank<br />

handle<br />

2 66 crank<br />

handles<br />

Panel 2 All<br />

trackside<br />

equipment<br />

In order to effectively plan the staff<br />

deploy-ment for commissioning, all the<br />

activities involved in commissioning were<br />

listed out and time required to complete<br />

each activity was evaluated. Trials were<br />

also conducted for trackside equipment for<br />

assessing actual time required for<br />

changeover. Accordingly, the number of<br />

staff required for that particular job was<br />

worked out. The activities undertaken<br />

during the free wheel possession are as<br />

shown in the table below:<br />

Connection of crank handle interlocking<br />

circuit to new system.<br />

To test each point, signal, track circuit, slots<br />

and crank handle from new panel after<br />

connection at site.<br />

Time<br />

taken<br />

3 hours<br />

6 hours<br />

3 hours<br />

2 hours<br />

2 hours<br />

15<br />

hours<br />

12<br />

Issue <strong>138</strong> <strong>Oct</strong>ober 2008<br />

<strong>IRSE</strong><br />

NEWS

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!