<strong>Winning</strong> <strong>the</strong> <strong>Owner's</strong> <strong>Goals</strong> <strong>for</strong><br />

<strong>the</strong> <strong>Architect</strong> <strong>Agreement</strong><br />

<strong>and</strong> Construction Contract<br />

Klehr | Harrison | Harvey | Branzburg LLP<br />

1835 Market Street<br />

Philadelphia, PA 19103<br />

Fax: 215-568-6603<br />

Gregory G. Gosfield, Esquire<br />

Real Estate <strong>and</strong> Finance<br />

Tel.: 215-569-4164<br />

Email: GGosfield@Klehr.com<br />

Peter J. Norman, Esquire<br />

Litigation<br />

Tel: 215.569-3596<br />

Email: pnorman@klehr.com<br />

THE MATERIAL USED IN THIS MANUAL IS FOR TEACHING<br />

THE PHILADELPHIA CLE SEMINAR.<br />

March 17, 2011


1. OVERVIEW<br />

<strong>Winning</strong> <strong>the</strong> <strong>Owner's</strong> <strong>Goals</strong> <strong>for</strong> <strong>the</strong> <strong>Architect</strong> <strong>Agreement</strong><br />

<strong>and</strong> Construction Contract<br />

1.1 Development Team<br />

1.1.1 Owner<br />

1.1.1.1 Attorney – structures <strong>and</strong> describes legal relationships among<br />

team members<br />

1.1.1.2 Financial Analyst – models <strong>the</strong> project, matches sources <strong>and</strong><br />

operating revenue/expenses<br />

1.1.1.3 Insurance Consultant – manages risks of losses due to casualty,<br />

general negligence, professional negligence, contractual liability<br />

1.1.2 Diligence Providers<br />

1.1.2.1 Title Insurer – right of third parties with interests in <strong>the</strong> l<strong>and</strong><br />

1.1.2.2 L<strong>and</strong> Use/Zoning Analyst -<br />

1.1.3 Owner’s Construction Representative (Owner’s representative or<br />

Construction Manager) – eyes, ears <strong>and</strong> intelligence <strong>for</strong> owner who is blind,<br />

deaf <strong>and</strong> dumb<br />

1.1.4 Design Team<br />

1.1.4.1 <strong>Architect</strong> – Design; L<strong>and</strong>scape; <strong>and</strong> Interior Designer –<br />

appearance<br />

1.1.4.2 Engineer – Structural; Environmental; Mechanical Electrical<br />

Plumbing - (MEP); Geotechnical; Lighting; <strong>and</strong> Acoustic -<br />

functionality<br />

1.1.5 Construction Team<br />

1.1.5.1 Construction Manager -At Risk” –<br />

1.1.5.1.1 The Contractor with whom <strong>the</strong> Owner enters into a<br />

contract;<br />

1.1.5.1.2 Is responsible <strong>for</strong> <strong>the</strong> overall administration of <strong>the</strong><br />

Project; <strong>and</strong><br />

1.1.5.1.3 enters into subcontracts with all of <strong>the</strong><br />

Subcontractors <strong>and</strong>/or Suppliers<br />

PHIL1 1391462-1 03/17/2011 10:51 AM


1.1.6 Funders<br />

1.1.7 Regulators<br />

1.1.5.2 Construction Manager “Not at Risk” –<br />

1.1.5.2.1 The Contractor with whom <strong>the</strong> Owner enters into a<br />

contract;<br />

1.1.5.2.2 Is responsible <strong>for</strong> <strong>the</strong> overall administration of <strong>the</strong><br />

Project; but<br />

1.1.5.2.3 does not enter into subcontracts with all of <strong>the</strong><br />

Subcontractors <strong>and</strong>/or Suppliers<br />

1.1.5.3 “General Contractor” – Usually means a CM that is also<br />

supplying some of <strong>the</strong> working labor <strong>for</strong> <strong>the</strong> project <strong>and</strong> may<br />

hire subcontractors <strong>and</strong>/or trades. May or may not be<br />

responsible <strong>for</strong> administration <strong>and</strong> coordination of <strong>the</strong> work.<br />

1.1.5.4 Subcontractors/Trade – specialty – work<br />

1.1.6.1 Lenders – Partial source of funds<br />

1.1.6.1.1 Equity paid first<br />

1.1.6.1.2 Assignment of Contracts, Permits <strong>and</strong> Design – who<br />

pays amount pre-dating assignment<br />

1.1.6.1.3 Inspection timing<br />

1.1.6.1.4 Approval of Change Order <strong>and</strong> Contract Document<br />

Amendments<br />

1.1.6.1.5 Notice or Consent Requirements<br />

1.1.6.2 Investors –<br />

1.1.6.2.1 Change Orders: Time, Sum, Scope<br />

1.1.6.2.2 Major Events: Budget, Personnel<br />

1.1.6.2.3 Takeover<br />

1.1.7.1 Local law – zoning variance; building permits; l<strong>and</strong> use<br />

conditions; development agreements with escrows; highway<br />

permits; utility availability; capacity (water treatment; storm<br />

water)<br />

PHIL1 1391462-1 03/17/2011 10:51 AM 2


1.2 Project<br />

1.1.8 End Users<br />

1.1.7.2 Specialty long lead items – environmental removal, caps;<br />

planned community warranties <strong>and</strong> disclosure<br />

1.1.8.1 Tenants –<br />

1.1.8.1.1 Build to suit<br />

1.1.8.1.2 Plans <strong>and</strong> specifications approvals, timing <strong>and</strong> defects<br />

1.1.8.1.3 Completion risk – move in liquidated damages<br />

1.1.8.2 Purchasers –<br />

1.1.8.2.1 Take out funds<br />

1.1.8.2.2 Buy-sell<br />

1.1.9 Brokers – Mortgage; Sale; Lease<br />

1.1.10 Payment <strong>and</strong> Per<strong>for</strong>mance Bond Surety –<br />

1.2.1 Location <strong>and</strong> local issues<br />

1.2.1.1 Entitlement/approval process;<br />

1.2.1.2 Vehicle <strong>and</strong> pedestrian access;<br />

1.2.1.3 Sight lines <strong>and</strong> signage;<br />

1.2.1.4 Mechanics liens;<br />

1.2.1.5 Contractor <strong>and</strong> Subcontractor lanes<br />

1.2.2 Project Description with Alternates: improvements; open space<br />

1.2.3 Special Uses/Approvals:<br />

1.2.3.1 Food (h<strong>and</strong>ling <strong>and</strong> disposal);<br />

1.2.3.2 Liquor;<br />

1.2.3.3 Medical assistance;<br />

1.2.3.4 High rise (staging vertical staging areas);<br />

1.2.3.5 Off-street curbcuts/decelaration/traffic lights; canopies;<br />

PHIL1 1391462-1 03/17/2011 10:51 AM 3


1.3 Contract Time<br />

1.2.3.6 Signage;<br />

1.2.3.7 Storm water;<br />

1.2.3.8 Lighting;<br />

1.2.3.9 Solar/geo<strong>the</strong>rmal power.<br />

1.3.1 Substantial Completion/Final Completion:<br />

1.3.2 Delay<br />

1.4 Indemnification<br />

1.3.1.1 certificate of occupancy – temporary, conditional, appealable,<br />

partial (base building/third party premises);<br />

1.3.1.2 third party certification – owner/ owner representative,<br />

architect, lender construction monitor; move-in/turnover ready;<br />

furniture fixtures <strong>and</strong> equipment, cabling<br />

1.3.2.1 Force majeure including wea<strong>the</strong>r conditions: st<strong>and</strong>ard of<br />

“outside” control – actual, reasonable, local peer st<strong>and</strong>ard;<br />

exclusions – monetary issues (fiscal melt down), unseasonable<br />

wea<strong>the</strong>r beyond a fixed period of time.<br />

1.3.2.2 Owner or Contractor Delay: recovery schedule mitigation.<br />

1.4.1 Indemnity <strong>for</strong> Project related claims<br />

1.4.2 No indemnity <strong>for</strong> indemnitee’s negligence<br />

1.4.3 Indemnity caps, floors (minimum “deductible”), tipping point (full coverage<br />

upon achieving a threshold amount).<br />

1.4.4 Indemnitor conditions: Notice sufficient to allow response; current<br />

updates; indemnitee marshalling; indemnitee’s co-operation; indemnitee’s<br />

non-interference <strong>and</strong> non-impairment<br />

1.5 Insurance<br />

1.5.1 General Liability<br />

1.5.2 Professional Liability<br />

1.5.3 Insurer of A Rating by Best<br />

1.5.4 Primary <strong>and</strong> non-contributory<br />

PHIL1 1391462-1 03/17/2011 10:51 AM 4


1.5.5 Owner as additional insured except professional liability<br />

1.5.6 Elimination of Owner as fiduciary <strong>for</strong> insurance proceeds.<br />

1.5.7 Increase <strong>Architect</strong>’s insurance if recourse is limited to fee plus insurance<br />

1.6 Liability:<br />

1.6.1 Breach of contract, gross negligence, violation of law, breach of third party<br />

contracts <strong>and</strong> warranties.<br />

1.6.2 Carve out <strong>for</strong> contributory acts leading to liability<br />

1.6.3 Limitations of liability: consequential damages, punitive damages, Fee paid<br />

plus insurance coverage available<br />

1.7 Dispute Resolution<br />

1.7.1 Mediation – adverse no consequences <strong>for</strong> stalemate<br />

1.7.2 Arbitration – triggered damages are below substantial threshold, compels<br />

resolution, “private”<br />

1.7.2.1 No injunctive relief<br />

1.7.2.2 All necessary parties may not be available<br />

1.7.2.3 No subpoena power<br />

1.7.2.4 No compulsion <strong>for</strong> discovery<br />

1.7.2.5 En<strong>for</strong>ceable by stipulations to court order<br />

1.7.2.6 No equivalent to contempt <strong>for</strong> violation of injunctive relief<br />

1.7.2.7 No breach of attorney-client privilege<br />

1.7.2.8 Three valuations: third is followed<br />

1.7.2.8.1 Average of two closest<br />

1.7.2.8.2 Average of three<br />

1.7.2.9 Baseball – no discretion, must choose <strong>the</strong> one “closest to<br />

correct”<br />

1.7.3 Litigation: expensive, rules of civil procedure, procedural delay, public<br />

1.8 Termination /Suspension<br />

PHIL1 1391462-1 03/17/2011 10:51 AM 5


1.8.1 For cause – pay <strong>for</strong> work to date less additional costs incurred in<br />

anticipation of complete work<br />

1.8.2 For convenience – pay <strong>for</strong> work to date plus a portion of lost future profit<br />

not general conditions. Maybe overhead.<br />

1.8.3 Contractor Remedies<br />

1.8.3.1 Limitation of damages <strong>for</strong> Owner termination <strong>for</strong> convenience<br />

1.8.3.2 Limitation of claims against Owner <strong>for</strong> concealed conditions<br />

1.8.3.3 Limitation on Contractor right to seek additional time<br />

1.8.4 Owner Remedies<br />

1.8.4.1 Delay Damages measured by a per diem fixed charge plus direct<br />

costs of substitute asset.<br />

1.8.4.2 Owner right to cure: a suspension of work <strong>for</strong> events outside of<br />

Contractor’s control be<strong>for</strong>e Contractor can terminate; separate<br />

Owner <strong>for</strong>ces interference; <strong>Architect</strong>’s obstruction or delay<br />

1.8.4.3 who pays <strong>and</strong> how if “contributory”<br />

1.9 Promotional Material: Restrictions on Contractor of using Owner <strong>and</strong> <strong>the</strong> Project in<br />

promotional material<br />

2. OWNER REPRESENTATIVE CONTRACT<br />

2.1 Services – describe scope of activity as to Work, duration<br />

2.2 Fee – profit <strong>and</strong> costs <strong>for</strong> percentage of work per<strong>for</strong>med through completion or<br />

earlier termination <strong>for</strong> owner’s convenience<br />

2.3 Reimbursables – list <strong>and</strong> cap<br />

2.3.1 Third party dispute resolution: background issues of document production,<br />

deposition, trial, travel.<br />

2.3.2 Over time or outside of business hours<br />

2.4 Termination:<br />

2.4.1 Transition services<br />

2.4.2 Mitigation of expenses <strong>for</strong> demobilization<br />

2.5 Assignment:<br />

PHIL1 1391462-1 03/17/2011 10:51 AM 6


2.5.1 Owner Representative : key staff – no assignment, severance, removal or<br />

substitution<br />

2.5.2 Owner – interests assignable to (i) affiliate, (ii) buyer of stock or (iii) assets;<br />

no release from liability<br />

2.6 No impairment:<br />

2.6.1 confidentiality<br />

2.6.2 independent contractor not agent<br />

2.6.3 no conflict of interest<br />

3. ARCHITECT’S AGREEMENT<br />

3.1 Basic Services – number of visits, attendance at construction meetings.<br />

3.1.1 Usual <strong>and</strong> customary structural, mechanical, electrical engineering services,<br />

interior design.<br />

3.1.2 Specifically:<br />

3.2 Additional Service -<br />

3.1.2.1 Programming<br />

3.1.2.2 L<strong>and</strong>scape design<br />

3.1.2.3 <strong>Architect</strong>ural Interior Design (B252-2007<br />

3.1.2.4 As-Designed Record drawings<br />

3.1.2.5 Post occupancy evaluation<br />

3.1.2.6 Coordination of Owner’s consultants<br />

3.1.2.7 Telecommunications/data design<br />

3.1.2.8 LEED® Certification (B214-2007)<br />

3.1.2.9 Value Analysis (B204-2007)<br />

3.2.1 Multiple preliminary designs<br />

3.2.2 Measured drawings<br />

3.2.3 Existing facilities surveys<br />

3.2.4 Site Evaluation <strong>and</strong> Planning (B203-2007)<br />

PHIL1 1391462-1 03/17/2011 10:51 AM 7


3.2.5 Building in<strong>for</strong>mation modeling<br />

3.2.6 Civil Engineering<br />

3.2.7 Detailed cost estimating<br />

3.2.8 On-site project<br />

3.2.9 Con<strong>for</strong>med construction documents<br />

3.2.10 As-Constructed Record drawings<br />

3.2.11 Facility Support Services (B210-2007)<br />

3.2.12 Acoustics engineering services<br />

3.2.13 Security Evaluation <strong>and</strong> Planning (B206-2007)<br />

3.2.14 Commissioning (B211-2007)<br />

3.2.15 Extensive environmentally responsible design<br />

3.2.16 Fast-track design services<br />

3.2.17 Historic Preservation (B205-2007)<br />

3.2.18 Furniture, Furnishings, <strong>and</strong> Equipment Design (B253-2007)<br />

3.2.19 Elevator Consultant<br />

3.3 <strong>Architect</strong> Power <strong>and</strong> Duty – The engagement of an Owner Representative or<br />

Construction Manager does not reduce <strong>Architect</strong>’s powers or duties<br />

3.4 Services Duration – Substantial Completion; Final Completion; Warrant Period<br />

3.5 Fee – percent; broken down <strong>for</strong> services<br />

3.6 Instruments of Service: Ownership of design - non-exclusive license<br />

3.6.1 Typically – any drawings, sketches, plans issued by <strong>Architect</strong> or <strong>the</strong> design<br />

team on Project.<br />

3.6.2 <strong>Architect</strong> does not want to design one McDonalds, <strong>and</strong> see <strong>the</strong> Owner use<br />

same design <strong>for</strong> o<strong>the</strong>r projects<br />

3.6.3 Owner wants broad license to use from <strong>Architect</strong> <strong>and</strong> its consultants<br />

3.6.4 Need <strong>for</strong> Dispute Provision – So Owner can retain license <strong>and</strong> use <strong>for</strong><br />

Project even if in dispute with <strong>Architect</strong> – escrow?<br />

PHIL1 1391462-1 03/17/2011 10:51 AM 8


3.6.5 Limited to Project<br />

3.6.6 Upon termination or payment in full, permanent <strong>and</strong> irrevocable, or at least<br />

waives of claims <strong>for</strong> use;<br />

3.6.7 Indemnity <strong>and</strong> release of old architect <strong>for</strong> use or misuse of Instruments;<br />

3.6.8 Distinguish ownership of materials between Project Documents which are<br />

Owner’s, <strong>and</strong> proprietary documents which remain owned by <strong>the</strong> generator<br />

3.7 Indemnity, Insurance –<br />

3.7.1 Insurance on professional liability - not name Owner as additional insured<br />

3.7.2 Project specific;<br />

3.7.3 Five-year tail if “claims made”<br />

3.8 Pre-Design Work:<br />

3.8.1 site conditions known or reasonably knowable; constructability/inferability;<br />

3.8.2 site preparation – inspection; demolition;<br />

4. CONTRACTOR’S CONTRACT<br />

4.1 Contract Sum<br />

4.1.1 Stipulated Sum<br />

4.1.2 Cost of Work <strong>and</strong> Fee – Owner risk of Contractor inefficiency; caps or preapprovals;<br />

narrow scope.<br />

4.1.3 GMP – Savings to Owner/Contractor; movement among line items;<br />

contingency<br />

4.1.4 Change Order – Caps on overhead <strong>and</strong> profit as percentage of change,<br />

4.1.5 Overhead – The indirect costs associated with providing <strong>and</strong> maintaining<br />

<strong>the</strong> work: office personnel, office rent, sales <strong>and</strong> advertising.<br />

4.1.6 General Conditions – Costs related to job site conditions :trailers,<br />

temporary heat, water <strong>and</strong> o<strong>the</strong>r utility consumption, toilets <strong>and</strong> hygiene<br />

faculties.<br />

4.1.7 Contractor Fee:\ – Profit, but sometimes <strong>the</strong> combined general conditions,<br />

overhead, <strong>and</strong> profit. Sometimes a contractor will negotiate to exclude<br />

general conditions from retainage as <strong>the</strong> costs are not from subcontractors<br />

or o<strong>the</strong>r hard cost providers.<br />

PHIL1 1391462-1 03/17/2011 10:51 AM 9


4.1.8 Caps on general conditions<br />

4.1.9 Owner or Contractor Delay – Costs of general conditions or overhead<br />

4.1.10 Alternates <strong>for</strong> add or subtract work – Lighting packages savings; exclusions<br />

to “equal or better” materials;<br />

4.1.11 Allowances <strong>for</strong> additional work, substitute work, or projected work not yet<br />

priced – Monument signage; fascia signage; audio/visual package; specific<br />

identified finish not yet priced<br />

4.1.12 Unit Prices <strong>for</strong> increase or decrease in <strong>the</strong> amount of a work component –<br />

Per outlet, per ceiling fan; per sprinkler<br />

4.2 Qualifications, Assumptions, Conditions<br />

4.2.1 Basis <strong>for</strong> overhead <strong>and</strong> general conditions.<br />

4.2.2 Concealed conditions:<br />

4.2.2.1 nei<strong>the</strong>r known nor reasonably discoverable (could, should,<br />

would reasonably/likely/any professional) – underground rock;<br />

4.2.2.2 utilities;<br />

4.2.2.3 contaminated soils; testing <strong>and</strong> inspection; unrenovated sections<br />

4.2.3 Third Party approvals/disapprovals.<br />

4.2.4 Temporary <strong>and</strong> ancillary work: sight screens; access;<br />

4.2.5 Order of prevailing documents. The Owner needs to be sure <strong>the</strong> specifics<br />

take precedence over <strong>the</strong> general.<br />

4.3 Pre-construction Work:<br />

4.3.1 site conditions known or reasonably knowable; constructability/inferability;<br />

4.3.2 site preparation – inspection; demolition;<br />

4.3.3 debris removal.<br />

4.4 Phasing: Rolling Occupancy:<br />

4.4.1.1 work hours;<br />

4.4.1.2 work noise;<br />

4.4.1.3 dust <strong>and</strong> debris containment;<br />

PHIL1 1391462-1 03/17/2011 10:51 AM 10


4.4.1.4 fences;<br />

4.4.1.5 truck schedules;<br />

4.5 Application <strong>for</strong> Payment<br />

4.5.1 Timing:<br />

4.4.1.6 finish work <strong>and</strong> topping<br />

4.5.1.1 5 days be<strong>for</strong>e <strong>the</strong> end of month Contractor delivers a proposed<br />

“pencil” application with back up sufficient to satisfy Owner<br />

<strong>and</strong> its lenders <strong>and</strong> o<strong>the</strong>r superior third parties, such as<br />

franchisor, ground l<strong>and</strong>lord, etc. (“Capital Providers”).<br />

4.5.1.2 Owner convenes review with Contractor, <strong>Architect</strong>, <strong>and</strong> Capital<br />

Providers.<br />

4.5.1.3 Owner, itself or through <strong>Architect</strong>, accepts or rejects by <strong>the</strong><br />

fifth of <strong>the</strong> month<br />

4.5.1.4 Contractor resubmits acceptable Application<br />

4.5.1.5 Payment with next disbursement by Capital Provider<br />

4.5.2 Qualification Requirements:<br />

4.5.2.1 Work per<strong>for</strong>med (no estimates or projections); materials stored<br />

on site subject to qualifying with required conditions; materials<br />

stored offsite if <strong>for</strong> long lead items (steel; prefab concrete;<br />

custom windows)<br />

4.5.2.2 Partial lien releases from Contractor <strong>and</strong> all Subcontractors<br />

conditioned on being paid<br />

4.5.2.3 No change in future work<br />

4.5.2.4 Certified payroll <strong>and</strong> o<strong>the</strong>r required submissions in <strong>the</strong> case of<br />

public stimulus money (FTE head count, MWBE, Steel, etc.)<br />

4.6 Progress Payment Authorizations<br />

4.6.1 Owner or Owner Representative to administer – may be more motivated<br />

than <strong>Architect</strong><br />

4.6.2 <strong>Architect</strong> – could cause delay or conflict to Owner’s detriment<br />

4.6.3 Independent right of Owner to withhold approval of an Application <strong>for</strong><br />

Payment<br />

PHIL1 1391462-1 03/17/2011 10:51 AM 11


4.6.4 Owner right of set-off <strong>for</strong> payments due from Contractor which have not<br />

been made.<br />

4.7 Retainage<br />

4.7.1 On all payments: exclude retainage on “general conditions”; built in to <strong>the</strong><br />

case of milestone; completion,<br />

4.7.2 Through job to (i) 50% Completion, (ii) Substantial or (iii) Final<br />

Completion<br />

4.7.3 Step down from 10% to 5% : disburse retainage to 5% <strong>and</strong> <strong>the</strong>reafter retain<br />

only 5%, or suspend fur<strong>the</strong>r retainage after 10% is retained <strong>for</strong> 50% of <strong>the</strong><br />

job<br />

4.7.4 Releases on line item completion: early subcontractors such as demo <strong>and</strong><br />

caissons do not have to wait <strong>for</strong> final topping of <strong>the</strong> driveway<br />

4.7.5 Punchlist of only cosmetic work with a scheduled budget at Final<br />

Completion <strong>and</strong> holdback of 150-200% of estimated cosmetic work<br />

4.8 Releases <strong>and</strong> Lien Waivers<br />

4.8.1 Partial Lien Waivers <strong>and</strong> Release of Claims<br />

4.8.1.1 Submitted with every monthly payment application<br />

4.8.1.2 By Contractor, Subcontractors, Suppliers, <strong>Architect</strong>s <strong>and</strong><br />

Engineers – anyone working on your project<br />

4.8.1.3 Limits Owner’s exposure at end of Project<br />

4.8.1.4 Valid under PA law to release lien rights<br />

4.8.2 Final Lien Waivers <strong>and</strong> Release of Claims<br />

4.8.2.1 Submitted with <strong>the</strong> final Application <strong>for</strong> Payment by Contractor<br />

4.8.2.2 By Contractor, Subcontractors, Suppliers, <strong>Architect</strong>s <strong>and</strong><br />

Engineers – anyone working on your project<br />

4.8.2.3 Valid under PA law to Bar future lien claims<br />

4.8.2.4 More certainty as to Final Payment<br />

4.8.2.5 Should be unconditional from all subs <strong>and</strong> suppliers, <strong>and</strong> may<br />

be conditional from Contractor<br />

4.8.3 Final Payment “Float” issue<br />

PHIL1 1391462-1 03/17/2011 10:51 AM 12


4.8.3.1 It is <strong>the</strong> best practice <strong>for</strong> <strong>the</strong> Owner to pay <strong>the</strong> Contractor <strong>for</strong><br />

“payments made” to subcontractors <strong>and</strong> suppliers, not<br />

“incurred”.<br />

4.8.3.1.1 Owner should get benefit of any deals cut between<br />

Contractor <strong>and</strong> its subs<br />

4.8.3.2 Accordingly, it should be <strong>the</strong> responsibility of <strong>the</strong> Contractor to<br />

make <strong>the</strong> final payments of retainage to <strong>the</strong> Owner <strong>and</strong> <strong>the</strong>n<br />

turn around <strong>and</strong> seek reimbursement from <strong>the</strong> Owner <strong>for</strong> <strong>the</strong>se<br />

costs.<br />

4.8.3.3 Typical Contract language:<br />

4.8.3.3.1 Contractor having furnished evidence satisfactory to<br />

<strong>the</strong> Owner that all subcontractors <strong>and</strong> suppliers have<br />

been paid <strong>and</strong> that <strong>the</strong>re are no claims, obligations or<br />

liens outst<strong>and</strong>ing <strong>for</strong> labor, services, materials,<br />

equipment, taxes or o<strong>the</strong>r items per<strong>for</strong>med furnished<br />

or incurred <strong>for</strong> or in connection with <strong>the</strong> Work<br />

4.8.3.4 Reduces suits against Owner by Subcontractors <strong>and</strong> Suppliers<br />

by abrogating Contractor’s “pay-if-paid” language.<br />

4.8.3.5 Note – Can result in major pushback from Contractors<br />

4.8.4 No waiver by General contractor<br />

4.8.5 Waiver by subcontractor<br />

4.8.6 Bonds<br />

4.8.7 Contract summary<br />

4.8.8 Construction loan exemption<br />

4.8.9 Permanent loan not exempt<br />

4.9 Contractor Services<br />

4.9.1 “Work” under Contract Documents<br />

4.9.1.1 Reasonably inferable - Work includes matters that are<br />

reasonably inferable as part of <strong>the</strong> work. For example, if <strong>the</strong><br />

Contractor is installing a machine into a building system, it is<br />

reasonably inferable that <strong>the</strong> Contractor must include <strong>the</strong> tubes<br />

<strong>and</strong> wires necessary to make <strong>the</strong> connection, even if <strong>the</strong>y are<br />

not all identified with specificity.<br />

PHIL1 1391462-1 03/17/2011 10:51 AM 13


4.9.1.2 Constructability from known or reasonably knowable<br />

conditions - Contractor must make independent determination<br />

of Constructability <strong>and</strong> that can it be achieved within <strong>the</strong><br />

Contract Time <strong>and</strong> Contract Sum<br />

4.9.1.3 Compliance with laws applicable to Work (materials, building<br />

code requirements)<br />

4.9.1.4 Contractor or Subcontractor should be responsible <strong>for</strong> loss due<br />

to <strong>the</strong> non-compliance of <strong>the</strong> Work required under <strong>the</strong> Plans<br />

<strong>and</strong> Specifications to meet applicable public <strong>and</strong> private code<br />

requirements applicable to that portion of <strong>the</strong> work – wrong<br />

slope of sewer pipe<br />

4.9.1.5 Contractor will exercise pro-active diligence in coordinating<br />

work where latent issues are more likely<br />

4.9.1.6 Contractor’s design work, if any, must be equal to <strong>the</strong><br />

<strong>Architect</strong>’s st<strong>and</strong>ard.<br />

4.9.2 Supervisor – means <strong>and</strong> methods<br />

4.9.2.1 Labor harmony – except unrest as part of national actions,<br />

Owner’s separate <strong>for</strong>ces<br />

4.9.2.2 Manufacturer recommendations, not just requirements<br />

4.9.2.3 Remove workers <strong>for</strong> bad acts: sexual or racial harassment; drug,<br />

alcohol, or weapons; disruptiveness; trespassing<br />

4.9.3 Update <strong>for</strong> Change Orders with Owner consent to Schedule of Time,<br />

Schedule of Values, Schedule of Subcontractors, all Contract Exhibits<br />

4.9.4 Clean-up daily if in occupied area<br />

4.9.5 Turnover: warranties, manuals, final as-builts, marked-up as builts, by both<br />

Contractor <strong>and</strong> Subcontractor<br />

4.9.6 Delivery to Owner of (i) as-built CADs <strong>and</strong> PDFs as well as (ii) operations<br />

<strong>and</strong> maintenance manuals as a condition of Final Payment to Contractor.<br />

4.9.7 Environmental: No exacerbation of distressed environmental condition.<br />

4.9.8 Contractor will be responsible <strong>for</strong> maintaining current records of<br />

construction changes <strong>and</strong> turning over final showing changes from prior<br />

versions <strong>and</strong> will conduct frequent site meetings of critical path participants<br />

4.9.9 Subcontracts must be subject to a three bid program, <strong>and</strong> after approved<br />

subcontracts, substitution is subject to Owner approval<br />

PHIL1 1391462-1 03/17/2011 10:51 AM 14


4.9.10 Contractor shall keep a current contact list of Subcontractors<br />

4.10 Owner Rights<br />

4.11 Bonds<br />

4.10.1 All work, whe<strong>the</strong>r major or minor must be approved by <strong>the</strong> Owner first;<br />

<strong>the</strong> <strong>Architect</strong> has certification duty but no approval right.<br />

4.10.2 Contractor shall maintain labor harmony, except <strong>for</strong> non-Project specific<br />

work unrest<br />

4.10.3 Deflective Works: Supervise - accept <strong>and</strong> reject per<strong>for</strong>mance<br />

4.10.4 Corrective work, prior to Substantial Completion; warranty work after<br />

Substantial Completion<br />

4.10.5 Suspend work <strong>for</strong> Contractor failure at Contractor’s cost<br />

4.10.6 Compel more workers if behind schedule to meet a Recovery Schedule<br />

4.10.7 Hire separate contractors <strong>for</strong> separate work on a “harmonious” basis<br />

4.10.8 Administration of Contract with <strong>Architect</strong>’s input/approval<br />

4.10.8.1 Interpret Contract terms, reject work<br />

4.10.8.2 No change without a Change Order signed by Owner<br />

4.10.8.3 Construction Change Directive by Owner without Contractor<br />

consent, disputes resolved by dispute resolution<br />

4.10.9 Owner, assignee has no obligation under Subcontracts until <strong>the</strong>y are<br />

assigned, <strong>and</strong> <strong>the</strong>y are to be assigned upon notice from Owner<br />

4.10.10 Owner, not <strong>Architect</strong>, is in charge of <strong>the</strong> Change Order process<br />

4.10.11 Owner has approval rights over changes in Contractor’s key personnel on<br />

<strong>the</strong> Project<br />

4.10.12 Pre-approve changes in work <strong>for</strong>ce <strong>and</strong> in Project Superintendent’s of<br />

Contractor <strong>and</strong> subcontractor<br />

4.11.1 Per<strong>for</strong>mance Bond – For benefit of Owner to Guaranty that Project will be<br />

completed <strong>for</strong> Contract Balance<br />

4.11.2 Payment Bond – For benefit of Subcontractors <strong>and</strong> Suppliers, <strong>the</strong> guaranty<br />

that once Owner has made payment to Contractor, <strong>the</strong> Subcontractors <strong>and</strong><br />

Suppliers who worked on <strong>the</strong> Project will be paid<br />

PHIL1 1391462-1 03/17/2011 10:51 AM 15


4.11.3 More certainty <strong>for</strong> Owner (or Lender) on capping project costs<br />

4.11.4 Lessens any potential lien filings on Project by Subcontractors- Suppliers<br />

4.11.5 Provides <strong>the</strong> Owner with better leverage in case of dispute with Contractor<br />

4.11.6 Bond Costs<br />

4.11.6.1 Part of Contractor’s Bid Cost<br />

4.11.6.2 No Extra Costs <strong>for</strong> both Per<strong>for</strong>mance Bond <strong>and</strong> Payment Bond<br />

– st<strong>and</strong>ard to be in same package<br />

4.11.6.3 Contractor’s Bonding Capacity is what is important – No real<br />

costs incurred if adding Project that is still below total bonding<br />

cap imposed by Bond Co.<br />

4.11.6.4 Typically Charges <strong>for</strong> Payment <strong>and</strong> Per<strong>for</strong>mance Bond <strong>for</strong><br />

qualified Contractors – ½ to 1% of construction cost <strong>for</strong><br />

Project<br />

4.11.7 Bonding Red Flags<br />

4.11.7.1 Strange Bond Company – Limit issues <strong>and</strong> denials<br />

4.11.7.2 See Pa. Insurance Department website<br />

4.11.7.3 Contractor “doesn’t do bonded work”<br />

4.11.7.4 Why? Usually financial problems/history<br />

4.11.7.5 Excessive Bond Costs<br />

4.11.7.6 2% or above, Contractor is ei<strong>the</strong>r a financial risk or is greedy<br />

4.11.7.7 “Individual Surety” – Run. Run away fast.<br />

4.11.7.8 Contractor – “We require our subcontractors to obtain bonds”<br />

4.11.7.9 Added Costs are usually 2 to 6% of each subcontracts costs<br />

4.11.7.10 Does not protect against Subcontractors/Suppliers filing<br />

mechanic’s liens<br />

4.11.7.11 O<strong>the</strong>r “Insurance Products” – available but<br />

4.11.7.12 Do not protect against Subcontractor/Suppliers filing<br />

mechanic’s liens<br />

PHIL1 1391462-1 03/17/2011 10:51 AM 16


4.11.7.13 Note- a Bond is not “Letter of Credit” or “Cash” – merely a<br />

contractual obligation of a supposedly responsible insurance<br />

company to pay <strong>for</strong> your losses<br />

4.12 Warranty<br />

4.12.1 Assignment to Owner<br />

4.12.2 Starts at Substantial Completion, Final Completion,<br />

4.12.3 Contractor shall en<strong>for</strong>ce <strong>the</strong> warranties, be responsible <strong>for</strong> loss if a warranty<br />

item is rejected, <strong>and</strong> conduct an end of warranty walk through like <strong>the</strong> one<br />

at Final Completion. Warranty “walk-through” prior to expiration of<br />

contractor warranty<br />

PHIL1 1391462-1 03/17/2011 10:51 AM 17