Autodesk Consulting Project Management Office<br />
Meeting Minutes<br />
Customer<br />
Project<br />
Date & Time<br />
Location<br />
Angkasa Pura II<br />
BIM Implementation for APII<br />
06-March-2014<br />
AP2 office – Jakarta, Indonesia + Conf. Call AT&T<br />
Invitees Attendees Apologies<br />
Mr. Bima Boediman (Pak Bima) – AP2<br />
Mr. Herwanto Budi S (Pak Herwanto) –<br />
AP2<br />
Mr. Rohit Deshmukh – Autodesk<br />
Mr. Toshio Shoko – Autodesk<br />
Mr. Dipankar Mondal – Autodesk<br />
Mrs. Linda Tulung – Autodesk<br />
Mr. Eddie Cendana (Pak Eddie) – EDP<br />
Media<br />
Mr. Leroy N S (Roy) – EDP Media<br />
Mr. Bima Boediman (PB)<br />
Mr. Herwanto Budi S (PH)<br />
Mr. Toshio Shoko (TS)<br />
Mr. Dipankar Mondal (DM)<br />
Mr. Eddie Cendana (PE)<br />
Mr. Leroy N S (Roy)<br />
Mr. J. Weni (PW)<br />
Mrs. Linda Tulung<br />
Mr. Rohit Deshmukh<br />
1 Actions from previous meeting:<br />
S.No. Description Owner Estimated Closure Date<br />
<strong>1.</strong> Send details of the Assessment Meeting Agenda to<br />
AP2<br />
2. Advise Assessment Meeting members from AP2 side<br />
based on Item 1<br />
Toshio Shoko 21 st Feb 2014<br />
Pak Bima 26 th Feb 2014<br />
3. BUZZSAW site setup Toshio Shoko 21 st Feb 2014<br />
4. Additional hardware requirement details to AP2 Toshio Shoko 21 st Feb 2014<br />
5. Procure additional hardware for BIM Implementation<br />
based on Item 4 above<br />
Pak Bima 28 th Feb 2014<br />
6. Add Product Training dates to Phase 4: BIM for<br />
Construction and update Project Plan accordingly<br />
7. Add Project Risk for MEP Drawings and update the<br />
Steering Group presentation for next meeting<br />
Dipankar<br />
Mondal<br />
Dipankar<br />
Mondal<br />
21 st Feb 2014<br />
21 st Feb 2014<br />
8. Add Pak Weni into Steering Group Dipankar<br />
Mondal<br />
21 st Feb 2014<br />
9. Provide updated Structural Drawings Pak Bima 25 th Feb 2014<br />
2 Items for Discussion:<br />
<br />
<br />
<br />
BIM Implementation Project Summary<br />
Steering Group Announcements<br />
Project Status<br />
© Autodesk Page 1 of 3
Autodesk Consulting Project Management Office<br />
<br />
<br />
<br />
Risks<br />
Issues and Escalations<br />
Topics for Next Steering Meeting<br />
2.1 Summary of discussion<br />
DM stated the meeting, explained & discussed thought the Steering Group Slides (Refer: Appendix) to all<br />
attendees in the meeting.<br />
DM raised the “DECISION ITEM” for the Steering Group Announcement to PB. PB agreed to update on the<br />
structural drawings by 10-Mar-2014 (i.e. Monday). DM re-iterated the importance of the drawings for the<br />
progress to move ahead, also mentioned the impact of project downtime and or project schedule timelines<br />
in absence of drawings.<br />
PB agreed to the need of drawings and will send the updates as-soon-as-possible. PB confirmed that AP2<br />
team willing to stretch extra working hours to finish the project within the agreed planned time. Project<br />
schedule and end dates will remain intact (1).<br />
DM went over the Project progress, risks & issues so far and on-going activities.<br />
PB raised 2 items as below:<br />
i) Indonesia elections will be held around April-2014, exact dates are unclear as of now, project plan<br />
needs to be readjusted to accommodate the election holidays.<br />
ii) Additional new Steering Group Members will get engaged from AP2 side along with Pak Bima<br />
himself; however Pak Bima will take a back seat moving forward in the project.<br />
Below mentioned Action Items from previous discussion stands closed:<br />
S.No. Description Owner Estimated Closure<br />
Date<br />
Status<br />
<strong>1.</strong> Send details of the Assessment Meeting<br />
Agenda to AP2<br />
Toshio<br />
Shoko<br />
21 st Feb 2014 CLOSED<br />
2. Advise Assessment Meeting members<br />
from AP2 side based on Item 1<br />
Pak Bima 26 th Feb 2014 CLOSED<br />
3. BUZZSAW site setup Toshio<br />
Shoko<br />
21 st Feb 2014 CLOSED<br />
4. Additional hardware requirement details to<br />
AP2<br />
Toshio<br />
Shoko<br />
21 st Feb 2014 CLOSED<br />
5. Procure additional hardware for BIM<br />
Implementation based on Item 4 above<br />
Pak Bima 28 th Feb 2014 CLOSED<br />
6. Add Product Training dates to Phase 4:<br />
BIM for Construction and update Project<br />
Plan accordingly<br />
7. Add Project Risk for MEP Drawings and<br />
update the Steering Group presentation for<br />
next meeting<br />
Dipankar<br />
Mondal<br />
Dipankar<br />
Mondal<br />
21 st Feb 2014 CLOSED<br />
21 st Feb 2014 CLOSED<br />
8. Add Pak Weni into Steering Group Dipankar<br />
Mondal<br />
21 st Feb 2014 CLOSED<br />
2.2 Agreements<br />
The following are the list of agreements achieved during the meeting:<br />
<strong>1.</strong> All parties agreed on Project Status and its current progress<br />
© Autodesk Page 2 of 3
Autodesk Consulting Project Management Office<br />
2. All parties agreed with the existing Project Risks & Issues.<br />
3. All parties agreed with the next Steering group meeting date for 3 rd April 2014 & its topics.<br />
4. All parties agreed to the proposal and item 1 from the above section<br />
3 Actions:<br />
S.No. Description Owner Estimated Closure Date<br />
<strong>1.</strong> Provide updated Structural Drawings Pak Bima 25 th Feb 2014<br />
10 th Mar 2014<br />
2. Provide MEP Drawings Pak Bima 14 th Mar 2014<br />
3. Update the Project Schedule to incorporate<br />
Indonesia Election dates<br />
Dipankar<br />
Mondal<br />
31 st Mar 2014<br />
4 Next Meeting:<br />
Steering Group Meeting on 3 rd April 2014<br />
5 Appendix<br />
Following are the list of documents that were referenced during the meeting discussion.<br />
5.1 Steering Group Meeting presentation<br />
Steering Meeting<br />
Presentation 20140306.pdf<br />
5.2 Attendee List (signed)<br />
Attendance List<br />
20140306-onsite.pdf<br />
Attendance List<br />
20140306-onphone.pdf<br />
© Autodesk Page 3 of 3
•<br />
•<br />
•<br />
•<br />
•<br />
•<br />
•<br />
•<br />
•<br />
•<br />
•<br />
•<br />
•<br />
•<br />
•<br />
•<br />
•<br />
•<br />
•<br />
•<br />
•
•<br />
•