<strong>Newcastle</strong> <strong>Works</strong> – Major Projects<br />

Blast Furnace Reline<br />

•Tenders have been received for a number of long lead items;<br />

•Preparing detail costing and scope to get overall approval;<br />

•Reline duration planned for 100 days, starting 5 May 2014;<br />

•Attention is given to the major problem with shortage of skilled resources.<br />

Sinter Plant Reline<br />

•Preparing detail costing and scope to get overall approval;<br />

•Attention is given to the major problem with shortage of skilled resources.<br />

Steel Making<br />

•Good progress made with the Hollow Jet project.<br />

•Desulphurization plant being commissioned, many design flaws being addressed.<br />