6 - 8.9 mio. DKK.<br />

3 - 5.9 mio. DKK.<br />

PSO Funding<br />

Figure 3 illustrates the number of projects and the size of the<br />

The total amount of financial funding from the different PSO<br />

total budgets divided into four groups. It shows that 63% of the<br />

programmes affiliated with Energinet.dk from 1998-2013 is<br />

projects have received a funding amount smaller than DKK 3<br />

DKK 1,867,425,664. Every year, the programmes have a total<br />

million. A reason for this is that many of the projects are fea-<br />

of approx. DKK 150 million which they can grant qualified pro-<br />

sibility studies where the aim is to investigate, whether there<br />

jects. If the programmes do not utilise the whole budget, it is<br />

is a valid foundation for a bigger project in a given energy area<br />

possible to assign the rest of the funding to the next year. The<br />

and whether the new technological possibility is a realistic op-<br />

figure below shows the total amount of funding from 1998-<br />

portunity.<br />

2013 divided on project size.<br />

Furthermore, the second largest group with 22% is the group<br />

Figure 3<br />

The total amount<br />

of funding divided<br />

on project size<br />

Number of projects<br />

400<br />

352<br />

300<br />

of projects in the budget area of DKK 3-6 million and the third<br />

largest group is projects in the budget area of DKK 6-9 million.<br />

The last group of projects with a budget from DKK 9 million and<br />

above is only 7%, indicating that not many projects receive a<br />

relatively large amount of PSO funding. However, it is observed<br />

that there is an increase in the projects with a budget over<br />

200<br />

DKK 9 million since 2009. A reason for this can be that since<br />

2009, the programmes have increased their focus on bigger<br />

124<br />

consortium projects that demands a larger budget. The aim of<br />

100<br />

the consortium projects is to support larger projects that inclu-<br />

0<br />

44 40<br />

de different partners from all the technological development<br />

phases. This means that the aim is to support projects where<br />

the partners can execute different tasks in the technological<br />

16<br />

9 mio. DKK. and over<br />

Under 3 mio.DKK.<br />

development phases from applied research to demonstration/<br />

commercialisation.