3.1.27 risk-based inspection RBI<br />

A risk assessment and management process that is focused on inspection planning<br />

<strong>for</strong> loss of containment of pressurized equipment in processing facilities, due to<br />

material deterioration. These risks are managed primarily through inspection in<br />

order to influence the probability of failure.<br />

3.1.28 strip lining<br />

Strips of metal plates or sheets that are welded to the inside of a vessel wall.<br />

Normally, the strips are of a more corrosion-resistant or erosion-resistant alloy than<br />

the vessel wall and provide additional corrosion/erosion resistance.<br />

3.1.29 temper embrittlement<br />

The reduction in toughness due to a metallurgical change that can occur in some<br />

low alloy steels, e.g. 2 1/4Cr-1Mo, as a result of long term exposure in the<br />

temperature range of about 650 o F to 1100 o F (345 o C to 595 o C).<br />