MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION<br />

( A GOVERNMENT OF MAHARASHTRA UNDERTAKING)<br />

The quantity of bank shall be paid on the basis of quantity of road cutting used in the bank.<br />

The final quantity to be paid for under this item shall be the total quantity of bank work reduced<br />

by 1% (one percent) less than quantity to be paid for using the materials from cutting.<br />

Item No. 7.:- Watering to OMC (16 kg to 24 kg of water per Cu.M.) The earth work in<br />

embankment in 20 cm to 30 cm layers. (95% proctor density).<br />

General : The item provides watering the layers of 20 to 30 cm of embankment laid.<br />

Material <strong>and</strong> Equipment : Water to be used shall be free of harmful elements, which may<br />

cause heavy efflorescence, etc. <strong>and</strong> approved by the Engineer-in-Charge. The contractor shall<br />

make his own arrangements for getting adequate quantity of acceptable water. The water<br />

tankers shall be used, without any additional payment.<br />

Watering : When the murum of the 20 to 30 cm layer in embankment road contains less than<br />

the optimum moisture, water shall be added to the material in the embankment layers of the<br />

road to bring the moisture, uniformly up to requirement. If the material contains more than the<br />

required moisture, it shall be allowed to dry until the moisture is reduced to the required extent.<br />

If due to wet weather etc. the moisture contents of the soil cannot be reduced to the appropriate<br />

amount by exposure, the compaction shall be suspended till suitable conditions prevail without<br />

contractor’s claiming any compensation.<br />

Item to Include : All material, equipment machinery labour, taxes etc. shall be included in the<br />

rate.<br />

Mode of Measurement <strong>and</strong> Payment : The measurement shall be taken on Cum. basis of the<br />

embankment of the road watered.<br />

Item No. 8.:- Consolidation with proper ramming / rolling in layers the earth work in<br />

embankment . (95% proctor density).<br />

General : The item provides consolidation of the earthwork in embankment in 20 to 30 cm<br />

layers for 8 to 10 tonnes roller <strong>and</strong> 40 to 50 cm layers for vibratory rollers. This item is to be<br />

executed after laying the earthwork in embankment in the layers of 20 to 30 cm <strong>and</strong> the layer is<br />

watered.<br />

Equipment : The ramming rods <strong>and</strong> 8-10 tone ordinary or vibratory roller as directed shall be<br />

used.<br />

Consolidation : When a loose layer is leveled manually or mechanically with camber provided<br />

<strong>and</strong> moistened or dried to a uniform <strong>and</strong> required moisture content suitable for maximum<br />

compaction, it shall be compacted by power rollers, vibratory rollers or heavy hauling or dozing<br />

equipment to give the specified 95% of the st<strong>and</strong>ard proctor density. If on testing, the density is<br />

found to be less than 95% of the st<strong>and</strong>ard density the contractor shall do additional compaction<br />

necessary to get the specified density after adding water if required. When the specified density<br />

is imperative, the work shall be removed <strong>and</strong> redone by the contractor at his own cost to give<br />

the specified density.<br />

Proper sequence of all component operations shall be maintained to give individual progress.<br />

For compaction of embankment the road roller shall move longitudinally <strong>and</strong> rolling shall be<br />

done from edges to centre. The camber shall be provided in the cutting <strong>and</strong> shall not be<br />

Contractor.<br />

Executive Engineer,<br />

MIDC, Division Kolhapur