02.11.2012 Views

ecosign

ecosign

ecosign

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

Photo: R. O’Neill<br />

INTERVIEWS<br />

Peter Luger, project manager<br />

ISR: What were the main challenges in the implementation<br />

of the project?<br />

P. Luger: With such a mega project, there are very<br />

many constantly changing challenges. I would like<br />

to limit my remarks here to what I found to be the<br />

three biggest.<br />

Developing the project, planning the ropeway engineering and observing<br />

the work schedules: With its 3km span, a new and highly aesthetic tower<br />

design in the form of tubular lattice work, and the need for close collaboration<br />

with the management at Whistler / Blackcomb and the local planners,<br />

the project was basically one long challenge. And the nine hours time difference<br />

also helped to ensure that my working day was often very long.<br />

Collaboration with the Canadian ropeway authority (BCSA) and the individual<br />

rulings required to get the 3S system approved constituted a further<br />

challenge that needed my attention throughout. The Canadian ropeway<br />

code does not cover such an innovative and complex system as a 3S gondola.<br />

That made it necessary to submit requests for variances for all the items<br />

where the Peak 2 Peak diverges from Canada’s CAN/CSA Z98-01.<br />

On-site installation and co-ordination of the work has also been one of the<br />

main challenges in the last two years. With the help of the fantastic, highly<br />

motivated teams from Austria, Canada and Switzerland, we really rose to<br />

this challenge! The installation team leaders in particular did a superb job;<br />

I merely had to provide the support.<br />

Could you briefly describe the main phases of the work on site?<br />

Erection of towers 3 and 2 in the period from 27 August to 21 October<br />

2007. That meant we achieved our goal for the first year on site before the<br />

snows came.<br />

Installation of the terminal systems in May and June 2008. At the same<br />

time towers 1 and 4 were erected, and the finishing touches put to towers 2<br />

and 3, which are 62.5 m high. In the first five weeks, the terminal installation<br />

team from Wolfurt and Canada showed such commitment that they<br />

were able to make up for the two-week delay to the commencement of<br />

works caused by the amount of snow on the ground.<br />

Transporting the ropes from the Fatzer plant in Romanshorn to the top of<br />

Blackcomb Mountain.<br />

Rope stringing from May to September 2008. The complex preparations<br />

for stringing were performed simultaneously with installation of the terminal<br />

and line equipment. And stringing could begin the moment the first<br />

track rope arrived at the terminal. That was a real challenge for our Swiss<br />

colleagues from Garaventa, and it was handled with perfect planning and<br />

organization.<br />

Installation of the electrical systems for the Peak 2 Peak Gondola and the<br />

four evacuation gondolas from mid-June to the end of September 2008.<br />

Installation and commissioning of the evacuation systems at the end of August<br />

and beginning of September 2008.<br />

Assembly and finishing work on the 28 carriers in September.<br />

Final adjustments and internal start-up of the complete installation in<br />

October.<br />

Final inspection and approval by the authorities in November, with the<br />

whole system ready to go right on time on 15 November 2008.

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!