Dubai Electricity & Water Authority<br />
1 Introduction<br />
1 Introduction<br />
To ensure the availability of power, it is essential that the load<br />
projections, the time of power requirements and other factors<br />
from all the potential developers are available with DEWA well<br />
in advance.<br />
The purpose of this document is as follows:<br />
<br />
To provide guidelines to all the major developers and the<br />
consultants in regard to the DEWA’s power supply<br />
requirements.<br />
To assist the developers and the consultants in<br />
understanding the requirements for submissions of project<br />
/ development Master Plan documents and to facilitate the<br />
project / development power supply on time.<br />
Power Supply Guidelines for Major Projects 1 of 14 August 2009