08.11.2014 Views

Lands & Regulation - Nunavut Planning - Industry Letter

Lands & Regulation - Nunavut Planning - Industry Letter

Lands & Regulation - Nunavut Planning - Industry Letter

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

section 95 (modification or abandonment of a project) – 120 days plus a potential<br />

extension for an additional 60 days;<br />

section 105 (ministerial decision following a determination by the <strong>Nunavut</strong> Impact<br />

Review Board (NIRB) that a project should proceed) – 120 days plus a potential<br />

extension for an additional 60 days; and<br />

section 106 (ministerial decision following a determination by the NIRB that a project<br />

should not proceed) – 120 days plus a potential extension for an additional 60 days).<br />

Second, of even greater concern are the elements of the process that could last for as much as 360<br />

days, or essentially an entire year, instances of which are as follows:<br />

section 125 (ministerial decision following a determination by a federal environmental<br />

assessment panel that project should proceed) – 180 days plus a potential extension for an<br />

additional 180 days;<br />

section 126 (ministerial decision following a determination by a federal environmental<br />

assessment panel that project should not proceed) – 180 days plus a potential extension<br />

for an additional 180 days;<br />

Conversely, there are elements of the assessment and review process that, in our view, should<br />

have been the subject of timelines or timeframes, but none have been provided for. Examples<br />

include:<br />

section 99 – determination of the scope of a project by the NIRB;<br />

section 101 – development, approval and issuance of the guidelines for the preparation of<br />

an environmental and socio-economic impact statement; and<br />

sections 102 and 103 – conduct and completion of the review of the proposed project by<br />

the NIRB.<br />

We further note that subsection 92(4) authorizes the Minister to extend the 45-day period for<br />

submission of the report that the NIRB is required to submit pursuant to subsection 92(1).<br />

However, unlike other provisions that authorize an extension, subsection 92(4) does not<br />

specifically limit the number of days for which the extension can be made.<br />

Finally, we note that the words “as soon as practicable” are used in section 110, subsection<br />

112(9), subsection 120(8) and section 131. However, the draft legislation provides no further<br />

guidance as to how quickly the actions described in those sections must be completed.<br />

In our analysis, under a “worst case scenario” the timelines and timeframes that currently appear<br />

in the proposed legislation could potentially require up to 800 days in order to complete the<br />

overall impact assessment process. However, as noted above, no timelines or timeframes have<br />

been provided for a number of important steps in the overall process. Taking all of these factors<br />

into account, and having regard to past environmental assessments, experienced industry<br />

observers have suggested that, under Bill C-25, three to five years could potentially be needed to<br />

complete the assessment of a major mining project in <strong>Nunavut</strong>. While a time period of this<br />

Page 4 of 9

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!