NATIONAL CEMETERY ADMINISTRATION - <strong>MSN</strong> COST GUIDE<br />
<strong>MSN</strong> 5: Oakl<strong>and</strong> Memorial Service Network<br />
CURRENT CONSTRUCTION UNIT COSTS AS NOTED IN CHART - VALID THROUGH OCTOBER 2014<br />
USE FOR PLANNING PURPOSES ONLY - NOT FOR BUDGETING<br />
PREPARED BY: <strong>Office</strong> <strong>of</strong> <strong>Construction</strong> & <strong>Facilities</strong> Management, <strong>Cost</strong> Estimating Service (003C2C).<br />
Updated: JUNE, 2014<br />
Location<br />
P.I.C.<br />
BUILDING<br />
ADMIN.<br />
BUILDING<br />
REST<br />
ROOM<br />
MAINT.<br />
BUILDING<br />
STORAGE<br />
BUILDING<br />
COMMITTAL<br />
SHELTER<br />
PRE-<br />
PLACED<br />
CRYPTS<br />
COLUM-<br />
BARIUM<br />
MEMORIAL<br />
WALL<br />
24' ROAD<br />
W/CURB<br />
METAL<br />
FENCE IRRIGATION<br />
$/SF $/SF $/SF $/SF $/SF EA. EA. EA. $/SPACE $/LF $/LF $/ACRE<br />
Kent, WA (TACOMA, WA) $412 $335 $353 $235 $118 $470,739 $530 $588 $294 $118 $206 $47,074<br />
Portl<strong>and</strong>, OR $389 $317 $333 $222 $111 $444,487 $500 $556 $278 $111 $194 $44,449<br />
Eagle Point, OR (EUGENE, OR) $406 $331 $348 $232 $116 $464,447 $523 $581 $290 $116 $203 $46,445<br />
Dixon, CA (SACRAMENTO, CA) $451 $368 $387 $258 $129 $515,905 $580 $645 $322 $129 $226 $51,590<br />
Santa Nella, CA (SAN FRANCISCO, CA) $463 $377 $397 $264 $132 $528,990 $595 $661 $331 $132 $231 $52,899<br />
Bakersfield, CA $398 $324 $341 $227 $114 $454,528 $511 $568 $284 $114 $199 $45,453<br />
Los Angeles, CA $414 $337 $354 $236 $118 $472,600 $532 $591 $295 $118 $207 $47,260<br />
San Diego, CA $408 $333 $350 $233 $117 $466,716 $525 $583 $292 $117 $204 $46,672<br />
Phoenix, AZ $317 $258 $272 $181 $91 $362,158 $407 $453 $226 $91 $158 $36,216<br />
Ft. Richardson, AK (ANCHORAGE, AK) $518 $422 $444 $296 $148 $592,119 $666 $740 $370 $148 $259 $59,212<br />
Honolulu, HI $482 $392 $413 $275 $138 $550,635 $619 $688 $344 $138 $241 $55,064<br />
NOTES:<br />
Unit costs have been updated using the most current project data available.<br />
<strong>Cost</strong> shown are averages to be used for establishing an order <strong>of</strong> magnitude. Actual costs will vary depending on complexity <strong>and</strong> unique conditions <strong>of</strong> each project.<br />
<strong>Cost</strong>s shown are for typical <strong>NCA</strong> construction only. Additional costs to be considered include: Pre-Design allowance; escalation to contract award date; construction contingencies;<br />
technical services; impact costs; utility agreements; site improvements; site utilities; CM fees; <strong>and</strong> current local market conditions.<br />
Allow additional funds for known adverse sub-surface conditions.<br />
Allow additional funds for special construction requirements such as: phasing; unusual site constraints, tie into existing structures.<br />
Funds for Federally required Physical Security <strong>and</strong> Energy construction m<strong>and</strong>ates are NOT INCLUDED in the unit costs.<br />
Allow additional funds for compliance with VA Physical Security St<strong>and</strong>ards <strong>and</strong> Sustainability <strong>Guide</strong>lines for 5' outside <strong>of</strong> Building Envelope.<br />
Sitework <strong>and</strong> site utility costs will vary greatly for each project. Early identification <strong>of</strong> requirements is critical.<br />
For conceptual estimates on projects up to $25M, 15% added building cost is a reasonable rule <strong>of</strong> thumb for sitework <strong>and</strong> site utilities . Factor may decrease to 10% for larger projects.<br />
For additional assistance contact:<br />
estimating@va.gov<br />
Page 1 <strong>of</strong> 2
<strong>MSN</strong> 5 - Escalation Rates<br />
NATIONAL CEMETERY ADMINISTRATION - <strong>MSN</strong> COST GUIDE<br />
<strong>MSN</strong> 5: Oakl<strong>and</strong> Memorial Service Network<br />
CURRENT CONSTRUCTION UNIT COSTS AS NOTED IN CHART - VALID THROUGH OCTOBER 2014<br />
USE FOR PLANNING PURPOSES ONLY - NOT FOR BUDGETING<br />
PREPARED BY: <strong>Office</strong> <strong>of</strong> <strong>Construction</strong> & <strong>Facilities</strong> Management, <strong>Cost</strong> Estimating Service (003C2C).<br />
Updated: JUNE, 2014<br />
YEAR<br />
2014 2015 2016 2017 2018<br />
ESCALATION RATE 3.00% 4.00% 5.00% 5.00% 5.00%<br />
NOTES:<br />
When using the above Escalation Rates over a number <strong>of</strong> years. These will need to be compounded to show true escalation.<br />
For additional assistance contact:<br />