17.11.2014 Views

BQ_-_14_-_Summer_2014

BQ_-_14_-_Summer_2014

BQ_-_14_-_Summer_2014

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

SERVING<br />

BUSINESS<br />

36<br />

on hold, such as the relocation of a lab support<br />

facility and balanced scorecard implementation.<br />

The compliance projects to address the warning<br />

letter were then themselves prioritized.<br />

When the FDA came for their follow-up site<br />

visit, management now had a list of projects<br />

demonstrating exactly how they would address<br />

every one of the agency’s concerns.<br />

Recipe for Disaster<br />

During his initial interviews with the team, the<br />

project manager quickly realized they were all<br />

rushing toward a cliff. The bulk of the compliance<br />

work was planned to take place during the facility’s<br />

usual summer shutdown. The plant would cease<br />

operations to replace several systems and make<br />

other major fixes, so the timing was ideal. But the<br />

scope of each project was enormous, comprised of<br />

huge lists developed in concert with the corporate<br />

regulatory and quality groups. The project manager<br />

asked the facility team if they’d be able to get all<br />

activities done in the time allotted. The answer:<br />

an unequivocal “no.” But the corporate message<br />

had been “get it done.” No excuses. So the team<br />

committed to doing it, and they’d give it their best<br />

shot.<br />

Evidence-based Solution<br />

To skirt catastrophe, the project manager worked<br />

with the facility team to develop three scenarios:<br />

• Scenario #1: The “schedule” scenario assumed<br />

the facility must complete as much as its<br />

compliance work within the designated summer<br />

shutdown period as possible. Given the<br />

current project scope, what activities would the<br />

team have to remove to provide 100 percent<br />

confidence they could meet the schedule? Result:<br />

They would have to eliminate so many activities<br />

and thus would accomplish so little that they’d<br />

meet none of the regulatory objectives. The FDA<br />

could shut them down.<br />

BioLogical Quarterly <strong>Summer</strong> 20<strong>14</strong><br />

• Scenario #2: The “full scope” scenario was at<br />

the other end of the spectrum. If the team were to<br />

perform every single activity on the project list,<br />

how long would it take? Result: As expected,<br />

it would take many months more than the FDA<br />

would accept and than the business could<br />

maintain supply continuity.<br />

• Scenario #3: The “balanced” scenario was<br />

prioritized based on the regulatory viewpoint.<br />

What were the absolute “must haves” that would<br />

satisfy the FDA’s requirements and prevent a plant<br />

shutdown? What could they wait to do later?<br />

The team assembled that list, and projects were<br />

prioritized into tiers. Next: How long would<br />

it take to perform these projects? Calculations<br />

showed that the shutdown would start slightly<br />

later and last slightly longer than the original<br />

summer shutdown timetable, but the facility could<br />

build up adequate inventory in advance, and<br />

they’d meet the FDA’s timetable.<br />

Building the three scenarios took almost a full<br />

month: gathering data, developing detailed<br />

schedules and identifying resource requirements. It<br />

was time well spent. All scenarios were presented to<br />

corporate management, with the third “balanced”<br />

scenario as the team’s recommendation. The official<br />

corporate response: “It’s a no brainer.”<br />

Tightly Integrated, Fully Orchestrated<br />

To stay within the “balanced” scenario schedule,<br />

every activity had to be carefully coordinated.<br />

The original plan had included four projects. They<br />

were integrated into a single program, led by one<br />

program leader and four sub-project team leads.<br />

The overarching plan had to be extremely detailed<br />

in terms of timing, handoffs and sequential and<br />

parallel activities. Otherwise, at some point,<br />

20 people would suddenly converge into<br />

a five-by-five-foot space to work.<br />

“To stay within the ‘balanced’ scenario<br />

schedule, every activity had to be<br />

carefully coordinated.”<br />

During execution, the program leader and project<br />

managers stayed close to their teams to ensure they<br />

had what they needed to meet the schedule every<br />

day, problem-solving as necessary to keep the<br />

projects on track. Due to frequent communications,<br />

facility and corporate management remained fully<br />

in sync throughout.<br />

Outcome<br />

The facility met its targets, the warning letter<br />

was lifted and a shutdown was avoided.<br />

The organization as a whole improved its ability<br />

to plan and execute complex projects. And the<br />

corporate culture evolved to keep more ahead<br />

of the curve on regulatory compliance.<br />

Tackling difficult<br />

compliance issues is<br />

not easy. But a processdriven<br />

approach provides<br />

an objective framework for<br />

regulatory success.<br />

No missed deadlines.<br />

No failed requirements.<br />

Plenty of matches. <strong>BQ</strong><br />

“The facility met its targets, the warning<br />

letter was lifted and a shutdown was<br />

avoided. The organization as a whole<br />

improved its ability to plan and execute<br />

complex projects.”<br />

Editor’s Note: This article originally appeared in<br />

PharmaVOICE.<br />

BioLogical Quarterly thanks PharmaVOICE for permitting the<br />

republication of Greg Kain’s essay.<br />

Integrated Project Management Company (IPM) is a project<br />

management consulting firm that specializes in the life<br />

sciences industry. Areas of company expertise include<br />

product development, alliance management, business process<br />

improvement, technology transfer, regulatory compliance and<br />

quality assurance. Headquartered in Chicago, IPM has offices<br />

in San Francisco, St. Louis and Boston. Visit ipmcinc.com or<br />

call 630-789-8600. Contact Greg at gkain@ipmcinc.com.<br />

Implementing IPM’s principles can have a calming effect on your organization.<br />

37

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!