BQ_-_14_-_Summer_2014
BQ_-_14_-_Summer_2014
BQ_-_14_-_Summer_2014
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
SERVING<br />
BUSINESS<br />
36<br />
on hold, such as the relocation of a lab support<br />
facility and balanced scorecard implementation.<br />
The compliance projects to address the warning<br />
letter were then themselves prioritized.<br />
When the FDA came for their follow-up site<br />
visit, management now had a list of projects<br />
demonstrating exactly how they would address<br />
every one of the agency’s concerns.<br />
Recipe for Disaster<br />
During his initial interviews with the team, the<br />
project manager quickly realized they were all<br />
rushing toward a cliff. The bulk of the compliance<br />
work was planned to take place during the facility’s<br />
usual summer shutdown. The plant would cease<br />
operations to replace several systems and make<br />
other major fixes, so the timing was ideal. But the<br />
scope of each project was enormous, comprised of<br />
huge lists developed in concert with the corporate<br />
regulatory and quality groups. The project manager<br />
asked the facility team if they’d be able to get all<br />
activities done in the time allotted. The answer:<br />
an unequivocal “no.” But the corporate message<br />
had been “get it done.” No excuses. So the team<br />
committed to doing it, and they’d give it their best<br />
shot.<br />
Evidence-based Solution<br />
To skirt catastrophe, the project manager worked<br />
with the facility team to develop three scenarios:<br />
• Scenario #1: The “schedule” scenario assumed<br />
the facility must complete as much as its<br />
compliance work within the designated summer<br />
shutdown period as possible. Given the<br />
current project scope, what activities would the<br />
team have to remove to provide 100 percent<br />
confidence they could meet the schedule? Result:<br />
They would have to eliminate so many activities<br />
and thus would accomplish so little that they’d<br />
meet none of the regulatory objectives. The FDA<br />
could shut them down.<br />
BioLogical Quarterly <strong>Summer</strong> 20<strong>14</strong><br />
• Scenario #2: The “full scope” scenario was at<br />
the other end of the spectrum. If the team were to<br />
perform every single activity on the project list,<br />
how long would it take? Result: As expected,<br />
it would take many months more than the FDA<br />
would accept and than the business could<br />
maintain supply continuity.<br />
• Scenario #3: The “balanced” scenario was<br />
prioritized based on the regulatory viewpoint.<br />
What were the absolute “must haves” that would<br />
satisfy the FDA’s requirements and prevent a plant<br />
shutdown? What could they wait to do later?<br />
The team assembled that list, and projects were<br />
prioritized into tiers. Next: How long would<br />
it take to perform these projects? Calculations<br />
showed that the shutdown would start slightly<br />
later and last slightly longer than the original<br />
summer shutdown timetable, but the facility could<br />
build up adequate inventory in advance, and<br />
they’d meet the FDA’s timetable.<br />
Building the three scenarios took almost a full<br />
month: gathering data, developing detailed<br />
schedules and identifying resource requirements. It<br />
was time well spent. All scenarios were presented to<br />
corporate management, with the third “balanced”<br />
scenario as the team’s recommendation. The official<br />
corporate response: “It’s a no brainer.”<br />
Tightly Integrated, Fully Orchestrated<br />
To stay within the “balanced” scenario schedule,<br />
every activity had to be carefully coordinated.<br />
The original plan had included four projects. They<br />
were integrated into a single program, led by one<br />
program leader and four sub-project team leads.<br />
The overarching plan had to be extremely detailed<br />
in terms of timing, handoffs and sequential and<br />
parallel activities. Otherwise, at some point,<br />
20 people would suddenly converge into<br />
a five-by-five-foot space to work.<br />
“To stay within the ‘balanced’ scenario<br />
schedule, every activity had to be<br />
carefully coordinated.”<br />
During execution, the program leader and project<br />
managers stayed close to their teams to ensure they<br />
had what they needed to meet the schedule every<br />
day, problem-solving as necessary to keep the<br />
projects on track. Due to frequent communications,<br />
facility and corporate management remained fully<br />
in sync throughout.<br />
Outcome<br />
The facility met its targets, the warning letter<br />
was lifted and a shutdown was avoided.<br />
The organization as a whole improved its ability<br />
to plan and execute complex projects. And the<br />
corporate culture evolved to keep more ahead<br />
of the curve on regulatory compliance.<br />
Tackling difficult<br />
compliance issues is<br />
not easy. But a processdriven<br />
approach provides<br />
an objective framework for<br />
regulatory success.<br />
No missed deadlines.<br />
No failed requirements.<br />
Plenty of matches. <strong>BQ</strong><br />
“The facility met its targets, the warning<br />
letter was lifted and a shutdown was<br />
avoided. The organization as a whole<br />
improved its ability to plan and execute<br />
complex projects.”<br />
Editor’s Note: This article originally appeared in<br />
PharmaVOICE.<br />
BioLogical Quarterly thanks PharmaVOICE for permitting the<br />
republication of Greg Kain’s essay.<br />
Integrated Project Management Company (IPM) is a project<br />
management consulting firm that specializes in the life<br />
sciences industry. Areas of company expertise include<br />
product development, alliance management, business process<br />
improvement, technology transfer, regulatory compliance and<br />
quality assurance. Headquartered in Chicago, IPM has offices<br />
in San Francisco, St. Louis and Boston. Visit ipmcinc.com or<br />
call 630-789-8600. Contact Greg at gkain@ipmcinc.com.<br />
Implementing IPM’s principles can have a calming effect on your organization.<br />
37