<strong>Technical</strong> Specification<br />
ANNEX-<strong>II</strong><br />
Testing <strong>of</strong> the underground <strong>water</strong> pipes<br />
After laying, jointing and anchoring, the pipe shall be slowly and carefully charged with<br />
<strong>water</strong>, so that all air is expelled, allowed to stand full for several days and then tested under<br />
pressure.<br />
A long main shall be tested in sections as the work <strong>of</strong> laying proceeds, and it is an advantage<br />
to leave the joints exposed for inspection during the testing.<br />
The open end <strong>of</strong> the pipe may be temporarily closed for testing under moderate pressure by<br />
fitting a blank flange. The end <strong>of</strong> the pipe shall be secured by struts or otherwise, to assist the<br />
end thrust <strong>of</strong> the <strong>water</strong> pressure in the pipe.<br />
The test pressure shall be applied by means <strong>of</strong> manually operated test pump or, in the case <strong>of</strong><br />
long pipes or pipes large diameter, by a power-driven test pump, which shall be left<br />
unattended. In either case precautions shall be taken to ensure that the required pressure is not<br />
exceeded. Pressure gauges shall preferably be recalibrated before the test.<br />
1.3.2. Above ground <strong>water</strong> pipe<br />
Polyvinyl chloride (PVC) pressure pipes, joints and fittings shall comply with TIS-172523, as<br />
fabricated by Siam Pipe Industry Co., Ltd. or equivalents approved, and comply with the<br />
relevant provisions as set out below:<br />
Water Supply: Class PVC 13.5<br />
All PVC pipes and fittings shall be from a single manufacturer and shall be designed,<br />
fabricated, and installed in accordance with the best practices and methods and shall comply<br />
with these <strong>Specifications</strong>.<br />
Sizes indicated on the Drawings are the nominal sizes.<br />
All PVC pipes and fittings shall be provided with an ultra violet inhibitor.<br />
1.3.3. Pumping system.<br />
Pumping system cover all the pumps set installed in <strong>water</strong> <strong>supply</strong> network to process the<br />
system properly and <strong>supply</strong> <strong>water</strong> to serve all the buildings inside Correction Center 1 (CC1):<br />
- Transfer pump (TP-01/02) with capacity 2x4 l/s <strong>of</strong> flow at 15m <strong>of</strong> head installed at pond<br />
to convey <strong>water</strong> from pond to treat by injecting alum and passing through slow sand filter<br />
to store at underground treated <strong>water</strong> tanks.<br />
- Back wash pump (BP-01) with capacity 8 l/s <strong>of</strong> flow at 30m <strong>of</strong> head installed at pump<br />
room near the elevated <strong>water</strong> tank to back wash the slow sand filter in case the sand filter<br />
not in good condition.<br />
- Transfer pump (TP-03/04) with capacity 2x8 l/s <strong>of</strong> flow at 20m <strong>of</strong> head installed at pump<br />
room near elevated tank to convey <strong>water</strong> from underground treated <strong>water</strong> tanks to elevated<br />
tank to <strong>supply</strong> to distribution network.<br />
Plumbing Works Page: 4