9.14. The Task Planning Template: TASK<br />

The TASK form is first completed in the planning phase and updated every week thereafter.<br />

Things to Check: TASK Form<br />

The first thing to check on the TASK form is that the engineers have produced a sufficiently<br />

detailed plan. No engineer should have tasks that are planned to take more than about ten hours.<br />

If any do, suggest ways to subdivide these tasks and have the team leader get the forms corrected<br />

and review them the next week.<br />

If the team is using the <strong>TSPi</strong> tool, much of the work of completing the TASK form will be done<br />

by the tool. Then all you need to check are that the tasks are properly entered and that the proper<br />

products and phases are identified for each task. Also, examine the actual hours for each<br />

completed task to ensure that the engineers have been properly entering the tasks on the LOGT<br />

forms. Finally, make sure that the engineers entered the week when each task was done.<br />

Interpreting the Data: TASK Form<br />

From the TASK form, you can determine whether the teams have a reasonably balanced<br />

workload or one or more of the engineers is overloaded. After the teams have worked for a week<br />

or so, examine the updated TASK forms to see which students have completed their tasks on time<br />

and which ones are falling behind. The data on the TASK form also show how the team is<br />

progressing and can help you anticipate problems. A typical problem is that one or two engineers<br />

are consistently late and are delaying the entire team. The team leader should then consider<br />

rebalancing the team's workload to reduce the work for these engineers.<br />

Common Reporting Mistakes: TASK Form<br />

If the teams are not using the <strong>TSPi</strong> tool, they must complete the TASK form manually. This<br />

requires that the engineers obtain their time data from the time logs and accumulate these data on<br />

the TASK form against the proper tasks and products. They must also note the week each task<br />

was completed and determine the earned value for each completed task. They generally have a<br />

substantial volume of data, so this is a highly error-prone activity.<br />

General Comments: TASK Form<br />

The TASK form provides a key tool for tracking team progress. It is important that the engineers<br />

complete it correctly and that they update it every week. Examine the TASK forms every week to<br />

ensure that the teams are updating them properly and that the work is proceeding roughly as<br />

planned.<br />

http://www.awl.com/cseng/titles/0-201-47719-X/onlinesupplements/9-14.htm (1 of 2) [11/5/1999 10:31:15 AM]