21.11.2014 Views

LIFE CYCLE COSTING (LCC) for GREEN BUILDING DESIGN

LIFE CYCLE COSTING (LCC) for GREEN BUILDING DESIGN

LIFE CYCLE COSTING (LCC) for GREEN BUILDING DESIGN

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

<strong>LIFE</strong> <strong>CYCLE</strong> <strong>COSTING</strong> (<strong>LCC</strong>)<br />

<strong>for</strong><br />

<strong>GREEN</strong> <strong>BUILDING</strong> <strong>DESIGN</strong><br />

Based on ASTM and ISO<br />

Building Economics Standards<br />

d<br />

Robert P. Charette, Concordia University<br />

1


Objectives<br />

• Present <strong>LCC</strong> analysis based on ASTM<br />

and ISO Building Economics Standards<br />

• Illustrate how <strong>LCC</strong> is used to evaluate<br />

investments in buildings<br />

• Present <strong>LCC</strong> application examples<br />

2


Outline<br />

1. The Notion of Life Cycle Costing<br />

2. Data Requirements<br />

3. Present Value Factors<br />

4. Calculating Life Cycle Costs<br />

5. Supplementary Evaluation Measures <strong>for</strong><br />

Building ud Investments<br />

ets<br />

6. Integrating <strong>LCC</strong> in the Design Process<br />

7. <strong>LCC</strong> Application Examples<br />

3


1. The Notion of<br />

Life Cycle Costing<br />

4


Life-Cycle Cost Analysis<br />

(<strong>LCC</strong>A)<br />

A method of economic analysis that sums<br />

up, over a given study period, all relevant<br />

costs of a building, building system, or<br />

building component, in present value (PV)<br />

dollars, today’s dollar.<br />

5


Initial Cost – Office Building - $100 / SF<br />

Uni<strong>for</strong>mat Categories:<br />

% of Total Building Cost<br />

01 Foundation<br />

3%<br />

02 Substructure<br />

3%<br />

03 Superstructure<br />

04 Exterior Closure<br />

05 Roofing<br />

1%<br />

06 Interior Construc.<br />

07 Conveying System<br />

5%<br />

08 Mechanical:<br />

Plumbing<br />

5%<br />

HVAC<br />

Fire Protection<br />

3%<br />

09 Electrical<br />

11 Equipment<br />

4%<br />

12 Sitework 4%<br />

5% 10% 15% 20%<br />

12%<br />

12%<br />

15%<br />

16%<br />

17%<br />

Source: Means Life Cycle Costing For Facilities<br />

6


Life Cycle Cost – Office Building - $200 / SF<br />

Initial Cost<br />

Operational Cost<br />

Uni<strong>for</strong>mat Categories:<br />

01 Foundation<br />

02 Substructure<br />

03 Superstructure<br />

04 Exterior Closure<br />

05 Roofing<br />

06 Interior Construc.<br />

07 Conveying System<br />

08 Mechanical:<br />

Plumbing<br />

HVAC<br />

Fire Protection<br />

09 Electrical<br />

11 Equipment<br />

12 Sitework<br />

Life Cycle Cost – Present Value $ / ft 2<br />

$2 $4 $6 $8 $10 $12 $14 $16 $18 $20<br />

Source: Means Life Cycle Costing For Facilities<br />

7


Life Cycle Cost Approaches<br />

$/SF<br />

Total $200<br />

$190<br />

-5%<br />

$175<br />

-12.5%<br />

100 $ 85 $<br />

80 $<br />

PV Operational<br />

a<br />

Costs<br />

PV Investment<br />

Costs<br />

100 $ 105 $ 95 $<br />

Conventional<br />

Baseline<br />

Design<br />

Traditional<br />

Options<br />

Green/<br />

Sustainable<br />

Option<br />

8


ASTM Standards<br />

Present Value Factors (4) – E917<br />

SPV<br />

UPV<br />

SPV*<br />

UPV*<br />

Evaluation Measures (4)<br />

NS – E1074<br />

SIR – E964<br />

AIRR – E1057<br />

DPB – E1121<br />

9


2. Data Requirements <strong>for</strong> <strong>LCC</strong><br />

10


Data Requirements <strong>for</strong> <strong>LCC</strong><br />

A. Investment costs<br />

B. OM&R costs<br />

C. Cyclical renewal costs<br />

D. Financial criteria<br />

d – discount rate %<br />

e – escalation rate %<br />

n – study period years<br />

11


3P 3.Present tValue Factors<br />

12


Four Present Value Factors<br />

From Financial Tables<br />

1. SPV - Single Present Value (w/o escalation)<br />

2. UPV - Uni<strong>for</strong>m Present Value (w/o escalation)<br />

3. SPV* - Modified Single Present Value<br />

(with escalation)<br />

4. UPV*- Modified Uni<strong>for</strong>m Present Value Value<br />

(with escalation))<br />

13


Designation: E 917 - 05<br />

Standard Practice <strong>for</strong> Measuring Life-Cycle<br />

Costs of Buildings and Building Systems<br />

Source: The American Society <strong>for</strong> Testing and Materials (ASTM)<br />

14


d= 8% d= 8%<br />

UPV* - Modified Uni<strong>for</strong>m Present Value Factors<br />

Discount Rate d = 8%<br />

Escalation Rates<br />

0% 1% 2% 3% 4% 5% 6% 7% 8% 9% 10% 11% 12%<br />

Year<br />

Year<br />

1 0,926 0,935 0,944 0,954 0,963 0,972 0,981 0,991 1,000 1,009 1,019 1,028 1,037 1<br />

2 1,783 1,810 1,836 1,863 1,890 1,917 1,945 1,972 2,000 2,028 2,056 2,084 2,112 2<br />

3 2,577 2,628 2,679 2,731 2,783 2,836 2,890 2,945 3,000 3,056 3,112 3,170 3,228 3<br />

4 3,312 3,393 3,474 3,558 3,643 3,730 3,818 3,908 4,000 4,093 4,189 4,286 4,384 4<br />

5 3,993 4,108 4,226 4,347 4,471 4,598 4,729 4,863 5,000 5,141 5,285 5,432 5,584 5<br />

6 4,623 4,777 4,936 5,099 5,268 5443 5,443 5,623 5,809 6,000 6197 6,197 6,401 6,611611 6,828 6<br />

7 5,206 5,402 5,606 5,817 6,036 6,264 6,500 6,745 7,000 7,264 7,538 7,823 8,118 7<br />

8 5,747 5,987 6,239 6,501 6,776 7,062 7,361 7,674 8,000 8,341 8,696 9,068 9,455 8<br />

9 6,247 6,534 6,837 7,154 7,488 7,838 8,207 8,593 9,000 9,427 9,876 10,35 10,84 9<br />

10 6,710 7,046 7,401 7,777 8,173 8,593 9,036 9,505 10,00 10,52 11,08 11,66 12,28 10<br />

11 7,139 7,525 7,935 8,370 8,834 9,326 9,850 10,41 11,00 11,63 12,30 13,01 13,77 11<br />

12 7,536 7,972 8,438 8,937 9,469<br />

10,04 10,65 11,30 12,00 12,75 13,55 14,40 15,32 12<br />

13 7,904 8,391 8,914 9,476 10,08 10,73 11,43 12,19 13,00 13,87 14,82 15,83 16,92 13<br />

14 8,244 8,782 9,363 9,991 10,67 11,41 12,20 13,07 14,00 15,01 16,11 17,30 18,59 14<br />

15 8,559 9,148 9,787 10,48 11,24 12,06 12,96 13,94 15,00 16,16 17,43 18,81 20,31 15<br />

15


4.Calculating Life Cycle Costs<br />

16


Life Cycle Cost Convention<br />

PV<br />

Investment<br />

Costs<br />

+<br />

PV<br />

Operational<br />

Costs<br />

All costs in today’s $<br />

17


A - Investment Costs<br />

Today’s Dollar - PV<br />

• Initial Cost – I 0<br />

• Capital Replacement Costs - Rep<br />

• Residual / Salvage Value ± Res<br />

= [ I 0 + Repl ± Res ]<br />

18


B - Operational Costs<br />

Today’s Dollar - PV<br />

• Energy Costs - E<br />

•Operations,Maintenance, & Repair Costs<br />

- OM&R<br />

= [E+OM&R]<br />

19


Example – <strong>LCC</strong> of Competing<br />

Heating / Cooling Systems<br />

• System A: Electric baseboard and<br />

window air conditioner<br />

• System B: Heat Pump<br />

Financial Criteria:<br />

Discount Rate d = 8% Energy Escalation e e = 6%<br />

Maintenance Escalation e m = 5% Study Period n = 15 years<br />

20


System A: Electric Baseboard<br />

and<br />

Window Air Conditioner<br />

‣ Investment Related Costs<br />

Initial Cost – I o $1,500<br />

Replacement Cost Year 8 (Base Yr $) $400<br />

Residual Value (Year 15 $) $150<br />

‣ Operation Related Costs<br />

Base Year Electric Energy Cost $1,200<br />

Base Year OM&R Cost $50<br />

21


<strong>LCC</strong> System A<br />

PV<br />

Investment<br />

Costs<br />

+<br />

PV<br />

Operational<br />

Costs<br />

= $1,772 + $16,156 = $17,927<br />

22


System B: Heat Pump<br />

‣ Investment Related Costs<br />

Initial Cost – I o $3,000<br />

Replacement Cost Year 8 (Base Yr $) $600<br />

Residual Value (Year 15 $) $300<br />

‣ Operation Related Costs<br />

Base Year Electric Energy Cost $820<br />

Base Year OM&R Cost $180<br />

23


<strong>LCC</strong> System B<br />

PV<br />

Investment<br />

Costs<br />

+<br />

PV<br />

Operational<br />

Costs<br />

=$3,384 + $12,798 = $16,182<br />

<strong>LCC</strong> System B $1,745 less or 10% less<br />

24


5. Supplementary Evaluation Measures<br />

25


Supplementary Evaluation Measures<br />

1. Net Savings - (NS) E1074<br />

2. Savings-to-Investment Ratio - (SIR) E964<br />

3. Adjusted Internal Rate of Return - (AIRR) E1057<br />

4. Discounted Payback - (DPB) E1121<br />

26


Example - NS, SIR, AIRR, DPB<br />

Attic Roof Insulation – R11 to R19<br />

Additional Investment Cost – I $1500<br />

Annual Energy Savings – A 0 $260<br />

Financial Criteria:<br />

d = 8% e e = 6% n = 30 yrs<br />

27


Suplementary Evaluation Measures<br />

Additional Investment of $1,500 <strong>for</strong> Insulation<br />

1. Net Savings (NS) $4,420<br />

2. Savings-to-Investment Ratio (SIR) 3.9<br />

3. Adjusted Internal Rate of Return (AIRR) 13%<br />

4. Discounted Payback (DPB) 6.2 years<br />

28


6. Integrating <strong>LCC</strong> in the Design<br />

Process<br />

29


Integrating <strong>LCC</strong> into the Design<br />

Process<br />

30


Integrating g <strong>LCC</strong> in Design<br />

The Problem<br />

• Usually incomplete data at the Schematic Phase<br />

– Design data, cost data, energy data<br />

This data necessary <strong>for</strong> <strong>LCC</strong> calculations<br />

Decisions are virtually irreversible later – no <strong>LCC</strong> possible<br />

• A design management problem !!!!!<br />

- Few if any directives issued requiring this data<br />

at the Schematic Phase of design<br />

31


Part of the Solution<br />

An Integrated Design Process (IDP) with all stakeholders<br />

that includes at the Schematic Phase:<br />

----------------------------------------------------------------------------<br />

• A Baseline Preliminary Project Description (PPD) in<br />

accordance with CSI/CSC Practice FF/180<br />

• An Elemental Cost Estimate With Analytic Parametrs<br />

• An Energy Analysis Simulation Model<br />

32


© The Construction Specifications Institute<br />

Manual of Practice FF/180<br />

Chart 3.4 Preliminary Project Description (PPD)<br />

33


Table 4.3 UNIFORMAT II Elemental Cost Summary <strong>for</strong> Buildings<br />

Project<br />

Example - 8 Story Office Building<br />

LEVEL 2 GROUP ELEMENTS .<br />

Level 3 Elements Quantity Unit Rate Cost<br />

GFA = 54,000.00 SF<br />

Cost per<br />

Unit GFA %<br />

A10 FOUNDATION - - - 69,726.50 1.29 1.60%<br />

A1010 Standard Foundations 6,000.00 SF 7.67 46,025.50 0.85<br />

A1020 Special Foundations - - -<br />

A1030 Slab on Grade 6,000.00 SF 3.95 23,700.00 0.44<br />

A20 BASEMENT CONSTRCUTION - - 75,467.20 1.40 1.70%<br />

A2010 Basement Excavation 2,700.00 CY 5.91 15,960.00 0.30<br />

A2020 Basement Walls 3,840.00 SF 15.50 1.10<br />

B10 SUPERSTRUCTURE - - 688,569.96 12.75 15.80%<br />

B1010 Floor Construction 48,000.00 SF 13.37 641,632.56 11.88<br />

B1020 Roof Construction 6,000.00 SF 782 7.82 46,937.40 40 087 0.87<br />

B20 EXTERIOR ENCLOSURE - - 794,141.00 14.71 18.20%<br />

B2010 Exterior Walls 25,500.00 SF 18.43 469,900.00 8.70<br />

B2020 Exterior Windows 6,600.00 SF 47.58 314,041.00 5.82<br />

B2030 Exterior Doors 5.00 LVS 2,040.00 10,200.00 0.19<br />

. . . . . . . .<br />

34


UNIFORMAT II Links PPD and Design Estimates<br />

Preliminary Project Description:<br />

B<br />

B10<br />

SHELL<br />

SUPERSTRUCTURE<br />

B1010 FLOOR CONSTRUCTION<br />

A. Floor System: Two-hour fire-rated, composite stell beam, steal deck, and<br />

concrete slab system in 20-foot by 25 foot bay dimensions capable of<br />

supporting 75 PSF live load.<br />

B1020 ROOF CONSTRUCTION<br />

A. Roof System: Two-hour fire-rated, composite stell beam, steal deck, and<br />

concrete slab system in 20-foot by 25 foot bay dimensions capable of<br />

supporting 30 PSF live load.<br />

B20<br />

EXTERIOR CLOSURE<br />

B2010 EXTERIOR WALLS<br />

A. Masonry Cavity Wall Construction:<br />

a. Modular face brick installed in running bond with tooled concave<br />

joints.<br />

b. Extruded polystyrene board installed between horizontal masonry<br />

rein<strong>for</strong>cing.<br />

c. Bituminous dampproofing applied over concrete masonry units.<br />

d. Load-bearing concrete masonry units with galvanized horizontal joint<br />

rein<strong>for</strong>ment<br />

e. Concrete masonry unit lintel units over openings; concrete masonry<br />

unit bond beams at top of wall.<br />

Cost Estimate Summary:<br />

Project<br />

Example - 8 Story Office Building<br />

LEVEL 2 GROUP ELEMENTS .<br />

Level 3 Elements<br />

Quantity<br />

A10 FOUNDATION -<br />

A1010 Standard d Foundations 6,000.00<br />

A1020 Special Foundations -<br />

A1030 Slab on Grade 6,000.00<br />

A20 BASEMENT CONSTRCUTION -<br />

A2010 Basement Excavation 2,700.00<br />

A2020 Basement Walls 3,840.00<br />

00<br />

B10 SUPERSTRUCTURE -<br />

B1010 Floor Construction 48,000.00<br />

B1020 Roof Construction 6,000.00<br />

B20 EXTERIOR ENCLOSURE -<br />

B2010 Exterior Walls 25,500.00500 B2020 Exterior Windows 6,600.00<br />

B2030 Exterior Doors 5.00<br />

35


Baseline Energy Simulation<br />

• kWh / SF vs targeted energy budget<br />

• Identify energy drivers<br />

• Identify alternatives to be evaluated<br />

36


Additional Benefits of Schematic<br />

Phase Elemental PPD and Estimates<br />

Can introduce<br />

• Cost risk analysis (Monte Carlo)<br />

• Project risk analysis<br />

• Preliminary construction schedules and<br />

accurate cash flow projections<br />

• Preliminary O&M budgets to optimize <strong>LCC</strong><br />

• Environmental Impact Simulation – Athena / Bees<br />

37


7. <strong>LCC</strong> Green Building Examples<br />

38


Mountain Equipment Co-op<br />

op<br />

39


Mountain Equipment Co-op<br />

Green Building Features<br />

40


Mountain Equipment Co-op, Montreal<br />

Green Building Features<br />

1. Geothermal Heat Pump System<br />

2. Floor Radiant Heating<br />

3. Natural Ventilation<br />

4. Natural Lighting<br />

5. Predictive Control System<br />

6. Solar DHW Panels<br />

7. Waterless Urinals<br />

8. Rainwater Drainage Management<br />

41


Mountain Equipment Co-Op<br />

Area<br />

4,260 M2<br />

Additional Cost $ 475,400<br />

Less Incentives $ 66,300<br />

Net Additional Cost $ 409,100<br />

Annual Savings $104,900<br />

Financial Criteria:<br />

d = 5% e e = 4% n = 30 years r = 5%<br />

42


Mountain Equipment Co-op<br />

op<br />

Additional Investment $ 409,100<br />

DPB<br />

4.0 Years<br />

Net Savings (NS) $2,313,050<br />

SIR 6.65<br />

AIRR 11.8%<br />

43


Centrifugal Chiller VFD<br />

Toronto Area Commercial Office Building<br />

44


<strong>LCC</strong> Centrifugal Chiller VFD<br />

Commercial Office Building<br />

Chiller Capacity<br />

300TR<br />

Operating Period<br />

May-October<br />

Additional Capital Cost $ 30,000<br />

Base Year Energy Saving<br />

($7.50/kWd $0.05/kWh)<br />

$ 5,000<br />

Base Year Additional Maintenance $ 300<br />

Financial Criteria:<br />

d=7% e e =6% e m = 5% n=30 years r = 7%<br />

45


<strong>LCC</strong> Centrifugal Chiller VFD<br />

Commercial Office Building<br />

A. PV Additional Capital Cost $ 30,000000<br />

B. PV Energy Savings<br />

(A o xUPV* = $ 5,000 x 26.02)<br />

$ 130,100<br />

C. PV Additional Maintenance Cost<br />

($ 6,807)<br />

(A o x UPV* = 300 x 22.69)<br />

D. 30 Year PV Savings (B-C) $ 123,293<br />

E. Net Savings – NS (D-A) $ 93,293<br />

F. SIR (D/A) 4.1<br />

G. AIRR 12.2%<br />

46


FAN MOTOR VFD<br />

HVAC System<br />

47


<strong>LCC</strong> – FAN MOTOR VFD<br />

HVAC System<br />

20 HP<br />

100 HP<br />

Annual Operating Hours<br />

3,640<br />

3,640<br />

Additional Capital Cost $ 3,695 $ 10,035<br />

Base Year Energy Savings $ 2,028 $ 7,502<br />

($0.09/kWh)<br />

Additional Annual Maintenance $200 $200<br />

Financial Criteria:<br />

d = 7% e e = 6% e m = 5% n = 30 years r = 7%<br />

48


<strong>LCC</strong> – FAN MOTOR VFD<br />

HVAC System<br />

30 HP 100 HP<br />

A. PV Additional Capital Cost $ 3,695 $ 10,035<br />

B. PV Energy Savings $ 52,769 $ 195,202<br />

C. PV Additional Maintenance ($ 4,538) ($ 4,538)<br />

D. 30 Year PV Savings (B-C) $ 48,230 $ 190,664<br />

E. Net Savings - NS (D-A) $ 44,536 $ 180,629<br />

F. SIR (D/A) 13.1 19.0<br />

G. AIRR 16.5% 18%<br />

49


The Cost and Financial Benefits of Green Buildings<br />

Greg Kats Report For The State of Cali<strong>for</strong>nia<br />

50


The Cost and Financial Benefits of Green Buildings<br />

Greg Kats Report For The State of Cali<strong>for</strong>nia<br />

1. Additional Investment $ 4.00/SF<br />

2. Annual Financial Benefits $2.93/SF<br />

Energy<br />

Emissions<br />

Water<br />

OM&R<br />

Productivity/Health (1% increase)<br />

$ 0.32/SF<br />

$ 0.07/SF<br />

$ 0.03/SF<br />

$ 0.47/SF<br />

$ 2.04/SF<br />

Financial Criteria:<br />

D = 7% e = 5% n = 20 years UPV* = 18.13<br />

51


20 YEAR PV Benefits of<br />

Green Buildings - $/SF<br />

PV Energy $ 5.80 10.9<br />

PV Emissions $127 1.27 24 2.4<br />

PV Water $ 0.54 0.9<br />

PV OM&R $852 8.52 16.0<br />

PV Productivity/Health $ 36.99 70.0<br />

Financial Criteria:<br />

%<br />

$5312 53.12 100%<br />

D = 7% e = 5% n = 20 years UPV* = 18.13<br />

52


The Cost and Financial Benefits of Green Buildings<br />

Greg Kats Report For The State of Cali<strong>for</strong>nia<br />

A. Additional Investment Cost $ 4.00/SF<br />

B. Annual Benefits $ 2.93/SF<br />

C. PV of Benefits A o xUPV*+2.93 x 18.13 = $ 53.12/SF<br />

D. Simple Payback – Years 137 1.37<br />

E. DPB – Years 1.60<br />

F. Net Savings - NS (C - A) $ 48.12/SF<br />

G. SIR (C÷A) 13.0<br />

H. AIRR (r = 7%) 21.5 %<br />

I. IRR (Conventional) 81.5 %<br />

53


Summary<br />

1. The Notion of Life Cycle Costing<br />

2. Data Requirements<br />

3. Present Value Factors<br />

4. Calculating Life Cycle Costs<br />

5. Supplementary Evaluation Measures <strong>for</strong><br />

Building ud Investments<br />

ets<br />

6. Integrating <strong>LCC</strong> in the Design Process<br />

7. <strong>LCC</strong> Application Examples<br />

54


END<br />

Robert Charette, PE, CVS<br />

robert_charette@sympatico.ca<br />

www.lifecyclecosting.org<br />

org<br />

514-739-3522<br />

55

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!