<strong>HERITAGE</strong> <strong>IMPACT</strong> <strong>ASSESSMENT</strong> <strong>OF</strong> N2 – MVEZO VILLAGE LINK ROAD AND BRIDGE, EASTERN CAPE PROVINCE<br />
bridge Abutment A is S31 57 32.55; E28 28 18.07, and bridge Abutment B is S31 57 34.42;<br />
E28 28 20.08.<br />
Alternative 2<br />
Alternative 2 (green route) starts at the same point as described in Alternative 1, but then<br />
heads in an easterly direction until it crosses the Mbashe River. It then either runs north or<br />
south around Nyalara Village until it meets the existing road near Gwatyu Village.<br />
Alternative 3<br />
Alternative 3 (purple route) starts at the N2 near Candu Village and runs in a south easterly<br />
direction through Candu and Ndesi Villages and then crosses the Mbashe River at the same<br />
point described in Alternative 1. The last section of the road follows the same route as<br />
Alternative 1.<br />
On further inspection Alternative 2 has a link that may prove impossible to complete, while<br />
Alternative 3 is a very poor alignment along an escarpment with an increased length of access.<br />
Figure 1. The locations of the proposed Mvezo link road and bridge route alternatives.<br />