05.11.2012 Views

Technical Support Report of Surge Bin Tower - Mine Safety and ...

Technical Support Report of Surge Bin Tower - Mine Safety and ...

Technical Support Report of Surge Bin Tower - Mine Safety and ...

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

FIELD INVESTIGATION<br />

2<br />

On November 15 through 18,2010, Michael Superfesky <strong>and</strong> Anthony Argirakis worked with<br />

Sonia Conway, Metal <strong>and</strong> Norunetal <strong>Safety</strong> <strong>and</strong> Health Inspector, Lexington Field Office, by<br />

providing assistance regarding the safe removal <strong>of</strong> the damaged conveyor <strong>and</strong> bin stlUcture. An<br />

additional40·foot <strong>of</strong> new conveyor truss was installed at the end <strong>of</strong>lhe Overl<strong>and</strong> Conveyor so<br />

that a stable cantilever was established until a new bin structure could be installed. Following<br />

the completion <strong>of</strong> this remedial work, the investigation <strong>of</strong> the <strong>Surge</strong> <strong>Bin</strong> <strong>Tower</strong> collapse<br />

commenced. The removal <strong>and</strong> installation <strong>of</strong> the new conveyor structure provided safe access to<br />

the area with little disturbance to the accident scene. A steady rain on November 16,2010, did<br />

produce a light coating <strong>of</strong> rust on the new fracture surfaces <strong>of</strong> the steel.<br />

MSHA was assisted during the investigation in collecting information <strong>and</strong> accessing the accident<br />

scene by the following Hilltop Basic Resources employees.<br />

John Morgan,<br />

Gary Lewis,<br />

Richard Popham,<br />

Kelly Carver,<br />

Configuration <strong>and</strong> Operation<br />

Vice President Mining Operations<br />

General Manager<br />

Quarry Manager<br />

Team Leader<br />

The <strong>Surge</strong> <strong>Bin</strong> <strong>Tower</strong> was configured with an overall height <strong>of</strong> 54 feet <strong>and</strong> square base 0[20.5<br />

feet per side. Photo 1 shows the <strong>Surge</strong> <strong>Bin</strong> <strong>Tower</strong> approximately 5 years prior to the collapse.<br />

The main structural members <strong>of</strong> the tower consisted <strong>of</strong> four columns with lateral bracing<br />

between the columns, a 2-level orthogonal arrangement <strong>of</strong>fIoor girders hung from the bin walls<br />

at the bottom, <strong>and</strong> stiffened bin walls which acted like plate girders (deep beams). The bin was<br />

square with interior dimensions <strong>of</strong> 20 feet by 20 feet <strong>and</strong> a height <strong>of</strong>28 feet. The bin was<br />

constructed by vertically stacking three prefabricated boxed sections (20 feet by 20 feet) together<br />

<strong>and</strong> bolting the box sections at each interface. The 3/4-inch-diameter bolts used for connecting<br />

tIle box sections were installed through the flange plates located on the top <strong>and</strong> bottom <strong>of</strong> each<br />

box section. The walls <strong>of</strong> each box section (bin walls) consisted <strong>of</strong> 1/4-ineh-thick steel plate<br />

stiffened on 2 foot centers using (non-bearing) steel angle sections with dimensions <strong>of</strong> 5 inches<br />

by 3 inches by 114 ineh. At the corners, the walls <strong>of</strong> the bin framed together at 90 degrees <strong>and</strong><br />

were connected using a 1/4-inch fillet weld placed on the inside. The comers <strong>of</strong> the bin were<br />

stiffened for bearing purposes by welding two vertical steel bars (plates) 6 inches by 114 inch at<br />

90 degrees to each other on the outside corners for the full 28-foot height <strong>of</strong> the bin. With<br />

respect to viewing the top <strong>of</strong> the bin from overhead, each corner <strong>of</strong> the bin, with the steel bar<br />

stiffeners attached, formed a cross. The attachment <strong>of</strong> the steel bar stiffeners to the bin corners<br />

helped in transferring the overall bin load (in bearing) to the columns below. The top <strong>of</strong> the<br />

columns had 3/4-inch-thick filler plates welded between both flanges on each side <strong>of</strong> the<br />

column's web to provide a bearing surface to connect the bottom <strong>of</strong> the bin corners <strong>and</strong> the bar<br />

stiffeners to the column. The bottom <strong>of</strong> the bin corners framed on top <strong>of</strong> the columns such that<br />

they interiorly rested upon one quarter <strong>of</strong> the total area provided by the filler plates <strong>and</strong> the<br />

column's web <strong>and</strong> flanges. Framing the bottom <strong>of</strong> the bin corner within an interior quadrant <strong>of</strong><br />

the column top allowed the steel bar stiffeners to be welded to the top <strong>of</strong> the column. The weld

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!