RAJASTHAN STATE AGRICULTURE MARKETING BOARD, AJMER<br />

Physical & Financial Progress of construction works<br />

Month : November., 2014<br />

<strong>Circle</strong> <strong>Ajmer</strong><br />

(Amt. in lacs)<br />

S. Divison KUMS Head Funded by<br />

Name of work<br />

Adm. Sanction F.S. <strong>2013</strong>- Stp. Date of Actual Date Upto Stage of work / remarks<br />

No.<br />

(KUMS/<br />

Date Amount 14 Compl. of Compl. Date<br />

MDF/<br />

NABARD/<br />

PROJECT/<br />

OTHER)<br />

1 2 3 4 5 6 7 8 9 10 11 12 13<br />

1 <strong>Ajmer</strong> <strong>Ajmer</strong> F&V Yard Work KUMS construction of office building at First Floor 07-05-2010 16.65 17-03-2011 30-09-2011 16.11 Final bill to be paid<br />

2 <strong>Ajmer</strong> <strong>Ajmer</strong> F&V Yard Work KUMS Construction of internal drain & drainage system with 07-05-2010 3.00 17-03-2011 30-09-2011 2.90 Final Bill to be Paid<br />

footpath<br />

3 <strong>Ajmer</strong> <strong>Ajmer</strong> F&V Yard Work KUMS Construction of parking shed near weigh bridge 07-05-2010 10.03 17-03-2011 - 1.33 F.S. Not Recived work stopped<br />

4 <strong>Ajmer</strong> <strong>Ajmer</strong> F&V Yard Work KUMS Construction of cow catcher 07-05-2010 2.00 17-03-2011 30-09-2011 1.59 Final Bill to be Paid<br />

KUMS <strong>Ajmer</strong> F&V Total 31.68 0.00 21.93<br />

5 <strong>Ajmer</strong> <strong>Ajmer</strong> Grain Yard Work KUMS Construction of Inter Locking Concrit Block Between 13-05-2014 29.64 25.48 1/27/2014 14-08-2014 24.86 Finalised<br />

shop and Age of Road Main Mandi yard <strong>Ajmer</strong> Grain<br />

6 <strong>Ajmer</strong> <strong>Ajmer</strong> Grain Yard Work KUMS Construction of Internal road to connect the Agro<br />

Processing Infra Structure from Main Mandi Road<br />

<strong>Ajmer</strong> Grain<br />

7 <strong>Ajmer</strong> <strong>Ajmer</strong> Grain Yard Work KUMS Kishan Kalewa Building at KUMS mandi yard <strong>Ajmer</strong><br />

Grain<br />

8 <strong>Ajmer</strong> <strong>Ajmer</strong> Grain Yard Work KUMS C.G.I. Sheet Roof Covering of Existing Auction<br />

Platform near water hut at main mandi yard KUMS<br />

<strong>Ajmer</strong> (Grain).<br />

9 <strong>Ajmer</strong> <strong>Ajmer</strong> Grain Yard Work KUMS Const. of Internal road Infront of New construction<br />

shops with godown at mandi yard <strong>Ajmer</strong> (Grain).<br />

13-05-2014 80.00 48.00 15-04-2015 - 28.32 Work in Progress<br />

05-06-2014 27.18 27.18 20-04-2015 - 0.13 Work In Progress<br />

16-09-2014 77.00 46.20 - - - NIT due on 23.12.2014<br />

16-09-2014 46.94 46.94 - - - NIT due on 23.12.2014<br />

10 <strong>Ajmer</strong> <strong>Ajmer</strong> Grain Yard Work KUMS Special Repair of Covered Auction platform at Subyard 16-09-2014 15.94 15.94 - - - NIT due on 23.12.2014<br />

Nasirabad Under KUMS <strong>Ajmer</strong> (Grain)<br />

KUMS <strong>Ajmer</strong> Grain Total 276.70 209.74 53.31<br />

11 <strong>Ajmer</strong> Beawar Yard Work KUMS Repair of Staff Quarters in main mandi yard KUMS 07-10-2014 22.78 13.67 - - - NIT to be Invited<br />

Beawar.<br />

12 <strong>Ajmer</strong> Beawar Yard Work KUMS Repair of Check Post (two) with front compound wall in 07-10-2014 6.88 4.13 - - - NIT to be Invited<br />

main mandi yard KUMS Beawar.<br />

13 <strong>Ajmer</strong> Beawar Yard Work KUMS Repair of Agmark Laboraty in main mandi yard KUMS<br />

Beawar.<br />

07-10-2014 12.81 7.69 - - - NIT to be Invited


1 2 3 4 5 6 7 8 9 10 11 12 13<br />

14 <strong>Ajmer</strong> Beawar Yard Work KUMS Repair of Water Hut in F&V Yard KUMS Beawar. 07-10-2014 1.32 0.79 - - - NIT to be Invited<br />

15 <strong>Ajmer</strong> Beawar Yard Work KUMS Repair of Water Storage Tank with pump room in F&V 07-10-2014 2.50 1.50 - - - NIT to be Invited<br />

yard Under KUMS Beawar<br />

16 <strong>Ajmer</strong> Beawar Yard Work KUMS Repair of Existing Drains in F&V Yard Under KUMS 07-10-2014 12.50 7.50 - - - NIT to be Invited<br />

Beawar.<br />

KUMS Beawar Total 58.79 35.28 0.00<br />

17 <strong>Ajmer</strong> Kekri Yard work KUMS Const. of Cow Catcher near main gate of mandi yard 17-09-<strong>2013</strong> 5.00 4.95 22-06-2014 20-06-2014 5.00 Finalised<br />

18 <strong>Ajmer</strong> Kekri Yard work KUMS Const. of CC Pavement work at Open Auction area 17-09-<strong>2013</strong> 125.86 4.28 25-08-2014 29-08-2014 88.03 Finalised<br />

19 <strong>Ajmer</strong> Kekri Yard work KUMS Const of C.C. pavement work at open land office 15-01-<strong>2013</strong> 64.16 - 13-11-<strong>2013</strong> 15-10-<strong>2013</strong> 51.04 Finalised & Price Ex. To be Paid<br />

building near rest house and canteen building<br />

20 <strong>Ajmer</strong> Kekri Yard work KUMS Const of C.C. pavement work bet(auction platform) 15-01-<strong>2013</strong> 31.38 - 13-11-<strong>2013</strong> 15-10-<strong>2013</strong> 24.80 Finalised & Price Ex. To be Paid<br />

21 <strong>Ajmer</strong> Kekri Yard work KUMS Const. of No. 01 Kiosk at sub yard Kadera Under 01-10-2014 1.61 1.61 NIT due on 23.12.2014<br />

KUMS Kekri.<br />

22 <strong>Ajmer</strong> Kekri Yard work KUMS Const. of Office Building at sub yard Kadera Under 01-10-2014 15.23 15.23 NIT due on 23.12.2014<br />

KUMS Kekri.<br />

23 <strong>Ajmer</strong> Kekri Yard work KUMS Const. of 01 No. Water Hut at sub yard Kadera Under 01-10-2014 6.30 6.30 NIT due on 23.12.2014<br />

KUMS Kekri.<br />

24 <strong>Ajmer</strong> Kekri Yard work KUMS Const. of Toilet Block at sub yard Kadera Under 01-10-2014 2.49 2.49 NIT due on 23.12.2014<br />

KUMS Kekri.<br />

25 <strong>Ajmer</strong> Kekri Yard work KUMS Const. of Pipe line work at sub yard Kadera Under 01-10-2014 12.50 12.50 NIT due on 23.12.2014<br />

KUMS Kekri.<br />

26 <strong>Ajmer</strong> Kekri Yard work KUMS Const. of Land Leveling work at sub yard Kadera 01-10-2014 15.00 15.00 NIT due on 23.12.2014<br />

Under KUMS Kekri.<br />

27 <strong>Ajmer</strong> Kekri Yard work KUMS Const. of Pipe line work at main mandi yard Kekri. 01-10-2014 17.50 17.50 NIT due on 23.12.2014<br />

28 <strong>Ajmer</strong> Kekri Yard work KUMS Const. of Welcome Gate No. 1 2 at main mandi yard 01-10-2014 22.00 22.00 NIT due on 23.12.2014<br />

Kekri.<br />

29 <strong>Ajmer</strong> Kekri Yard work KUMS Const. of C.C. Pavement work with drain work back 01-10-2014 58.94 35.36 NIT due on 08.01.2015<br />

side B Block at main mandi yard Kekri.<br />

30 <strong>Ajmer</strong> Kekri Yard work KUMS Const. of C.C. Pavement work with drain work back 01-10-2014 79.99 47.99 NIT due on 08.01.2015<br />

side A Block at main mandi yard Kekri.<br />

31 <strong>Ajmer</strong> Kekri Yard work KUMS Const. of C.C. Pavement work at Subyard Sarwar 01-10-2014 35.32 35.32 NIT due on 08.01.2015<br />

Under KUMS Kekri.<br />

32 <strong>Ajmer</strong> Kekri Yard work KUMS Const. of Covered Auction platform at Subyard Sarwar 01-10-2014 57.00 34.20 NIT due on 23.12.2014<br />

Under KUMS Kekri.<br />

KUMS Kekri Total 550.28 254.73 168.87<br />

33 <strong>Ajmer</strong> Kishangarh Yard work KUMS Labour shed Main mandi yard 11-09-2012 6.19 1.72 18-05-<strong>2013</strong> 28-06-<strong>2013</strong> 4.46 Final bill to be paid<br />

34 <strong>Ajmer</strong> Kishangarh Yard work KUMS S/R of Internal Road in Grain Mandi Yard 30-08-<strong>2013</strong> 103.51 10-06-2014 27-03-2014 90.67 F.S. Not Recived work<br />

35 <strong>Ajmer</strong> Kishangarh Yard work KUMS S/R of Office Building in Main Mandi Yard 30-08-<strong>2013</strong> 14.45 9.85 04-04-2014 07-10-2014 11.50 Finalised


1 2 3 4 5 6 7 8 9 10 11 12 13<br />

36 <strong>Ajmer</strong> Kishangarh Yard work KUMS Const of Cow Catcher Buitification of Main Gate & 30-08-<strong>2013</strong> 8.50 5.77 04-04-2014 07-10-2014 6.79 Finalised<br />

Check Post Main Mandi Yard<br />

37 <strong>Ajmer</strong> Kishangarh Yard work KUMS Const. of Internal Road for Agro Processing Infra 24-09-<strong>2013</strong> 77.61 48.39 31-08-2014 30-09-2014 67.41 Final bill to be paid<br />

Structure<br />

38 <strong>Ajmer</strong> Kishangarh Yard work KUMS Detail Plane Table survey of Main Mandi Yard Campus 22-09-2014 1.50 1.50 - - 0.00 NIT due on 23.12.2014<br />

KUMS Kishangarh.<br />

KUMS Kishangarh Total 211.76 67.23 180.83<br />

39 <strong>Ajmer</strong> Bijaynagar Yard work KUMS S/R. and Beautification of check post and main gate 31-01-<strong>2013</strong> 10.00 6.24 24-11-<strong>2013</strong> 05-03-2014 9.64 Finalised<br />

40 <strong>Ajmer</strong> Bijaynagar Yard work KUMS S/R. of labour shed subyard Gulabpura 31-01-<strong>2013</strong> 14.31 2.32 24-11-<strong>2013</strong> 05-03-2014 11.33 Finalised<br />

41 <strong>Ajmer</strong> Bijaynagar Yard work KUMS S/R. of main gate and Boundary wall subyard Gulabpura 31-01-<strong>2013</strong> 12.00 3.67 24-11-<strong>2013</strong> 05-03-2014 11.15 Finalised<br />

42 <strong>Ajmer</strong> Bijaynagar Yard work KUMS S/R. of boundary wall with fencing work at main mandi 31-01-<strong>2013</strong> 6.65 1.01 24-11-<strong>2013</strong> 05-03-2014 6.65 Finalised<br />

43 <strong>Ajmer</strong> Bijaynagar Yard work KUMS Const & Development of park subyard Gulabpura 31-01-<strong>2013</strong> 9.07 0.88 24-11-<strong>2013</strong> 05-03-2014 8.54 Finalised<br />

44 <strong>Ajmer</strong> Bijaynagar Yard work KUMS S/R. farmenr rest house at subyard Gulabpura 31-01-<strong>2013</strong> 10.65 3.28 24-11-<strong>2013</strong> 05-03-2014 9.85 Finalised<br />

45 <strong>Ajmer</strong> Bijaynagar Yard work KUMS Renewal of Existing drains in Main Mandi Yard, 21-08-<strong>2013</strong> 28.27 3.95 22-03-2014 20-03-2014 24.32 Final bill to be paid<br />

Bijaynagar<br />

46 <strong>Ajmer</strong> Bijaynagar Yard work KUMS Repair of Canteen Building, Grading Lab, Water Hut,<br />

Toilet Blocks, in Main Mandi Yard Bijaynagar.<br />

21-08-<strong>2013</strong> 20.75 6.41 22-03-2014 20-03-2014 20.21 Finilieshed<br />

47 <strong>Ajmer</strong> Bijaynagar Yard work KUMS Construction of Remaining Road Work from front of<br />

office building to new alloted plot for agriculture<br />

marketing & existing road recarpeting in main mandi<br />

Bijay Nagar.<br />

21-08-<strong>2013</strong> 29.65 3.41 28-03-2014 28-03-2014 27.93 Finalised<br />

48 <strong>Ajmer</strong> Bijaynagar Yard work KUMS Construction of Tubewell & Connecting G.I. Pipe Line 21-08-<strong>2013</strong> 8.50 5.51 28-03-2014 2.99 Work Stopped by Contractor<br />

in various buildings at subyard Gulabpura under KUMS<br />

Bijay Nagar.<br />

49 <strong>Ajmer</strong> Bijaynagar Yard work KUMS Const. of Tubewell & CWR in Main Mandi KUMS, 21-08-<strong>2013</strong> 11.00 6.01 28-03-2014 4.99 Work Stopped by contractor<br />

Bijaynagar<br />

50 <strong>Ajmer</strong> Bijaynagar Yard work KUMS Const. of New Drain at Main Mandi Yard KUMS, 21-08-<strong>2013</strong> 27.64 3.43 22-03-2014 22-03-2014 27.57 Finilieshed<br />

Bijaynagar<br />

51 <strong>Ajmer</strong> Bijaynagar Yard work KUMS Const. of CWR in Sub Yard Gulabpura under KUMS, 21-08-<strong>2013</strong> 2.50 0.11 28-03-2014 2.38 Work Stoped by Contractor<br />

Bijaynagar<br />

52 <strong>Ajmer</strong> Bijaynagar Yard work KUMS Supplying & Fixing 10 MT Weight machine with const. 09-07-2014 14.76 14.76 0 NIT to be Invited<br />

Of Platform & Other work in main mandi yard Bijay<br />

nagar<br />

53 <strong>Ajmer</strong> Bijaynagar Yard work KUMS Const Of Kiosk in main mandi yard Bijya nagar. 09-07-2014 1.80 1.80 20-02-2015 0 Work Stoped by Constructor<br />

54 <strong>Ajmer</strong> Bijaynagar Yard work KUMS Laying of GI pipe line in Plot For <strong>Agriculture</strong> marketing 09-07-2014 2.70 2.70 20-02-2015 0.05 Work Stoped by Constructor<br />

Facility area in main mandi yard Bijya nagar.<br />

55 <strong>Ajmer</strong> Bijaynagar Yard work KUMS Repair of Toilet Block in main mandi yard Bijay nagar. 09-07-2014 3.00 3.00 20-04-2015 0 Work in Progress


1 2 3 4 5 6 7 8 9 10 11 12 13<br />

56 <strong>Ajmer</strong> Bijaynagar Yard work KUMS Remaining work of wire fencing with repair of 09-07-2014 38.60 38.60 24-03-2015 3.85 Work in Progress<br />

boundary wall in main mandi yard Bijay nagar.<br />

57 <strong>Ajmer</strong> Bijaynagar Yard work KUMS Repair of covered auction platform in main mandi yard 09-07-2014 26.76 26.76 20-04-2015 0.12 Work in Progress<br />

Bijay nagar.<br />

58 <strong>Ajmer</strong> Bijaynagar Yard work KUMS Const. Of Kiosk in sub yard Gulabpura under KUMS 09-07-2014 3.60 3.60 20-02-2015 0.39 Work Stoped by Constructor<br />

Bijaynagar.<br />

59 <strong>Ajmer</strong> Bijaynagar Yard work KUMS Wire fencing on Ex. Boundary wall Repair in sub yard 09-07-2014 33.80 33.80 24-03-2015 6.68 Work in Progress<br />

Gulabpura under KUMS Bijaynaar.<br />

60 <strong>Ajmer</strong> Bijaynagar Yard work KUMS Const. of Toilet Block in sub yard Gulabpura under 09-07-2014 4.49 4.49 20-02-2015 Work Stoped by Constructor<br />

KUMS Bijaynagar.<br />

61 <strong>Ajmer</strong> Bijaynagar Yard work KUMS Renewal of Existing BT Road in Main Mandi Yard, 09-07-2014 79.97 70.40 24-03-2015 0.89 Work in Progress<br />

Bijaynagar<br />

62 <strong>Ajmer</strong> Bijaynagar Yard work KUMS Const. of C.C. Pavement work in main mandi yard 09-07-2014 79.94 60.04 24-03-2015 56.58 Work in Progress<br />

Bijaynagar.<br />

63 <strong>Ajmer</strong> Bijaynagar Yard work KUMS Repair Of Boundary wall in sub yard Bandanwara under 09-07-2014 19.96 19.96 20-02-2015 0.10 Work in Progress<br />

KUMS Bijaynagar.<br />

KUMS Bijaynagar Total 500.37 326.14 236.21<br />

64 <strong>Ajmer</strong> Nagaur Yard Work KUMS Const. of Covered Tiolet Unit (Ladies) at Main Mandi 10-09-2014 1.80 1.80 NIT due on 23.12.2014<br />

Yard Nagaur.<br />

65 <strong>Ajmer</strong> Nagaur Yard Work KUMS Const. of Kiosk at Main Mandi yard Nagaur. 10-09-2014 2.05 2.05 NIT due on 23.12.2014<br />

66 <strong>Ajmer</strong> Nagaur Yard Work KUMS Const. of Water Hut at Main Mandi Yard Nagaur. 10-09-2014 2.45 2.45 NIT due on 23.12.2014<br />

67 <strong>Ajmer</strong> Nagaur Yard Work KUMS Repairing of Boundary wall sub Yard F&V Nagaur 10-09-2014 7.35 7.35 NIT due on 23.12.2014<br />

Under KUMS Nagaur.<br />

68 <strong>Ajmer</strong> Nagaur Yard Work KUMS Const. of 3 Nos. Covered Toilet Unit (Gents) at Main 10-09-2014 5.40 5.40 NIT due on 23.12.2014<br />

Mandi Yard Nagaur.<br />

69 <strong>Ajmer</strong> Nagaur Yard Work KUMS Repairing of Kiosk at Main Mandi Yard Nagaur. 10-09-2014 0.95 0.95 NIT due on 23.12.2014<br />

70 <strong>Ajmer</strong> Nagaur Yard Work KUMS Improvement of Depretion in C.C. Pavement near 10-09-2014 6.00 6.00 NIT due on 23.12.2014<br />

G,H&I Block Main Mandi Yard Nagaur.<br />

71 <strong>Ajmer</strong> Nagaur Yard Work KUMS Repairing of R.C.C. Covered Auction Platform 3 Nos. at 10-09-2014 25.01 25.01 NIT due on 23.12.2014<br />

Main Mandi Yard Nagaur.<br />

72 <strong>Ajmer</strong> Nagaur Yard Work KUMS Raising of Boundary wall at Main Mandi Yard Nagaur. 10-09-2014 14.41 14.41 NIT due on 23.12.2014<br />

73 <strong>Ajmer</strong> Nagaur Yard Work KUMS S/R of Drainages work at Main Mandi Yard Nagaur. 10-09-2014 38.75 38.75 NIT due on 23.12.2014<br />

KUMS Nagaur Total 104.17 104.17 0.00<br />

74 <strong>Ajmer</strong> Merta City Yard work KUMS Const of 2 Nos Covered Auction Platform in F&V 30-08-<strong>2013</strong> 103.18 23.13 10-06-2014 83.57 Hightension line to be shifted<br />

75 <strong>Ajmer</strong> Merta City Yard work KUMS Drain work at main mandi yard mertacity 25-02-2014 22.95 18.51 27-12-2014 07-09-2014 18.24 Finalised<br />

KUMS Mertacity Total 126.13 41.64 101.81<br />

76 <strong>Ajmer</strong> Degana Yard work KUMS Strengthing Renwal with winding & CC work 11-03-<strong>2013</strong> 38.68 - 12-01-2014 0.68 Wrok Stopped by KUMS<br />

KUMS DEGANA TOTAL 38.68 0.00 0.68<br />

Total of KUMS Work 1898.56 1038.93 763.64


1 2 3 4 5 6 7 8 9 10 11 12 13<br />

77 <strong>Ajmer</strong> Mertacity MDF (Vill. MDF Dholarai Khurd Khetaram Maker House to Sukharam 01-03-2014 4.80 4.80 1/22/2015 3.29 Work all most complete<br />

CC)<br />

Harijan's House<br />

78 <strong>Ajmer</strong> Mertacity MDF (Vill. MDF Dhaneria Dedaram Getla's House to Main Road 01-03-2014 5.60 5.60 1/22/2015 3.96 Work all most complete<br />

CC)<br />

79 <strong>Ajmer</strong> Mertacity MDF (Vill. MDF Karak wall Aam Gavad (Hathai) to Dildarkhan House to 01-03-2014 9.60 9.56 1/22/2015 6.97 Work all most complete<br />

CC)<br />

Mertactiy Main Road<br />

80 <strong>Ajmer</strong> Mertacity MDF (Vill. MDF Kawardi Pole to via Jaskaran Sharma's House to upto 01-03-2014 9.60 9.56 1/22/2015 5.23 Work all most complete<br />

CC)<br />

Mahendra Singh's House<br />

81 <strong>Ajmer</strong> Mertacity MDF (Vill. MDF Liliya Ananad Singh Rathoure's House to up to Main 01-03-2014 4.00 4.00 1/22/2015 2.74 Work all most complete<br />

CC)<br />

Road<br />

82 <strong>Ajmer</strong> Mertacity MDF (Vill. MDF Padukala Main Market (Jain Shab shop) to Main Road 01-03-2014 3.20 3.20 1/22/2015 2.19 Work all most complete<br />

CC)<br />

83 <strong>Ajmer</strong> Mertacity MDF (Vill. MDF Ram Niwas Didel's House (Aam Gawad) to up to Main 01-03-2014 11.20 11.16 1/22/2015 7.85 Work all most complete<br />

CC)<br />

Mandi Road.<br />

84 <strong>Ajmer</strong> Mertacity MDF (Vill. MDF Ram Lal ji Lal Beniwal's house to Bansal Megwal 01-03-2014 16.00 15.94 1/22/2015 12.49 Work all most complete<br />

CC)<br />

House to Main Road<br />

85 <strong>Ajmer</strong> Mertacity MDF (Vill. MDF Sahakar Bhawan to Pemaram Rao Bade to upto Village 01-03-2014 9.60 9.56 1/22/2015 6.58 Work all most complete<br />

CC)<br />

86 <strong>Ajmer</strong> Mertacity MDF (Vill. MDF Segawas Purkharam Bhanwaria's House to Merta Road 01-03-2014 8.00 8.00 1/22/2015 5.49 Work all most complete<br />

CC)<br />

Main Road<br />

87 <strong>Ajmer</strong> Mertacity MDF (Vill. MDF Suriyas (Merta) Jhitia Ugam Ram Raika's House to up 01-03-2014 7.20 7.20 1/22/2015 5.15 Work all most complete<br />

CC)<br />

to Narayan Raika House<br />

88 <strong>Ajmer</strong> Mertacity MDF (Vill. MDF Dangawas Bndharam Lamrod's House to Pawan Teli 01-03-2014 9.60 9.56 1/22/2015 6.82 Work all most complete<br />

CC)<br />

House<br />

89 <strong>Ajmer</strong> Mertacity MDF (Vill. MDF Dotoali Sukharam Jakhad's House to Ganpatdas's House 01-03-2014 9.60 9.56 1/22/2015 8.85 Work all most complete<br />

CC)<br />

to Ranaram Luhar's House<br />

90 <strong>Ajmer</strong> Degana MDF (Vill. MDF Chundia Hariram Fhagodia (Aam Gawad) to Main 01-03-2014 5.20 5.20 1/22/2015 3.68 Work all most complete<br />

CC)<br />

Raod.<br />

91 <strong>Ajmer</strong> Mertacity MDF (Vill. MDF Nemaram Mundel's House to Via Temple to Main Road 01-03-2014 6.00 6.00 1/22/2015 4.31 Work all most complete<br />

CC)<br />

92 <strong>Ajmer</strong> Mertacity MDF (Vill. MDF Netdiay Hari Ram Luhar's House to Padgad and Regaro 01-03-2014 9.60 9.56 1/22/2015 6.62 Work all most complete<br />

CC)<br />

ke baas to Main <strong>Ajmer</strong> Road<br />

93 <strong>Ajmer</strong> Mertacity MDF (Vill. MDF Aam Gawad to (Jivan Ram Sarag) Village outer to 01-03-2014 9.60 9.60 1/22/2015 6.58 Work all most complete<br />

CC)<br />

Arniyala Marg<br />

94 <strong>Ajmer</strong> Mertacity MDF (Vill. MDF Aam Gward to Main Raod 01-03-2014 4.80 4.80 1/22/2015 3.29 Work all most complete<br />

CC)<br />

95 <strong>Ajmer</strong> Mertacity MDF (Vill. MDF Gatia Dr. Mool Singh's House to Via Ajit Singh House 01-03-2014 4.80 4.80 1/22/2015 3.29 Work all most complete<br />

CC)<br />

to Basani Road .<br />

96 <strong>Ajmer</strong> Degana MDF (Vill. MDF Dhanipura Gram Bus stand to Dhanipura common well 01-03-2014 16.00 15.94 11/22/2014 8/20/2014 11.99 Finalised<br />

CC)<br />

97 <strong>Ajmer</strong> Degana MDF (Vill.<br />

CC)<br />

MDF Main Road to Village Kuchera Main Road 01-03-2014 12.00 11.95 11/22/2014 8/20/2014 9.17 Finalised


1 2 3 4 5 6 7 8 9 10 11 12 13<br />

98 <strong>Ajmer</strong> Degana MDF (Vill. MDF Modikalan Village Water Tank to Anganbadi Road 01-03-2014 6.40 6.40 11/22/2014 8/20/2014 4.51 Finalised<br />

CC)<br />

Main Road up to IT Center<br />

99 <strong>Ajmer</strong> Degana MDF (Vill. MDF Nimbola Viswa Village Main Road to Megharam Jat 01-03-2014 8.00 8.00 11/22/2014 8/20/2014 5.91 Finalised<br />

CC)<br />

House<br />

100 <strong>Ajmer</strong> Degana MDF (Vill. MDF Village Bhewda Bus Stand Main Road to IT Center upto 01-03-2014 8.00 8.00 11/22/2014 8/20/2014 5.90 Finalised<br />

CC)<br />

Tehsil Bhavdas.<br />

101 <strong>Ajmer</strong> Degana MDF (Vill. MDF Village Piliya common well to Kabooter Chowk 01-03-2014 4.00 4.00 11/22/2014 8/20/2014 3.04 Finalised<br />

CC)<br />

102 <strong>Ajmer</strong> Degana MDF (Vill. MDF Rawat Khera Village to Sohan Singh Rawat's house to 01-03-2014 4.00 4.00 11/22/2014 8/20/2014 3.04 Finalised<br />

CC)<br />

Main Road<br />

103 <strong>Ajmer</strong> Degana MDF (Vill. MDF Sathana Khurd Village Jujuria ki Dhani to Gawai Dhani 01-03-2014 12.00 11.95 11/22/2014 8/20/2014 8.97 Finalised<br />

CC)<br />

104 <strong>Ajmer</strong> Degana MDF (Vill. MDF Narsinghvasni Village Sainyo Mohella to Gokal 01-03-2014 9.60 9.56 11/22/2014 8/20/2014 7.33 Finalised<br />

CC)<br />

Chowkidar's House to Chawlad Road<br />

105 <strong>Ajmer</strong> <strong>Ajmer</strong> F&V MDF Other MDF Repair of Division office Building 03-10-2012 10.00 3.46 8/20/<strong>2013</strong> 5/2/2014 8.06 Finalised<br />

106 <strong>Ajmer</strong> <strong>Ajmer</strong> Grain Deposit<br />

Works<br />

107 <strong>Ajmer</strong> <strong>Ajmer</strong> Grain Deposit<br />

Works<br />

108 <strong>Ajmer</strong> <strong>Ajmer</strong> F&V Deposit<br />

Works<br />

109 <strong>Ajmer</strong> <strong>Ajmer</strong> F&V Deposit<br />

Works<br />

110 <strong>Ajmer</strong> Beawar Deposit<br />

Works<br />

111 <strong>Ajmer</strong> Kekri Deposit<br />

Works<br />

112 <strong>Ajmer</strong> Mertacity Deposit<br />

Works<br />

113 <strong>Ajmer</strong> Mertacity Deposit<br />

Works<br />

114 <strong>Ajmer</strong> <strong>Ajmer</strong> F&V Deposit<br />

Works<br />

115 <strong>Ajmer</strong> <strong>Ajmer</strong> F&V Deposit<br />

Works<br />

116 <strong>Ajmer</strong> <strong>Ajmer</strong> F&V Deposit<br />

Works<br />

117 <strong>Ajmer</strong> Nagaur Deposit<br />

Works<br />

118 <strong>Ajmer</strong> Nagaur Deposit<br />

Works<br />

Total of MDF Works 238.00 230.92 173.30<br />

<strong>Agriculture</strong> Repair of Wall & Concrit Block in Office Area at ATC 02-01-2014 6.00 6.00 27-10-2014 20-08-2014 5.49 Finalised<br />

Tabigi <strong>Ajmer</strong><br />

<strong>Agriculture</strong> Repair of store (Godown) at Office campus of D.D. 10-03-2014 3.77 3.77 20-12-2014 11-10-2014 3.16 Finalised<br />

(Agro) A.T.C. Tabiji <strong>Ajmer</strong><br />

<strong>Agriculture</strong> Renovation of Fertilizer laboratory Dy. Director agri 14-01-2014 18.03 18.03 27-12-2014 - 11.00 Work in Progress<br />

(Chem.) <strong>Ajmer</strong><br />

<strong>Agriculture</strong> S/R Office Building Dy Dirctor Agri. Ext., <strong>Ajmer</strong> 06-01-2014 2.00 2.00 27-09-2014 14-07-2014 1.81 Finalised<br />

<strong>Agriculture</strong> Const. of Soil Testing Lab at Asst. Dir. Agri. (Ext.) 27-10-2014 21.46 21.46 - - - NIT to be Invited<br />

<strong>Agriculture</strong> Asstt. Dir. (Ext.) Kekri Office under Dy. Dir Agri. (Ext) 23-08-2012 77.93 62.80 25-08-2014 - 51.43 Work in Progress<br />

<strong>Ajmer</strong><br />

<strong>Agriculture</strong> Meeting cum Trainin hall repair & rennovation work of 06-01-2014 10.99 10.99 27-12-2014 - 3.23 Work in Progress<br />

Asst. Dag. (Ext.) Merta city Nagour<br />

<strong>Agriculture</strong> Const. of Soil Testing Lab at Asst. Dir. Agri. (Ext.) 27-10-2014 21.46 21.46 - - - NIT due on 23.12.2014<br />

Pathya<br />

Pustak<br />

Pathya<br />

Pustak<br />

Pathya<br />

Pustak<br />

Pathya<br />

Pustak<br />

Pathya<br />

Pustak<br />

Various repair works of pathya pustak mandal ajmer 15-07-2011 15.20 4.40 5/17/2012 17-05-2012 10.80 Final bill to be paid<br />

C.C. Road 29-03-2012 6.42 0.54 04-03-<strong>2013</strong> 28-02-<strong>2013</strong> 5.88 Final bill to be paid<br />

Parking Shed 29-03-2012 5.93 0.84 04-03-<strong>2013</strong> 28-02-<strong>2013</strong> 5.09 Final bill to be paid<br />

Office building & 4 Nos. godown Nagour 24-01-2012 90.41 39.19 23-11-2012 30-06-2014 51.22 Final bill to be paid<br />

Const of 4 th class residential qtrs. Nagour 24-01-2012 4.20 2.79 23-11-2012 30-06-2014 1.41 Final bill to be paid


1 2 3 4 5 6 7 8 9 10 11 12 13<br />

Total of Deposit Works 283.80 194.27 150.52<br />

119 <strong>Ajmer</strong> <strong>Ajmer</strong> Grain Other RKVY Grading cleaning & Packing Facilities KUMS <strong>Ajmer</strong><br />

(Grain)<br />

10-01-<strong>2013</strong> 100.00 - - - 2.33 NIT invited two times, No.<br />

Agencies are intersted in<br />

processing unit<br />

S/R Rd. Total 640.60 537.21 411.52<br />

Div. <strong>Ajmer</strong> Grand Total 2545.16 1582.14 1179.47<br />

1 Chittorgarh Nimbahera Yard Work KUMS Const. of covered auction plat form at KUMS NBH 09-04-<strong>2013</strong> 39.02 18.09 29-06-2014 27-06-2014 36.27 complete<br />

2 Chittorgarh Nimbahera Yard Work KUMS Const. of CC Road near Garlic platform KUMS NBH. 09-04-<strong>2013</strong> 78.21 29.07 12-09-2014 22-05-2014 75.11 complete<br />

3 Chittorgarh Nimbahera Yard Work KUMS Const. of Various works at S.Y. Kanera pkg 01<br />

4 Chittorgarh Nimbahera Yard Work KUMS Const. of Check post S.Y. Kanera 09-04-<strong>2013</strong> 5.94 5.92 08-06-2014 0.76 Finishing work in Progress<br />

5 Chittorgarh Nimbahera Yard Work KUMS Const. of office Building S.Y. Kanera 09-04-<strong>2013</strong> 10.45 10.40 08-06-2014 1.41 Shuttering in Progress<br />

6 Chittorgarh Nimbahera Yard Work KUMS Const. of kiosk S.Y. Kanera 09-04-<strong>2013</strong> 0.93 0.93 08-06-2014 0.26 Shuttering in Progress<br />

7 Chittorgarh Nimbahera Yard Work KUMS Cont. of Toilet Block S.Y. Kanera 09-04-<strong>2013</strong> 2.79 2.78 08-06-2014 0.43 Finishing work in Progress<br />

8 Chittorgarh Nimbahera Yard Work KUMS Const. of water hut S.Y. Kanera 09-04-<strong>2013</strong> 1.40 1.40 08-06-2014 0.38 Finishing work in Progress<br />

9 Chittorgarh Nimbahera Yard Work KUMS Const. of room for weighting birdge (Dharm kanta) 18-02-2014 2.95 2.95 10-11-2014 0.07 S. S. In Progress<br />

10 Chittorgarh Nimbahera Yard Work KUMS Const. of covered auction plat form at Grain Mandi<br />

Yard NBH<br />

18-02-2014 41.81 41.81 6.07 Column Casting work in<br />

Progress<br />

11 Chittorgarh Nimbahera Yard Work KUMS Const. of Labour shed at main mandi yard Kums NBH 16-05-2014 16.72 16.72 10-01-2015 11.73 Finishing work in Progress<br />

12 Chittorgarh Nimbahera Yard Work KUMS Cons.t of water hut at main mandi yard Kums NBH 16-05-2014 2.05 2.05 10-01-2015 06-10-2014 1.88 Complete & Final<br />

13 Chittorgarh Nimbahera Yard Work KUMS Dismentling of over head tank 19-06-2014 3.5 3.5 06-12-2014 0.04 WIP<br />

14 Chittorgarh Nimbahera Yard Work KUMS Const. of over head tank 19-06-2014 28.00 28.00 06-03-2015 0.06 WIP<br />

15 Chittorgarh Nimbahera Yard Work KUMS Const. of CC road in main mandi yard NBH. 11-09-2014 49.48 49.48 0.00 NIT to be issued<br />

16 Chittorgarh Nimbahera Yard Work KUMS S/R of Farmer Rest House under KUMS NBH 11-09-2014 21.65 21.65 0.00 NIT to be issued<br />

17 Chittorgarh Nimbahera Yard Work KUMS S/R of Garlic P/F at KUMS NBH 11-09-2014 10.06 10.06 0.00 NIT to be issued<br />

18 Chittorgarh Nimbahera Yard Work KUMS S/R & Covering of Existing open auction P/F infront of 11-09-2014 52.17 31.30 0.00 NIT to be issued<br />

Rural Godown KUMS NBH<br />

19 Chittorgarh Nimbahera Yard Work KUMS Const. of Tube Well at main mandi yard NBH. 11-09-2014 4.56 4.56 0.00 NIT to be issued<br />

KUMS Nimbahera Total 371.69 280.67 134.47<br />

20 Chittorgarh Chittorgarh Yard Work KUMS Specials Repair of Internal Road Form Main Gate to<br />

F&V Yard Chittorgarh<br />

17/9/13 38.38 22.83 29-05-2014 17.76 50% work completed this case<br />

under A.C.D.<br />

21 Chittorgarh Chittorgarh Yard Work KUMS Const. of open Auction platform at main mandi yard<br />

KUMS Chittorgarh<br />

54559-64<br />

18.02.11<br />

25.08 19.64 12-09-2014 5.44 C.C. Work in progress


1 2 3 4 5 6 7 8 9 10 11 12 13<br />

22 Chittorgarh Chittorgarh Yard Work KUMS Const. of Wall and Pillar with Gate Between F&V 1387-1425 1.02 1.02 26-09-2014 01-07-2014 0.69 Work complete<br />

Boundary and Grain Yard Boundary KUMS Chittogarh 20.7.11<br />

23 Chittorgarh Chittorgarh Yard Work KUMS Const. of Kisan Bhawan at KUMS Chittorgarh 03-08-2012 112.50 62.36 20-06-2009 28-11-2012 103.65 Work finalised<br />

KUMS Chittorgarh Total 176.98 105.85 127.54<br />

24 Chittorgarh Badisadari Yard Work KUMS S/R of Internal Road with CC pavement SY. Dungla 54559-64 29.94 29.94 15-07-2014 16-05-2014 29.32 Comp.<br />

18.02.11<br />

KUMS Badi Sadari Total 29.94 29.94 29.32<br />

25 Chittorgarh Begun Yard Work KUMS Raising with Barbed wire fencing existing compound 54559-64 16.50 8.13 01-02-2012 10.56 Finishing work in Progress<br />

wall<br />

18.02.11<br />

26 Chittorgarh Begun Yard Work KUMS Drainage System at Mandi Yard 54559-64 19.11 11.38 01-02-2012 9.42 Finishing work in Progress<br />

18.02.11<br />

27 Chittorgarh Begun Yard Work KUMS Covering of existing Auction platfarm 40468-79 34.20 9.96 01-02-2012 27.95 Finishing work in Progress<br />

28.11.11<br />

28 Chittorgarh Begun Yard Work KUMS Const. of Cow Catcher 8.11.12 1.30 1.30 01-02-2012 0.25 Finishing work in Progress<br />

KUMS Begun Total 71.11 30.77 48.18<br />

29 Chittorgarh Pratapgarh Yard Pratapgarh Const. of decorative gate sub yard Chhotisadri 53861-66<br />

28.03.13<br />

11.00 7.73 03-05-2012 3.16 Work Stopped by Contrector<br />

10% panelity imposed<br />

30 Chittorgarh Pratapgarh Yard Pratapgarh S/R & Maintenance of Staff Qtr. 10-01-2014 13.45 11.14 20-03-2014 9.05 Complete<br />

31 Chittorgarh Pratapgarh Yard Work KUMS Construction of Approch Road & Gate at Sub yard 3985 15.56 5.91 08-02-2014 14-05-2014 15.03 Work completed & Final<br />

Chotisadri<br />

6.8.09<br />

32 Chittorgarh Pratapgarh Yard Work KUMS Dismentling of over head tank 18.10.12 3.80 3.80 06-12-2014 0.04 WIP<br />

33 Chittorgarh Pratapgarh Yard Work KUMS Const. of C.C. Pavement Sub Yard Chhoti Sadri 23.17 23.17 22.02.15 2.33 Work not started by contractor<br />

34 Chittorgarh Pratapgarh Yard Work KUMS Const. of CDE Bolock S.Y. Chhoti Sadri 25.08 25.08 22.02.15 2.15 Work not started by contractor<br />

35 Chittorgarh Pratapgarh Yard Work KUMS Const. of Drainage System 15.20 15.20 22.02.15 0 WIP<br />

36 Chittorgarh Pratapgarh Yard Work KUMS R/W for existing covered auction plat farm 7.00 7.00 22.02.15 2.66 WIP<br />

37 Chittorgarh Pratapgarh Yard Work KUMS Const. of C.C. Raod Block 'I' 29.87 29.87 22.02.15 0.07 Work not started by contractor<br />

38 Chittorgarh Pratapgarh Yard Work KUMS Const. of C.C. Raod Block 'J' 29.37 29.37 22.02.15 0.07 Work not started by contractor<br />

39 Chittorgarh Pratapgarh Yard Work KUMS Const. of C.C. Raod Block 'K' 12.15 12.15 22.02.15 0.03 Work not started by contractor<br />

40 Chittorgarh Pratapgarh Yard Work KUMS Const. of Remaining Boundary wall Gate and Check<br />

28.61 28.61 05-01-2015 7.17 Finishing work in Progress<br />

post<br />

KUMS Pratapgarh Total 214.26 199.03 41.76


1 2 3 4 5 6 7 8 9 10 11 12 13<br />

41 Chittorgarh Bhilwara Yard Work KUMS Extension of Chairman Room at office building KUMS 17-09-<strong>2013</strong> 2.84 2.84 05-11-<strong>2013</strong> 03-09-2014 2.72 Complete and to be finalized<br />

Bhilwara<br />

42 Chittorgarh Bhilwara Yard Work KUMS Construction Addition & Alteration work in Labour 17-09-<strong>2013</strong> 6.83 6.83 05-11-<strong>2013</strong> 03-09-2014 5.69 Complete and to be finalized<br />

shed KUMS Bhilwara<br />

43 Chittorgarh Bhilwara Yard Work KUMS Const. of Nalla from Grain mandi centin to jain mandir 17-09-<strong>2013</strong> 14.44 14.44 09-09-2014 7.17 Stoped by contractor<br />

KUMS BHL.<br />

44 Chittorgarh Bhilwara Yard Work KUMS S/R of Auction Platform (Stone Slab roofing ) at mandi 17-09-<strong>2013</strong> 10.30 10.30 14-08-2014 0.09 Withdraw in CI. 32<br />

yard BHL.<br />

45 Chittorgarh Bhilwara Yard Work KUMS S/R of office Building KUMS BHL 17-09-<strong>2013</strong> 8.76 8.76 14-08-2014 0.32 Withdraw in CI. 32 Tender to be<br />

invited<br />

46 Chittorgarh Bhilwara Yard Work KUMS Raising of boundry wall at S.Y. Asind 17-09-<strong>2013</strong> 26.00 26.00 9.36 WIP<br />

47 Chittorgarh Bhilwara Yard Work KUMS Covering of Exisiting Auction platform S.Y. Asind 17-09-<strong>2013</strong> 35.53 35.53 11-09-2014 24.64 Complete and to be finalized<br />

48 Chittorgarh Bhilwara Yard Work KUMS Const. Of compound wall with gate & check post at new 30-08-2012 140.59 80.29 0.00 Tender to be invited<br />

mandi yard paldi kums Bhilwara<br />

49 Chittorgarh Bhilwara Yard Work KUMS Const. Of covering of existing auction platfarm by 24-07-2014 46.06 46.06 0.00 Tender to be invited<br />

R.C.C. Slab subyard kotri kums Bhilwara<br />

50 Chittorgarh Bhilwara Yard Work KUMS Const. Of covering of existing auction platfarm by 24-07-2014 30.00 30.00 0.00 Tender to be invited<br />

R.C.C. Slab subyard Sahapura kums Bhilwara<br />

51 Chittorgarh Bhilwara Yard Work KUMS Const. of decorative gate mandi yard kums Bhilwara. 24-07-2014 50.00 50.00 0.00 Tender to be invited<br />

52 Chittorgarh Bhilwara Yard Work KUMS Const. Of remaining boundary wall at sub yard kotri 24-07-2014 7.00 7.00 0.00 Tender to be invited<br />

53 Chittorgarh Bhilwara Yard Work KUMS Repair of farmer rest house and const. Of toilet block 24-07-2014 9.00 9.00 0.00 Tender to be invited<br />

sub Yard sahapura<br />

54 Chittorgarh Bhilwara Yard Work KUMS repair of office building sub yard Kotri 24-07-2014 8.00 8.00 0.00 Tender to be invited<br />

55 Chittorgarh Bhilwara Yard Work KUMS Const. Of main gate at sub yard sahapura 24-07-2014 22.00 22.00 0.00 Tender to be invited<br />

56 Chittorgarh Bhilwara Yard Work KUMS const. Of hand Pump Sub Yard Sahapura 24-07-2014 1.50 1.50 0.00 Tender to be invited<br />

57 Chittorgarh Bhilwara Yard Work KUMS Const. Of internal C.C. Road sub Yard asind 09-09-2014 250.12 150.07 0.00 Tender to be invited<br />

58 Chittorgarh Bhilwara Yard Work KUMS Const. Of internal C.C. Road sub Yard Sahapura 09-09-2014 231.24 138.74 0.00 Tender to be invited<br />

59 Chittorgarh Bhilwara Yard Work KUMS Const. Of internal C.C. Road sub Yard Kotri 09-09-2014 51.56 30.94 0.00 Tender to be invited<br />

60 Chittorgarh Bhilwara Yard Work KUMS Repair raising and remaining boundary wall sub Yard 09-09-2014 34.05 34.05 0.00 Tender to be invited<br />

Sahapura<br />

61 Chittorgarh Bhilwara Yard Work KUMS Repair raising and remaining boundary wall sub Yard<br />

Banera<br />

09-09-2014 24.75 24.75 0.00 Tender to be invited


1 2 3 4 5 6 7 8 9 10 11 12 13<br />

62 Chittorgarh Bhilwara Yard Work KUMS Repair of office building sub Yard Banera 09-09-2014 8.00 8.00 0.00 Tender to be invited<br />

KUMS Bhilwara Total 1018.57 745.10 49.99<br />

63 Chittorgarh Gangapur Yard Work KUMS Raising of Existing compound wall KUMS Gangapur i- 7 ¼6½ Ñf’k<br />

xzqi&2@03<br />

3-7-06<br />

16.00 16.00 14-08-2014 10.77 WIP<br />

64 Chittorgarh Gangapur Yard Work KUMS Covering of Existing open Auction platform KUMS 1387-1425 62.71 61.23 27-10-2014 45.91 WIP<br />

Gangapur<br />

20.7.11<br />

KUMS Gangapur Total 78.71 77.23 56.68<br />

Total of KUMS Works 1961.26 1468.59 487.94<br />

65 Chittorgarh Bhilwara Yard Work KUMS Const. of cold Storage Unit 27-07-2012 225.00 5.46 30-09-2010 30-04-<strong>2013</strong> 220.11 Comp<br />

Cold Storage Total 225.00 5.46 220.11<br />

66 Chittorgarh Bhilwara <strong>Agriculture</strong> <strong>Agriculture</strong> (1) Maintenance of Office joint director agriculture 26-04-<strong>2013</strong> 12.78 12.78 10-05-2012 02-10-2014 6.50 Work completed<br />

(extension) Bhilwara<br />

67 Chittorgarh Chittorgarh <strong>Agriculture</strong> <strong>Agriculture</strong> (2) Maintenance of staff qtr. for Joint Director 08-10-2012 13.47 13.47 10-05-2012 6.50 Work all most complete<br />

Agriculuture (extension) Bhilwara<br />

68 Chittorgarh Chittorgarh <strong>Agriculture</strong> <strong>Agriculture</strong> Construction of Water pond at ATC Chittorgarh 26-04-<strong>2013</strong> 12.40 12.40 28-03-2014 5.58 Cement mortar Top layer<br />

complete<br />

69 Chittorgarh Bhilwara <strong>Agriculture</strong> <strong>Agriculture</strong> Repair of AD (Ext.) Office Gulabpura 08-10-2012 5.40 5.40 26-10-2014 11-09-2014 3.57 complete & Final<br />

70 Chittorgarh Bhilwara <strong>Agriculture</strong> <strong>Agriculture</strong> Repair of Training hall at (ATMA) BHl. 10-09-<strong>2013</strong> 3.00 3.00 28-03-2014 16-05-2014 2.94 Comp<br />

71 Chittorgarh Bhilwara <strong>Agriculture</strong> <strong>Agriculture</strong> Repair of A.S. Residential Quarter at Asst. Dag. (Ext.) 06-01-2014 2.09 2.09 10-03-2015 0.01 WIP<br />

Kotri.<br />

72 Chittorgarh Bhilwara <strong>Agriculture</strong> <strong>Agriculture</strong> Repair work of A.S. Residential of Asst. Qtr. Of Asst. 06-01-2014 2.94 2.94 10-03-2015 1.38 WIP<br />

Dg. Ext Kotri.<br />

73 Chittorgarh Bhilwara <strong>Agriculture</strong> <strong>Agriculture</strong> Repair work of AAO Residential of Asst. Qtr. Of Asst. 06-01-2014 3.88 3.88 10-03-2015 0.65 WIP<br />

Dg. Ext Kotri.<br />

74 Chittorgarh Bhilwara <strong>Agriculture</strong> <strong>Agriculture</strong> Repair work of Asst. Dag. (Ext.) office building of 06-01-2014 4.38 4.38 10-03-2015 0.69 WIP<br />

Assist. Dag. (ext.) Kotri.<br />

75 Chittorgarh Bhilwara <strong>Agriculture</strong> <strong>Agriculture</strong> Construction of hall at first floor of DY. Dag Office. 28-11-<strong>2013</strong> 19.71 19.71 0.00 NIT to be issued<br />

1 Udaipur Udaipur<br />

Grain<br />

2 Udaipur Udaipur<br />

Grain<br />

3 Udaipur Udaipur<br />

Grain<br />

Deposit works Total 80.05 80.05 27.82<br />

Grand Total Division Chittorgarh<br />

2266.31 1554.10 735.87<br />

Yard Work KUMS Dovelopment of land (Phase I) for purposed Grain 17.09.13 299.88 179.93 25.05.15 40.38 Cutting work in progress<br />

Madni Yard Balicha<br />

Yard Work KUMS Dovelopment of land (Phase II) for purposed Grain 17.09.13 300.30 180.18 25.05.15 27.82 Cutting work in progress<br />

Madni Yard Balicha<br />

Yard Work KUMS Dovelopment of land (Phase III) for purposed Grain 17.09.13 315.00 189.00 25.05.15 169.23 Cutting work in progress<br />

Madni Yard Balicha


1 2 3 4 5 6 7 8 9 10 11 12 13<br />

4 Udaipur Udaipur<br />

Grain<br />

5 Udaipur Udaipur<br />

Grain<br />

6 Udaipur Udaipur<br />

Grain<br />

7 Udaipur Udaipur<br />

Grain<br />

8 Udaipur Udaipur<br />

Grain<br />

9 Udaipur Udaipur<br />

Grain<br />

10 Udaipur Udaipur<br />

Grain<br />

Yard Work KUMS For computerization of gate no. 1 with widening &<br />

const. of sliding gate & small gate with approach C.C.<br />

road<br />

Yard Work KUMS For computerization of gate no. 2 with widening &<br />

const. of sliding gate & small gate with approach C.C.<br />

road<br />

Yard Work KUMS Development of Land near A.D. Office & back side of<br />

shop no. 57 to 64<br />

Yard Work KUMS Development of land back side of Staff Quarter for<br />

demarcation of shops<br />

Yard Work KUMS Fixing of interlocking block in open area & repair of<br />

farmer rest house.<br />

13.05.14 10.02 10.02 29.01.15 4.05 Check post comp. Widening,<br />

gate no. 1 progress. Electric<br />

work in progress.<br />

13.05.14 10.02 10.02 29.01.15 5.76 Check post comp. Widening,<br />

gate no. 2 progress. Electric<br />

work in progress.<br />

13.05.14 4.56 4.56 24.02.15 9.90 80% cutting complete.<br />

13.05.14 28.56 28.56 24.02.15 4.65 Cutting Comp.<br />

13.05.14 7.02 7.02 16.01.15 11.93 Tile work complete progress.<br />

Interlocking work & color in<br />

progress.<br />

Yard Work KUMS S/R of existing open auction platform near gate no. 2 13.05.14 20.84 20.84 09.03.15 0.00 E/W done at road level<br />

hinderance of water level.<br />

Yard Work KUMS Const. of check post, gate & remaining boundary wall at 13.05.14 28.03 28.03 16.03.15 9.13 Masinary work comp. At layout<br />

new mandi yard balicha grain.<br />

given. New layout given after<br />

removal of encroachment in<br />

October. Plaster in progress.<br />

11 Udaipur Udaipur<br />

Grain<br />

12 Udaipur Udaipur<br />

Grain<br />

13 Udaipur Udaipur<br />

Grain<br />

14 Udaipur Udaipur<br />

Grain<br />

15 Udaipur Udaipur<br />

Grain<br />

16 Udaipur Udaipur<br />

Grain<br />

17 Udaipur Udaipur<br />

Grain<br />

18 Udaipur Udaipur<br />

F&V<br />

19 Udaipur Udaipur<br />

F&V<br />

20 Udaipur Udaipur<br />

F&V<br />

Yard Work KUMS Const. of WBM road (40 ft. wide) near A.D. Office. 13.05.14 29.79 29.79 24.02.15 0.06 Cutting in Progesss<br />

Yard Work KUMS Extension (on first floor) & S/R of Office Building 13.05.14 29.91 29.91 16.03.15 0.06 roof laid parapet masonary in<br />

progress. Solar plate to remove.<br />

Yard Work KUMS Barbed wire fencing (Galvanized wire) on boundary<br />

wall from cold house to sheed<br />

13.05.14 2.40 2.40 16.01.15 0.00 Barbed wiring in progress.<br />

Yard Work KUMS Repair & maintenance of staff quarter, const. of Room 13.05.14 17.17 17.17 16.01.15 0.00 Roof laid<br />

with Toilet block (on first floor) & Const. of parking<br />

shed in Sec. Quarter.<br />

Yard Work KUMS Const. of Battery room of Solar system in existing office 06.08.13 3.41 0.71 20.06.13 30.05.14 3.12 Finalized.<br />

building in KUMS (Grain) Udaipur.<br />

Sub Yard KUMS Const. of Tubewell and surface reservoir 28.06.13 6.50 5.38 31.01.14 30.06.14 5.91 Finalized.<br />

Jhadol<br />

Sub Yard KUMS Development of Land (Phase-I) 28.06.13 29.60 11.47 03.12.13 15.01.14 21.05 Finalized.<br />

Jhadol<br />

KUMS Udaipur Grain Total 1143.01 754.99 313.05<br />

Yard Work KUMS Construction of gate and checkpost (2 No.) for proposed 08-11-2012 6.80 6.76 15.05.<strong>2013</strong> 14.07.14 3.93 Finalized.<br />

F&V Yard Balicha<br />

Yard Work KUMS Dovelopment of land (west side) of Entrance for F&V 30.07.<strong>2013</strong> 29.99 12.07 12.04.14 30.05.14 24.09 Finalized.<br />

Yard Balicha<br />

Yard Work KUMS Const. of Remaining Boundary wall at new F&V mandi 14.08.14 7.50 7.50 16.05.15 0.00 E/w in progress<br />

yard Balicha under KUMS F&V


1 2 3 4 5 6 7 8 9 10 11 12 13<br />

21 Udaipur Udaipur Yard Work KUMS Const. of WBM Road from NH-8 to Office Building at 14.08.14 3.85 3.85 16.01.15 2.81 WMB in progress<br />

F&V<br />

new F&V mandi yard Balicha under KUMS F&V<br />

KUMS Udaipur F&V Total 48.14 30.18 30.83<br />

22 Udaipur Rajsamand Yard Work KUMS const. of Third type staff qtr 12.10.12 13.30 6.85 10.10.13 30.03.14 12.64 Finalized<br />

23 Udaipur Rajsamand Yard Work KUMS const of Fourth type staff qtr 12.10.12 20.00 9.66 10.10.13 30.03.14 18.58 Finalized<br />

24 Udaipur Rajsamand Yard Work KUMS Extension of office building 12.10.12 27.95 15.38 10.10.13 30.03.14 12.57 To be finalized<br />

25 Udaipur Rajsamand Yard Work KUMS Const. of Boundary wall at sub yard Amet 15.07.<strong>2013</strong> 28.90 19.01 21.02.14 13.19 Withdraw of remaining work<br />

require to finalize.<br />

26 Udaipur Rajsamand Yard Work KUMS Const. of Auction plateform (160x30) 15.07.<strong>2013</strong> 29.70 21.85 21.02.14 22.08.14 23.19 Finalized.<br />

27 Udaipur Rajsamand Yard Work KUMS Const. of Covered auction platform in subyard Kuraj 15.07.<strong>2013</strong> 27.00 11.13 21.02.14 23.06.14 17.57 Finalized.<br />

28 Udaipur Rajsamand Yard Work KUMS Const. of Drain 14.08.14 29.75 29.75 26.10.14 0.00 Drain concrete work in progress.<br />

29 Udaipur Rajsamand Yard Work KUMS Providing fabricating & erecting retoreflective board in 14.08.14 3.21 3.21 26.10.14 0.00 Fabrication in progress.<br />

KUMS (main mandi)<br />

30 Udaipur Rajsamand Yard Work KUMS Providing fabricating & erecting retoreflective board in 14.08.14 3.80 3.80 26.10.14 0.00 Fabrication in progress.<br />

KUMS (F&V)<br />

31 Udaipur Rajsamand Yard Work KUMS P&F Aluminium grill on (main entrance & windows) at 14.08.14 6.46 6.46 26.10.14 0.00 Layout given<br />

Kisan Bhawan.<br />

32 Udaipur Rajsamand Yard Work KUMS P&F interlocking block at Kishan Bhawan 14.08.14 17.64 17.64 26.10.14 0.00 Interlocking complete<br />

33 Udaipur Rajsamand Yard Work KUMS Interlocking block floor for staff qtr. & Office Building. 14.08.14 19.80 19.80 26.10.14 0.00 E/w in progress<br />

34 Udaipur Rajsamand Yard Work KUMS Const. of Approach road of gate no. 02 & staff qtr. 14.08.14 10.08 10.08 26.10.14 0.00 Approach gate no. 2 is in<br />

progress. E/w for staff qtr.<br />

35 Udaipur Rajsamand Yard Work KUMS Const. of boundary wall around staff qtr. 14.08.14 6.00 6.00 26.10.14 0.00 Masonry in progress.<br />

36 Udaipur Rajsamand Yard Work KUMS Const. of gate, raising of B/w (road side & fixing of 14.08.14 3.94 3.94 26.10.14 0.00 Gate prepared ralling in progress<br />

railing on B/w (front side & road side) of Office<br />

Building.<br />

37 Udaipur Rajsamand Yard Work KUMS Covering of PID by self supporting metal roofing 14.08.14 28.00 28.00 26.10.14 0.00 E/w in progress<br />

without trusses purlin & ancillary support.<br />

38 Udaipur Rajsamand Yard Work KUMS Const. of PID at KUMS F&V 14.08.14 17.17 17.17 26.10.14 0.00 E/w in progress<br />

KUMS Rajsamand Total 292.70 229.73 97.74<br />

39 Udaipur Fatehnagar Yard Work KUMS S/R of Krishi Seva Kendra 08.02.<strong>2013</strong> 3.44 0.20 14.10.<strong>2013</strong> 14.12.13 3.24 To be finalized<br />

40 Udaipur Fatehnagar Yard Work KUMS S/R of Farmers rest house 08.02.<strong>2013</strong> 9.65 2.39 14.10.<strong>2013</strong> 14.12.13 7.26 To be finalized<br />

41 Udaipur Fatehnagar Yard Work KUMS S/R of existing office building 08.02.<strong>2013</strong> 11.40 6.59 14.10.13 29.08.14 4.81 To be finalized after<br />

electification<br />

42 Udaipur Fatehnagar Yard Work KUMS Const. of Boundary wall for new land & Raising of 11.07.<strong>2013</strong> 22.56 13.88 12.03.14 25.11.2014 14.06 To be finalized<br />

Existing B/W<br />

43 Udaipur Fatehnagar Yard Work KUMS Covering strengthening & widening of existing covered 11.07.<strong>2013</strong> 29.85 29.76 21.02.14 30.11.2014 21.74 To be finalized<br />

auction plateform (opp block B)<br />

44 Udaipur Fatehnagar Yard Work KUMS Strengthing and upgradation Internal Road 17.09.<strong>2013</strong> 79.72 29.07.14 30.06.14 57.83 Finalized


1 2 3 4 5 6 7 8 9 10 11 12 13<br />

45 Udaipur Fatehnagar Yard Work KUMS Const. of C.C. Road form Main Gate no 2 to Staff<br />

Quarter<br />

17.09.<strong>2013</strong> 50.15 29.07.14 29.07.14 38.34 To be finalized. Revise F.S.<br />

Require.<br />

46 Udaipur Fatehnagar Yard Work KUMS S/R of existing auction platform (220x30) 'D' Block 17.09.<strong>2013</strong> 47.85 37.10 2.08.14 27.08.14 46.80 Finalized<br />

with G.I. Sheet (Steel truss) covering in front of rest<br />

house<br />

47 Udaipur Fatehnagar Yard Work KUMS S/R of Check Post & modernization of Main Gate 1 & 2 17.09.<strong>2013</strong> 29.59 28.17 25.06.14 27.08.2014 12.04 S/S column hinderence due to<br />

H.T. Line Remove in July. Now<br />

roof laid. C.C. Approach Com.<br />

Check Post finishing in progress.<br />

48 Udaipur Fatehnagar Yard Work KUMS Land Lavelling of Qr. & Development of Park 17.09.<strong>2013</strong> 6.66 3.82 22.03.14 30.08.2014 5.98 Finalized<br />

49 Udaipur Fatehnagar Yard Work KUMS S/R of existing auction platform (158x30)with G.I. 17.09.<strong>2013</strong> 34.37 34.12 09.09.14 26.08.2014 32.22 To be Finalized.<br />

Sheet (Steel truss) covering Subyard Bhinder.<br />

50 Udaipur Fatehnagar Yard Work KUMS S/R of existing auction platform (120x30) with G.I.<br />

Sheet (Steel truss) covering Subyard Vallabhnagar.<br />

17.09.<strong>2013</strong> 26.10 21.16 26.06.14 26.08.2014 26.01 Finalized<br />

51 Udaipur Fatehnagar Yard Work KUMS S/R of Extension of Canteen building. 18.06.14 18.58 18.58 24.05.15 0.25 S/S Masonry in progress.<br />

52 Udaipur Fatehnagar Yard Work KUMS S/R of Dispensary toilet, Interlocking block, GI sheet 18.06.14 8.90 8.90 24.02.15 0.15 Work in progress<br />

covering outside dispensary.<br />

53 Udaipur Fatehnagar Yard Work KUMS S/R of Labour shed 18.06.14 4.37 4.37 24.04.15 0.05 Work in progress<br />

54 Udaipur Fatehnagar Yard Work KUMS Const. Of Office Building Subyard Vallabhnagar. 5.39 5.39 25.04.14 0.35 Finalized.<br />

KUMS Fatehnagar Total 388.58 214.43 271.13<br />

55 Udaipur Banswara Sub KUMS Const. of Boundary wall sub yard Kushalgarh. 08.11.2012 25.60 22.6.13 - 21.91 Finalized.<br />

yardwork<br />

KUMS Banswara Total 25.60 0.00 21.91<br />

Total of KUMS Works 1898.03 1229.33 734.66<br />

56 Udaipur Udaipur<br />

(grain)<br />

Cold Storage NABARD Cunstruction of cold storage 2000 MT capacity 06.08.09 11.00<br />

Coore<br />

for 6<br />

nos.<br />

226.00 30.9.10 30.10.2012 222.64 Finalized.<br />

Total of cold storage 0.00 226.00 222.64<br />

57 Udaipur Udaipur Agri. <strong>Agriculture</strong> Const. of Meeting hall & staff room at first floor Joint 22.10.13 30.00 27.94 12.11.14 16.07 finishing work in progress<br />

Dir. (Ext) <strong>Agriculture</strong>.<br />

58 Udaipur Udaipur Agri. <strong>Agriculture</strong> Various (ext.) renovation work of Office Building 22.10.13 19.70 19.70 12.11.14 15.92 To be finalized.<br />

D.D.Z.P. Udaipur.<br />

59 Udaipur Udaipur Agri. <strong>Agriculture</strong> Const. of Boundary wall at Main Gate work Assistant 25.11.13 3.00 3.00 12.09.14 14.07.14 3.00 Finalized.<br />

Dir. (Ext.) Salumber.<br />

60 Udaipur Udaipur Agri. <strong>Agriculture</strong> Repair & Maintenance work of Office Assistant Dir. 25.11.13 7.00 7.00 12.09.14 14.07.14 6.74 Finalized.<br />

(Ext.) Salumber.<br />

61 Udaipur Rajsamand Agri. <strong>Agriculture</strong> Const. of Meeting Hall D.D. Agri. (Ext.) Z.P.<br />

22.10.13 17.21 17.21 12.11.14 9.17 To be finalized.<br />

Rajsamand.<br />

62 Udaipur Rajsamand Agri. <strong>Agriculture</strong> Const. of Tube Well at STL D.D. Agri. (Ext.) Z.P.<br />

Rajsamand.<br />

22.10.13 4.00 4.00 12.11.14 3.30 To be finalized.


1 2 3 4 5 6 7 8 9 10 11 12 13<br />

63 Udaipur Rajsamand Agri. <strong>Agriculture</strong> Mislaneous Const. work. D.D. <strong>Agriculture</strong> (Ext.) Z.P. 25.11.13 0.91 0.91 12.11.14 0.00 Finishing in progress<br />

Rajsamsnd<br />

64 Udaipur Banswara Agri. <strong>Agriculture</strong> Various (ext.) renovation work of A.D. Agri. (Ext.) 22.10.13 20.75 20.75 27.10.14 6.04 finishing work in progress<br />

Banswara.<br />

65 Udaipur Banswara Agri. <strong>Agriculture</strong> S/R of Distrubuted Joint Director Agri. (Ext.) 20.07.11 10.70 1.65 12.04.14 12.04.14 10.70 Finalized.<br />

66 Udaipur Banswara Agri. <strong>Agriculture</strong> Additional work in Office Building JT. Dir. Udr. TSP 08.10.12 8.50 0.97 12.04.14 12.04.14 8.32 Finalized.<br />

67 Udaipur Dungarpur Agri. <strong>Agriculture</strong> Const. of Soil testing Director Ag. Sagwada Distt.<br />

Dungarpur.<br />

08.10.12 21.46 21.46 0.00 NIT to be received on<br />

12.12.2014<br />

68 Udaipur Udaipur Agri. <strong>Agriculture</strong> Const. of Soil testing Director Ag. Salumber Distt.<br />

Udaipur.<br />

08.10.12 21.46 21.46 0.00 NIT to be received on<br />

12.12.2014<br />

69 Udaipur Banswara Agri. <strong>Agriculture</strong> Const. of Soil testing Director Ag. Bagidora Distt.<br />

Banswara.<br />

08.10.12 21.46 21.46 0.00 NIT to be received on<br />

12.12.2014<br />

70 Udaipur Rajsamand RRPPM RRPPM Const of various works at RRPPM, Rajsmand 21.10.11 129.14 114.54 29.11.12 - 97.23 After 12 Month delay one by one<br />

now main building almost<br />

complete qtr. Finishing in<br />

progress. C.C. road comp.<br />

Boundary gate fixing to be done.<br />

Now compl. To be finalized after<br />

handover.<br />

Total of Deposit Works 315.29 282.05 176.49<br />

Division Udaipur Total 2213.32 1737.38 1133.79<br />

<strong>Circle</strong> <strong>Ajmer</strong> Total 7024.79 4873.62 3049.13<br />

Superintending Engineer<br />

RSAMB <strong>Ajmer</strong>