Working with Acid Sulphate Soils: A Consultant's Perspective
Working with Acid Sulphate Soils: A Consultant's Perspective
Working with Acid Sulphate Soils: A Consultant's Perspective
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
ASS Investigations<br />
TIMING<br />
Fieldwork (generally <strong>with</strong>in 4 weeks/20 days)<br />
Laboratory analysis (generally <strong>with</strong>in 3-4 weeks/say 20 days)<br />
DEC approval of ASSDMP (nominal 45 days)<br />
DoW issue of dewatering licence (nominal 10 days)<br />