Examination Statement<br />

Fur<strong>the</strong>r in<strong>for</strong>mation in support <strong>of</strong> DPD policy <strong>BH3</strong> – Land SE <strong>of</strong> Aiskew<br />

Yuill Homes<br />

This statement provides some in<strong>for</strong>mation in support <strong>of</strong> <strong>the</strong> <strong>allocation</strong> <strong>of</strong> Site <strong>BH3</strong>, South<br />

East <strong>of</strong> Aiskew, to assist in considering <strong>the</strong> questions raised in relation to p<strong>has</strong>ing and<br />

access.<br />

<strong>Background</strong><br />

<strong>Part</strong> <strong>of</strong> <strong>the</strong> <strong>BH3</strong> <strong>site</strong> <strong>has</strong> <strong>been</strong> <strong>promoted</strong> <strong>for</strong> <strong>allocation</strong> <strong>by</strong> Yuill as developer <strong>for</strong> many years,<br />

including to <strong>the</strong> previous Local Plan Inquiry, where <strong>the</strong> Inspector deemed it to be a suitable<br />

<strong>site</strong> <strong>for</strong> housing. However it remained unallocated due to availability <strong>of</strong> sufficient <strong>site</strong>s<br />

elsewhere. A plan showing <strong>the</strong> part <strong>of</strong> <strong>BH3</strong> controlled <strong>by</strong> Yuill is shown at Appendix 1. The<br />

remainder <strong>of</strong> <strong>BH3</strong> comprises <strong>the</strong> <strong>for</strong>mer Hatchery, which is split from <strong>the</strong> Yuill area <strong>by</strong> Blind<br />

Lane, a public right <strong>of</strong> way which is not adopted <strong>by</strong> <strong>the</strong> Highways Authority.<br />

Question: Is <strong>the</strong> p<strong>has</strong>ing <strong>of</strong> both BH2 and <strong>BH3</strong> justified in terms <strong>of</strong><br />

brownfield/greenfield status and are <strong>the</strong>y deliverable as p<strong>has</strong>ed given <strong>the</strong><br />

different ownerships Could <strong>the</strong> detailed access requirements, i.e. <strong>the</strong> loop<br />

layout and provision <strong>of</strong> access to <strong>the</strong> neighbouring <strong>site</strong>, BM2, be implemented<br />

Brownfield/Greenfield<br />

1. It should be pointed out that paragraph 1 on page 26 states that <strong>the</strong> western part <strong>of</strong> <strong>BH3</strong><br />

is in agriculture (pasture) use. This is not <strong>the</strong> case. Approximately one third <strong>of</strong> <strong>the</strong> Yuill<br />

area is a <strong>for</strong>mer nursery (with associated areas <strong>of</strong> hardstanding, structures, tracks etc.).<br />

There is a disused <strong>for</strong>mer tennis court (hardstanding), and <strong>the</strong> remainder is disused<br />

grassland. It <strong>has</strong> not <strong>been</strong> put to any agricultural use <strong>for</strong> many years. Since <strong>the</strong> DPD was<br />

submitted to <strong>the</strong> Secretary <strong>of</strong> State, an additional area <strong>of</strong> land <strong>has</strong> <strong>been</strong> made available to<br />

Yuill at <strong>the</strong> 2 nd access point. This fronts <strong>the</strong> road and comprises 4 holiday cottages and one<br />

residential cottage. These are brownfield uses.<br />

2. There are not many sizeable brownfield options in Aiskew, and indeed none <strong>of</strong> <strong>the</strong><br />

alternatives suggested <strong>for</strong> earlier release are wholly brownfield (or even 50% brownfield) in<br />

area. The proposed p<strong>has</strong>ing <strong>the</strong>re<strong>for</strong>e suggests <strong>the</strong> most sustainable option overall, when<br />

considering o<strong>the</strong>r sustainability matters such as proximity to local amenities and services.<br />

The p<strong>has</strong>ing also considers access and deliverability issues, as set out below.<br />

P<strong>has</strong>ing<br />

3. Given that <strong>the</strong>re are several <strong>site</strong> <strong>allocation</strong>s in Aiskew that abut each o<strong>the</strong>r, it was<br />

suggested that a master plan approach be taken, in order to provide <strong>for</strong> a properly planned<br />

approach to <strong>the</strong> development <strong>of</strong> BH2/<strong>BH3</strong>, where a significant chunk <strong>of</strong> <strong>the</strong> housing<br />

numbers will be delivered. At <strong>the</strong> request <strong>of</strong> <strong>the</strong> Council, Yuill produced a broad master<br />

plan to show how <strong>the</strong> <strong>site</strong>s could link toge<strong>the</strong>r in planning terms.<br />

3. The p<strong>has</strong>ing <strong>of</strong> <strong>the</strong> <strong>site</strong>s reflects <strong>the</strong> master plan approach. Paragraph 3 <strong>of</strong> <strong>the</strong> Allocations<br />

document states:<br />

For reasons <strong>of</strong> access and residential amenity, development should take place first, if<br />

possible [my emp<strong>has</strong>is], on <strong>the</strong> area <strong>of</strong> land currently occupied <strong>by</strong> Aiskew House Farm,<br />

utilising <strong>the</strong> existing access <strong>for</strong> Aiskew House Farm direct from <strong>the</strong> A684….


Upon completion <strong>of</strong> this area <strong>of</strong> <strong>the</strong> <strong>site</strong>, <strong>the</strong> remainder will <strong>the</strong>n be developed. A fur<strong>the</strong>r<br />

access will be gained <strong>by</strong> <strong>the</strong> second access point to <strong>the</strong> A684 through <strong>the</strong> existing frontage<br />

<strong>of</strong> <strong>the</strong> <strong>for</strong>mer Cartman’s Nursery, as indicated on Diagram BH2/<strong>BH3</strong>/BM2. The details <strong>of</strong><br />

this should be agreed between <strong>the</strong> developer and NYCC Highways prior to any<br />

development taking place. Potential access from <strong>the</strong> <strong>site</strong> into <strong>site</strong> BM2 adjacent should also<br />

be accommodated and agreed with NYCC Highways.<br />

(It is assumed that <strong>the</strong> last sentence refers to provision <strong>of</strong> an access from <strong>site</strong> BH2 into<br />

BM2).<br />

4. The above is reflected in policy BH2 and <strong>BH3</strong>, point ii. <strong>of</strong> which states that Site <strong>BH3</strong> will be<br />

delivered in P<strong>has</strong>e 1 (up to 2016) and P<strong>has</strong>e 2. Yuill do not interpret this as meaning that<br />

<strong>the</strong> development <strong>of</strong> <strong>BH3</strong> must proceed rigidly in a west-east direction following <strong>the</strong><br />

completion <strong>of</strong> BH2, but ra<strong>the</strong>r that it is preferred <strong>for</strong> development to occur on BH2 first, if<br />

possible, to get rid <strong>of</strong> an existing amenity problem. The wording <strong>of</strong> <strong>the</strong> policy, in our<br />

interpretation, allows <strong>for</strong> an earlier release <strong>of</strong> <strong>the</strong> Yuill controlled part <strong>of</strong> <strong>BH3</strong> if necessary to<br />

aid delivery, which is why Yuill supported it. The development <strong>of</strong> <strong>the</strong> Yuill part is not reliant<br />

upon completion <strong>of</strong> <strong>the</strong> Hatchery or BH2, because a second (independent) access point<br />

directly into <strong>the</strong> Yuill land is clearly set out in <strong>the</strong> DPD.<br />

5. If any suggestion on improving soundness could be made, it is that <strong>the</strong> policy BH2/<strong>BH3</strong> and<br />

supporting paragraphs 3 and 4 be reworded to provide a little more clarity on this matter,<br />

and also to provide flexibility to allow later-p<strong>has</strong>ed <strong>site</strong>s to be brought <strong>for</strong>ward in <strong>the</strong> event<br />

<strong>of</strong> lack <strong>of</strong> delivery. Delivery would be reviewed annually in <strong>the</strong> SHLAA/AMR.<br />

6. Questions have <strong>been</strong> raised on <strong>the</strong> question <strong>of</strong> access to <strong>the</strong> Hatchery area <strong>of</strong> <strong>BH3</strong> and to<br />

<strong>the</strong> Pig Farm at BH2. At present, we believe <strong>the</strong>re is no legal right <strong>of</strong> access (<strong>for</strong><br />

development) to <strong>the</strong> Hatchery along Blind Lane, and we believe it will have to be accessed<br />

ei<strong>the</strong>r via <strong>the</strong> Yuill <strong>site</strong> (across Blind Lane) or via <strong>the</strong> Pig Farm. Both require negotiations<br />

yet to be concluded, but it is our opinion that <strong>the</strong> policy p<strong>has</strong>ing (with a little<br />

clarification/flexibility as suggested above) allows <strong>for</strong> this issue to be dealt with.<br />

7. A master plan approach to developing adjacent <strong>site</strong>s is sound planning policy, and this can<br />

still be achieved in design terms even if <strong>the</strong>y are split into p<strong>has</strong>es with <strong>the</strong> middle section<br />

possibly coming last. In this case it would be possible to take a pincer approach to<br />

development, with <strong>the</strong> early p<strong>has</strong>es designed both to be stand-alone developments or parts<br />

<strong>of</strong> a potentially larger overall development.<br />

8. In terms <strong>of</strong> access, our transport consultants, White Young Green, held discussions with<br />

NYCC during <strong>the</strong> LDF promotion. These culminated in submission in 2007 <strong>of</strong> access design<br />

options to NYCC. These demonstrated that a satisfactory access from <strong>the</strong> A684 can be<br />

achieved at <strong>the</strong> western part <strong>of</strong> <strong>BH3</strong>, at <strong>the</strong> second access point. The options <strong>for</strong> this<br />

include a simple priority junction, mini-roundabout or traffic signal controlled junction. All<br />

are possible on land controlled <strong>by</strong> Yuill and all are equally acceptable to Yuill. An email from<br />

NYCC Highways confirmed that access geometry is not an issue, and this is shown at<br />

Appendix 2.<br />

9. It should be noted that, since Submission, <strong>the</strong> owners <strong>of</strong> <strong>the</strong> cottages at Cartmans Nursery<br />

(fronting <strong>the</strong> road) have decided <strong>the</strong>y wish to leave when <strong>the</strong> development starts, so <strong>the</strong>y<br />

have also made this additional property available to Yuill. This provides fur<strong>the</strong>r scope in<br />

terms <strong>of</strong> <strong>the</strong> second access point. This is arguably <strong>the</strong> best point along <strong>the</strong> A684 <strong>for</strong><br />

accessing <strong>the</strong> development land behind.


10. Although any application would need to be accompanied <strong>by</strong> an up-to-date Transport<br />

Assessment, it is clear that providing a satisfactory access point into <strong>the</strong> Yuill controlled<br />

area <strong>of</strong> <strong>BH3</strong> is not an issue. The master plan included a loop road arrangement, which was<br />

advised <strong>by</strong> NYCC at <strong>the</strong> time as <strong>the</strong> most appropriate <strong>for</strong> a large development from a single<br />

access point. The master plan was designed to ensure that <strong>the</strong> Yuill part could be delivered<br />

ei<strong>the</strong>r as a stand-alone development, or a first p<strong>has</strong>e <strong>of</strong> a larger area, with potential<br />

extensions to <strong>the</strong> loop road across Blind Lane to <strong>the</strong> Hatchery (in later p<strong>has</strong>es), ultimately<br />

joining up with <strong>the</strong> Pig Farm and BM2.<br />

11. Yuill do not control <strong>the</strong> o<strong>the</strong>r areas <strong>of</strong> <strong>the</strong> master plan, or Blind Lane, which are in different<br />

ownerships. However, it is our opinion that <strong>the</strong> proposed p<strong>has</strong>ing policy allows <strong>for</strong> <strong>the</strong> early<br />

development <strong>of</strong> <strong>the</strong> Yuill part <strong>of</strong> <strong>BH3</strong> in p<strong>has</strong>e 1, and time <strong>for</strong> negotiations with regard to<br />

access to <strong>the</strong> Hatchery <strong>for</strong> development in p<strong>has</strong>e 2.<br />

12. In conclusion, given that <strong>the</strong> Yuill-<strong>promoted</strong> part <strong>of</strong> <strong>BH3</strong> is suitable, available and<br />

deliverable, and that access is not an issue, we believe that its inclusion in Policy <strong>BH3</strong><br />

p<strong>has</strong>e 1 is sound.<br />

* * * * *<br />

APPENDICES:<br />

APPENDIX 1: PLAN SHOWING YUILL LAND WITHIN <strong>BH3</strong> AND WIDER MASTER PLAN AREA<br />

APPENDIX 2: EMAIL FROM NYCC re. SITE ACCESS<br />

Louise Nicholson, Planning Manager, Yuill Homes, Cecil House, Loyalty Road, Hartlepool TS25 5BD