Annex 5: Categorization of Audit Findings by Risk Severity<br />
In addition to explaining and giving details about the “Effect, potential impact or risk” in the text of<br />
an audit observation, UNDP requires that the auditor also identifies the risk level in the audit report<br />
by using one of the following 3 pre-established risk levels:<br />
High<br />
Medium<br />
Low<br />
Action that is considered imperative to ensure that UNDP is not exposed to high<br />
risks (i.e. failure to take action could result in major consequences and issues).<br />
Action that is considered necessary to avoid exposure to significant risks (i.e. failure<br />
to take action could result in significant consequences).<br />
Action that is considered desirable and should result in enhanced control or better<br />
value for money.