Dartmouth Street Sewer Repair<br />

The 43-year-old sewer line that crosses Dartmouth Street near Costco is<br />

broken and requires repair. The break is located under concrete pavement<br />

and cannot be easily excavated and repaired without affecting traffic for<br />

several weeks. This project may require alternative trenchless technology so<br />

that traffic impacts can be minimized.<br />

Dartmouth Street Sewer Repair<br />

Location<br />

Dartmouth Street<br />

Funding Status<br />

Fully Funded<br />

Project Manager(s)<br />

Ted Kyle<br />

Public Works<br />

EXTERNAL EXPENSES<br />

Actual<br />

2009 – 10<br />

Revised<br />

2010 – 11<br />

Projected<br />

2010 – 11<br />

2011 – 12 2012 – 13 2013 – 14 2014 – 15 2015 – 16<br />

PROJECTED<br />

TOTAL<br />

Design and Engineering 0 0 0 $40,000 0 0 0 0 $40,000<br />

Construction 0 0 0 $200,00 0 0 0 0 $200,00<br />

INTERNAL EXPENSES<br />

TOTAL 0 0 0 $240,000 0 0 0 0 $240,000<br />

Project Management 0 0 0 $20,000 0 0 0 0 $20,000<br />

Construction Management 0 0 0 $30,000 0 0 0 0 $30,000<br />

TOTAL 0 0 0 $50,000 0 0 0 0 $50,000<br />

TOTAL PROJECT EXPENSE 0 0 0 $290,000 0 0 0 0 $290,000<br />

REVENUE FUNDING SOURCE<br />

Sanitary Sewer Fund 0 0 0 $290,000 0 0 0 0 $290,000<br />

TOTAL 0 0 0 $290,000 0 0 0 0 $290,000<br />

OTHER REVENUE SOURCE 0 0 0 0 0 0 0 0 0<br />

TOTAL 0 0 0 0 0 0 0 0 0<br />